Which information could be recorded on an ‘empathy map’ for the marketing staff?
Which 2 statements explain why the Architecture Angels ' Chief Accountant would be an appropriate Business Ambassador?
The Applications Manager, who is already very busy, is proposed as a Change Agent.
Which action by the Change Manager is MOST likely to make this department ' s change agent role effective?
Sales staff are unhappy that they have been told that they will lose the Sales relaxation area completely to make space for the new Selco staff. The Sales staff are considering consulting their Union about escalating their discontent.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-
rounds of the new bedroom and en-suite bathroom facilities throughout the project.
Is this an appropriate application of Agile Project Management for this project?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to ' install a heat reclamation system ' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to " temporarily weatherproof the roof " should NOT be set until Solution Development Timebox A.
Is this an appropriate approach to setting high-level acceptance criteria?
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.


The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.
Which information is MOST likely to be relevant for the change agents when being inducted into the change programme for the Operational delivery processes workstream?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.
On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be ‘hot-desks,’ not used by staff permanently based in the office.
Is this an appropriate approach to reward the brain in the need for ‘certainty,’ and why?
Which is the BEST reason to remind learners of related knowledge or skill they already possess?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 Sales Team Leaders (TL) are likely to be the line leaders MOST engaged in implementing change, based on the actions that have occurred to date?
Which statement should be recorded under the High-level change approach heading?
Which 2 actions should the Workshop Facilitator take to implement the new
Must Have requirement?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
The Change Manager has read Goleman ' s articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that
leadership style can improve organizational culture and performance as measured by staff surveys.
Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the
organization.
Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each
recommendation in Column 1, select from Column 2 the ' dimension ' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be
used once, more than once or not at all.


Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager

Which 2 statements represent appropriate entries for the plan for Post-Project
activities?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
Which 2 actions should the Team Leader take to implement the new Must
Have requirement?
The Web Content Manager has provided the Web Developer with a mock up
of the ' Contact Us ' page, to be created for the new coffee bar insurance
product. When producing the code, the Web Developer has created a button
that reads ' Delete ' instead of ' Cancel ' .
What action should the Web Content Manager take?
The Business Ambassador assigned to the project is only available 2 days a
week. The Project Manager has stated that the Investigation stage for each
Timebox should, where possible, be planned around the availability of the
Business Ambassador.
Is this an appropriate application of the DSDM lifecycle?
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
' all members of the project understand and accept the DSDM approach ' .
What action should the Project Manager take?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what
needed to be done before these would be acceptable.
Is this an appropriate application of Agile Project Management for this project?
Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.

Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)
During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,
controlled and evidenced.
Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(During the meeting, Mira Bachar asked Sukra Aroon which AgilePM project artifacts should use to provide an auditable record of compliance requirements throughout Project Increment 4.
Based on AgilePM guidance, which of the following is an appropriate response?)
(Lee Tan, General Manager of EPR Southeast Asia, is serving as a Business Advisor during Project Increment 4. He has not attended any Sprint Reviews, calling them " project meetings " and " a waste of time. " He later complains to Sarah about the lack of project awareness.
Which of the following actions reflects an AgilePM approach?)
(Which one of the following actions should Hira take to balance the benefit of agile leadership whilst ensuring alignment of the Project Increment with project objectives?)
(Brinda Vyas has been absent for two weeks, leaving Mira Bachar and the Delivery Teams to make decisions. Recent strategic adjustments haven ' t been communicated to the Delivery Teams causing frustration and risk of rework.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which one of the following statements does NOT align with AgilePM ' s MoSCoW prioritization?)
During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,
controlled and evidenced.
Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(During the meeting, Wanida Anong shared specific safety and hygiene standards associated with the water used for Hydrotherapy treatments. Water quality needs to be monitored to ensure it meets specific safety and hygiene standards.
Which of the following approaches balances agility with compliance?)
(At a Sprint Review, Brinda Vyas realized that guest luxury has been prioritized over sustainability, creating misalignment with the project vision.)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(It is appropriate that the Delivery Team Leaders attend this Project Sprint Planning Event?)
(During Sprint Planning, the Delivery Team identifies a potential risk in integrating Spa systems with the resort ' s client management system.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
(In the Ecolodge Panthera Resort (EPR) Project, answer the following questions about risk management.
In addition to the Developers, the teams include:
Mira Bachar (Guest Services Manager) – Product Owner for both Delivery Teams
Lee Tan (General Manager) – Business Advisor
Brinda Vyas – Business Visionary
Hira – Project Manager
Sukra Aroon – Solutions Architect
Wanida Anong – Regulatory Compliance Manager
Sarah Lark – Business Sponsor
Priya – Business Advisor
Select 2 answers to each question.
Which 2 statements describe the application of AgilePM ' s approach to managing risk?)
(Brinda believes that a meditation garden is essential for the holistic wellness experience, but Sukra, the Solution Architect, warns of risk associated with cultivating and maintaining the required plants.
How should Hira resolve this?)
AgilePM |