Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?
In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?
In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?
Choose all of the correct answers (multiple possibilities)
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?
The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?
Choose all of the correct answers (multiple possibilities):
Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).
Which of the following statements are not correct? [2017 Edition]
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?
What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers — multiple possibilities)
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)
Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?