(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.
Which of the following form a Contractor ' s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(Regarding the FIDIC Red Book (edition 2017): what two answers provide for requirements regarding a notice and other communication?
Choose all of the correct answers (multiple possibilities).)
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers — multiple possibilities)
(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?
Choose all of the correct answers (multiple possibilities).)
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
(Under the FIDIC Red, Yellow, and Silver Books (edition 1999), which of the following entitlements of the Employer can result in a deduction of the Contract Price and Payment Certificates subject to Sub-Clause 2.5? (2 correct answers apply))
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?
If a FIDIC Red, Yellow, or Silver Book (edition 2017) is applied, in which of the following two cases is the Contractor required to submit a revised programme?
Choose all of the correct answers (multiple possibilities).
Towards the end of implementing a varied work (initiated originally by the Contractor as a " Value Engineering Proposal " , relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]
Choose all of the correct answers (multiple possibilities).
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?
Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?
Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)
The procurement process of a project executed based on any FIDIC Contract model is exactly the same in terms of definitions, time and steps, which makes it universal and more easy to use worldwide. Is this statement true or false?
Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?
Choose all of the correct answers (multiple possibilities).
(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
(FIDIC Red Book (edition 2017) stipulates that the measurement shall be made as per the actual quantities executed at Site. Which one of the following statements is correct?)
Under the FIDIC Construction Contract, which one of the following statements is correct?
Which two statements are true under the FIDIC Red Book (edition 1999)?
(Choose all of the correct answers — multiple possibilities)
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)
Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)
A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?
Choose all of the correct answers (multiple possibilities)