The programme manager has analysed the costs of using an expert external company to work on the Research and Development Project. Although using the external experts is likely to produce a higher quality solution which would lead to increased organizational adoption, the SRO has insisted that the project only uses internal staff to minimize costs.
Is the SRO's response an appropriate application of the ‘deploy diverse skills' principle, and why?
The programme is now in the ‘close the programme’ process. All the planned training from the Training Project has been completed. However, it is too early to tell how much impact the training will have on service to customers. This will need to be monitored during normal business operation.
Which theme is MOST relevant to this situation?
The programme is in the ‘design the outcomes’ process. One risk to the programme is that new and improved meter technology may be developed during implementation. This risk has been assessed as high probability and high impact and is therefore a high priority. The initial delivery approach proposes a phased roll-out of the meters so that the programme can exploit any new technology that emerges. The CTO has been appointed as the owner of this risk.
Is this appointment an appropriate application of the identify and prioritize risks’ activity, and why?
The CFO has specified the need to calculate the Net Present Value (NPV) to demonstrate the return on investment for the programme. How should the resulting benefit be expressed?
The programme is in the ‘deliver the capabilities’ process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.
Which theme is MOST relevant to this situation, and why?
Through which document programmes establish the context in which risks will be identified and assessed and responses planned and implemented?
The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.
Is this an appropriate application of the structure' theme, and why?
The Training Project has included some interactive games in the training materials. This is to help engineering staff members share ideas and experiences during the training of how to apply the new processes. However, the CEngO thinks that the engineering staff members will find this approach rather childish as they are very experienced and normally work independently. As a result, the CEngO has asked for the games to be removed from the training materials.
Is the CEngO's request an appropriate application of the 'knowledge' theme, and why?
Which of the following is Not one of MSP defined levels of stakeholder engagement?
The Customer Processes Project has reported that the work to develop the integrated billing and accounting services is progressing according to plan. However, when the system was tested, the system performance was very slow and there are errors that were not previously identified. The programme manager is concerned about the possible impact of this inaccurate reporting.
Which type of data gathering should be improved, and why?
Which one of below options is the delivery mechanism for 'stakeholder engagement'?
The programme has just started. One outcome will be that fewer staff need to work as meter readers. The CEO of UU is keen to make the redundancy process as smooth as possible for the affected staff. As a result, the CEngO is attending a meeting with the meter readers to discuss UU’s plans for the future, as well as the different redundancy and early retirement packages.
Is this an appropriate application of the 'lead with purpose' principle?
The Employment Contracts Project in Tranche 1 will identify the skills needed by sales staff. However, the Customer Processes Project in Tranche 2 will define new ways to sell gas and electricity to existing water customers which may result in changes to the previously defined skills requirements. If any rework is required, this would delay increasing the number of electricity and gas customers. The programme manager has set up a process to independently monitor the situation, so they can be warned immediately if this becomes likely to happen.
Which principle is being applied MOST by the programme manager when implementing the independent monitoring, and why?
One of the outcomes from the programme is 'customers buy package deals'. However, this outcome cannot be fully achieved until the end of Tranche 3 when training for the call centre staff is complete. Some senior managers think that this could be delivered more quickly, but the Call Centre Manager does not want their staff members affected by too many changes at the same time, so that they can continue to meet the needs of existing customers. The programme manager has designed the tranche structure to take this into account.
Is this tranche design an appropriate application of the 'bring pace and value' principle, and why?
Which type of cost is associated in training, moving and supporting an operational unit?
The programme has successfully completed all projects and work according to the delivery plan and is in the ‘close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.
Which role should be responsible for managing these activities?
The Department of Utilities Oversight (DOUO) is the regulating body overseeing utility companies in the region. The regulator has advised UU that they are concerned there will be a lack of competition in the industry, once UU sales are increased. UU has contacted both the DOUO and other water companies in the region to work on identifying solutions that would be practical for everyone.
Is this an appropriate application of the 'collaborate across boundaries' principle, and why?
The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
The programme is halfway through the first tranche. The CRO has contacted the programme manager with exciting news. They have been shown a new piece of technology which makes it easier and cheaper to service and maintain smart meters. They think that it might be possible to add this technology to future smart water meter installations without much additional cost. The programme manager has added this to the risk register.
Is this an appropriate application of the design' theme, and why?
MSP |