PgMP Program Management Professional (PgMP) Questions and Answers

Questions 4

A program manager concurrently implements a software program at four client locations. The client’s objective is to maintain quality while shortening the software implementation timeline.

What key elements should be included in the benefits register to achieve this goal?

Options:

A.

Plans for tracking and communicating risks associated with the program

B.

Plans for conducting program quality assurance and control on a regular basis

C.

Plans for program schedule control to meet the shorter timeline

D.

Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits.

Buy Now
Questions 5

An organization is considering a new program. The business analyst believes that the benefits to the organization would equate to $1,550,000 in five years. If the rate of return for this program is six percent what is the maximum amount the organization should invest in this program?

Options:

A.

$1,158,250

B.

It depends on the internal decision making process. C. $2,074,249

C.

$1,550,000

Buy Now
Questions 6

A program manager has a multiple-project program that is scheduled to be completed by year’s end. During the program delivery phases of the projects, several mandatory changes are identified that would extend the program’s completion date.

What is the next step for the program manager?

Options:

A.

Apply resource leveling to ensure the program is completed on schedule

B.

Update the schedule to reflect the extended completion date

C.

Adjust working hours to ensure the program is completed on schedule

D.

Submit a change request to extend the program schedule

Buy Now
Questions 7

You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Options:

A.

Program administrative closure

B.

Enterprise environmental factors

C.

Closing processes

D.

Organizational process assets

Buy Now
Questions 8

Part of program management is to identify what motivates your program team members. If you subscribe to Maslow's Hierarchy of Needs, which need is at the top of the hierarchy?

Options:

A.

Physiological

B.

Safety

C.

Self actualization

D.

Esteem

Buy Now
Questions 9

According to Standard for Program Management, Second Edition, how many knowledge areas are involved for program management?

Options:

A.

7

B.

5

C.

9

D.

11

Buy Now
Questions 10

What is a stakeholder analysis chart?

Options:

A.

It is a matrix that identifies who must communicate with whom.

B.

It is a matrix that documents the stakeholders' requirements, when the requirements were created, and when the fulfillment of the requirements took place.

C.

It is a matrix that documents stakeholders' threats, perceived threats, and communication needs.

D.

It is a matrix that identifies all of the stakeholders and to whom they must report to.

Buy Now
Questions 11

Which of the following statements are true regarding program scope statement? (Choose three.)

Options:

A.

It defines all the work and only the required work for the program.

B.

It formally authorizes the program.

C.

It sets authorities and limits for the program manager and team.

D.

It represents a common understanding of the program for the purpose of facilitating communication among the stakeholders.

Buy Now
Questions 12

A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product’s delivery time.

What should the program manager update first?

Options:

A.

Procurement management plan

B.

Benefits register

C.

Risk register

D.

Benefits management plan

Buy Now
Questions 13

A program manager joins a team to fix a troubled enterprise-wide customer relationship management (CRM) system. Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository for similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity.

What should the program manager do with the knowledge gained from this activity?

Options:

A.

Include the lessons learned in the weekly program report

B.

Update the communications management plan

C.

Update the lessons learned database

D.

Communicate the corrective action to the program sponsor

Buy Now
Questions 14

Which of the following is described in the statement given below?

"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication."

Options:

A.

Stakeholder register

B.

Program scope statement

C.

Governance plan

D.

Organizational chart

Buy Now
Questions 15

Robert is the program manager for his organization which operates in a matrix structure.

Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

Options:

A.

Resource management plan

B.

Program management calendar

C.

Schedule management plan

D.

Resource calendar

Buy Now
Questions 16

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?

Options:

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member.

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.

D.

Create an online message board so team members can see and respond to everyone’s ideas.

Buy Now
Questions 17

A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the conditions of the program is that after the event takes place, a park will be built for the community’s use.

What should the program manager do to ensure community support?

Options:

A.

Review the scope with the program sponsor and community representatives

B.

Organize an advocacy group and facilitate community engagement

C.

Negotiate the program scope with community representatives

D.

Ensure community representatives are part of the steering committee

Buy Now
Questions 18

Which of the following increases when one fast tracks the project?

Options:

A.

Resource

B.

Risk

C.

Cost

D.

Communication

Buy Now
Questions 19

A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

Options:

A.

Gold plating

B.

Errors and omissions

C.

Expert judgment by the project manager

D.

Value added change

Buy Now
Questions 20

Wan is the program manager for his organization. He has been hearing reports that some

project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Options:

A.

The schedule to complete the work will take longer.

B.

The cost of the program and project will increase.

C.

The risks of failure will increase.

D.

The morale of the project managers will decline.

Buy Now
Questions 21

Martha is the program manager for her organization. One of the projects of a program is done but is also considerably over budget. Kay, the project manager, has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Martha instruct Kay to do with the information regarding the schedule delays and cost overruns?

Options:

A.

Create an entry in the lessons learned documentation and explain her reasoning behind the corrective actions.

B.

File the information as part of the project final report.

C.

Create a variance report.

D.

Create an exceptions report.

Buy Now
Questions 22

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.

What should the program manager do?

Options:

A.

Document the concerns that program goals may be affected and present at the next program governance board review meeting for guidance and actions to be taken

B.

Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan

C.

Work with the project managers of the affected components to implement fast tracking and update the resource management plan accordingly

D.

Evaluate critical success factors and key performance indicators (KPIs) to monitor benefits throughout the program's life cycle

Buy Now
Questions 23

Alice is the project manager of the NHQ Project and is entering the project's closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?

Options:

A.

Project Integration Plan

B.

Project Contract

C.

Project Quality Control procedures

D.

Project Communications Management Plan

Buy Now
Questions 24

Which of the following can be used to help you or other project managers on future projects?

Options:

A.

Sponsor

B.

Charter

C.

Stakeholder

D.

Documentation

Buy Now
Questions 25

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.

What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?

Options:

A.

Note stakeholder communication needs in the program charter and document their expectations in the benefits sustainment plan.

B.

Note stakeholder communication needs in the communications management plan and document their expectations in the benefits management plan.

C.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits management plan.

D.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits sustainment plan.

Buy Now
Questions 26

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

Options:

A.

Select the best bid from the prequalified vendor list.

B.

Accept the bid from the new vendor and document the decision.

C.

Advise the sponsor of a possible conflict of interest prior to awarding the bid.

D.

Add the new vendor to the prequalified list and replace the project manager.

Buy Now
Questions 27

Which of the following is used to build consensus through rounds of anonymous surveys?

Options:

A.

The Pareto chart

B.

The Delphi technique

C.

The Monte Carlo simulation

D.

The Gantt chart

Buy Now
Questions 28

You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

Options:

A.

Program requirements for resource competency levels

B.

Structure of the program management team

C.

Metrics and qualifications for program acceptance

D.

Location of the program work

Buy Now
Questions 29

An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers.

What should the program manager do first to obtain program approval?

Options:

A.

Prepare the stakeholder engagement plan for approval by the program steering committee.

B.

Analyze the business environment to identify key stakeholders, and then perform a stakeholder analysis.

C.

Conduct a brainstorming session with the program team to identify and analyze external stakeholders.

D.

Create a project-level stakeholder analysis, and then perform a high-level program stakeholder analysis.

Buy Now
Questions 30

An organization supports both programs and projects for various industries. What is a portfolio?

Options:

A.

A portfolio is the total amount of funds that have been invested in programs, projects, and operations.

B.

A portfolio describes all of the monies that are invested in the organization.

C.

A portfolio describes the organization of related projects, programs, and operations.

D.

A portfolio describes any project or program within one industry or application areA.

Buy Now
Questions 31

The program manager wants to ensure that a program contributes to shareholder value.

The program manager should verify alignment with which of the following?

Options:

A.

Program charter

B.

Organizational structures and policies

C.

Organizational strategic objectives

D.

Program governance plan

Buy Now
Questions 32

A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility.

What other important step should the program manager complete?

Options:

A.

Development of the program's vision statement

B.

Review of strategic goals against any external environmental factors

C.

Identification and documentation of the initial risks for ERP software implementation

D.

Mapping of the financial benefits to the ERP software's functionality

Buy Now
Questions 33

You are the program manager for your organization. Your program is about to being initiated and management is asking you for a document that will define all of the required resources, skills, and competencies you'll need in your program. What document defines the skills and competencies for a program?

Options:

A.

Staffing management plan

B.

Staffing pool description

C.

Program resources requirements plan

D.

Human resources management plan

Buy Now
Questions 34

You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

Options:

A.

The local government

B.

The change control board

C.

The stakeholders

D.

The program board

Buy Now
Questions 35

A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.

What should the program manager do next?

Options:

A.

Modify the program schedule to accommodate the risk.

B.

Incorporate the project risk into the program risk response strategy.

C.

Instruct the project manager to escalate the risk to the program sponsor.

D.

Ask the road construction project manager to manage the risk at the project level.

Buy Now
Questions 36

A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.

What should the program manager do to address these key stakeholders' concerns?

Options:

A.

Meet with the stakeholders and update the stakeholder map.

B.

Create a progress report to share with stakeholders after the next status meeting.

C.

Capture stakeholder expectations, and revise the stakeholder engagement plan.

D.

Update the communications management plan after meeting with the program steering committee.

Buy Now
Questions 37

Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company’s staff is unhappy about the acquisition. As a result, company B’s project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?

Options:

A.

Inform the stakeholders of this issue as soon as possible

B.

Change the program standards, aligning them with the project standards

C.

Work with the reports provided to extract the required information

D.

Remind the project manager of the relevant program standards

Buy Now
Questions 38

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?

Options:

A.

Program resource management planning

B.

Program risk mitigation

C.

Resource interdependency management

D.

Project resource planning

Buy Now
Questions 39

Which one of the following is not considered one of the three components of the Iron Triangle?

Options:

A.

Time

B.

Cost

C.

Scope

D.

Quality

Buy Now
Questions 40

You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule

beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

Options:

A.

Avoidance

B.

Mitigation

C.

Transference

D.

Workaround

Buy Now
Questions 41

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Options:

A.

It defines a program and groups the program's discrete work elements in a way that helps organize and define the total work scope of the program.

B.

It subdivides the program deliverables to work packages that are linked to the activities within the program.

C.

It defines all the work and only the required work for the program.

D.

It subdivides the program deliverables to work packages that are linked to the activities within the program.

Buy Now
Questions 42

You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager,

create at this time?

Options:

A.

Life cycle costing estimates

B.

Lessons learned documentation

C.

Operational transfer plan

D.

Program closure reports

Buy Now
Questions 43

Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

Options:

A.

Net present value

B.

Future value

C.

Present value

D.

Cost-Benefit ratio

Buy Now
Questions 44

Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?

Options:

A.

Conflict

B.

Noise

C.

Barrier

D.

Ad hoc

Buy Now
Questions 45

You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?

Options:

A.

You must ensure that the project sponsor closes the project.

B.

You must ensure that that the projects within the program have been closed at the project level.

C.

You must close the project before operations closes the project.

D.

You must ensure that the program management team closes the project for the project manager.

Buy Now
Questions 46

Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

Options:

A.

Resource network diagram

B.

Resource breakdown structure

C.

Resource histogram

D.

Pareto chart

Buy Now
Questions 47

Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?

Options:

A.

A change to add additional funds to the program scope

B.

A change to reduce the program scope

C.

Anything that management demands

D.

A change to add additional time to the program schedule

Buy Now
Questions 48

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Options:

A.

Operational transfer plan

B.

Program transition plan

C.

Benefits transfer plan

D.

Program closure plan

Buy Now
Questions 49

You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you've made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?

Options:

A.

Quality audit

B.

Scope verification

C.

Scope control

D.

Financial audit

Buy Now
Questions 50

Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?

Options:

A.

Program architecture baseline

B.

Program risk register

C.

Program WBS

D.

Program charter

Buy Now
Questions 51

What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated?

Options:

A.

Program scope statement definition

B.

Feasibility study creation

C.

Business case creation

D.

Program charter creation

Buy Now
Questions 52

An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback. As this type of program had previously been conducted by the company, the program manager QUESTION NO:s whether similar results were experienced during testing.

What should the program manager do next?

Options:

A.

Document the results to share with the program governance board.

B.

Facilitate another test market sampling.

C.

Contact the R&D department for product testing results.

D.

Review the program management information system (PMIS) for lessons learned.

Buy Now
Questions 53

Which of the following shows the ratio between a task's budgeted and actual costs?

Options:

A.

To-Complete Performance Index (TCPI)

B.

Schedule Variance (SV)

C.

Schedule Performance Index (SPI)

D.

Cost Performance Index (CPI)

Buy Now
Questions 54

Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."

Options:

A.

Budget

B.

Planned Value

C.

Contingency Reserve

D.

Earned Value

Buy Now
Questions 55

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Options:

A.

Contract and the quality measurements for the vendor's work

B.

The scope verification document and the termination notice

C.

Contract and scope verification process documents

D.

Work that has been completed and uncompleted work

Buy Now
Questions 56

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.

Since the shutdown was not anticipated, what should the program manager do first?

Options:

A.

Implement the appropriate risk response plan and inform the stakeholders of the planned actions.

B.

Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.

C.

Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.

D.

Collaborate with the sponsor to determine options and negotiate a new date for the milestone.

Buy Now
Questions 57

The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively

address the risks.

In this situation, what should the program manager change about the risk management plan?

Options:

A.

Allow the component project manager to delegate risk management responsibilities.

B.

Assign the resolution of project-level risks to the component project manager.

C.

Include risk escalation policies and procedures in the risk response plan.

D.

Increase flexibility with risks that require a risk response.

Buy Now
Questions 58

A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha’s program closure plan?

Options:

A.

Execute the transition plan, and include knowledge transfer to transition Alpha support to operations.

B.

Keep the Alpha program open until support is no longer required, then execute program closure.

C.

Adjust Alpha’s exit criteria to ensure its support is included in the Beta program.

D.

Document the program closure procedure to ensure that resources are released from Alpha to develop Beta.

Buy Now
Questions 59

The program manager completed the program's benefits analysis and planning activities.

What will this ensure for the program?

Options:

A.

Information necessary to establish key benefit performance indicators

B.

A transition plan to facilitate the ongoing realization of benefits

C.

A plan to monitor performance due to operational, financial, and benefits changes

D.

A benefits management plan to guide the work through the remainder of the program

Buy Now
Questions 60

A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company’s headquarters. Five regional sales departments are located at different locations around the world.

At this stage of the program, what is the first step?

Options:

A.

Develop a program work breakdown structure

B.

Identify and quantify business benefits of the program

C.

Determine and prioritize the various components of the program

D.

Prepare a program organization chart covering both sales and production

Buy Now
Questions 61

When is the lessons learned document updated?

Options:

A.

At closing phase

B.

At planning phase

C.

Throughout the project lifecycle

D.

At execution phase

Buy Now
Questions 62

Which of the following can be an effective tool during quality control to help determine the how the problem occurred?

Options:

A.

Rework

B.

Flowcharting

C.

Trend Analysis

D.

Pareto Diagram

Buy Now
Questions 63

Which of the following documents describes the details for each component in the WBS?

Options:

A.

WBS detail

B.

Risk register

C.

WBS dictionary

D.

Project charter

Buy Now
Questions 64

Who makes Go/No-Go decisions during phase gate reviews?

Options:

A.

Program Governance board

B.

Program Manager

C.

Board of Project Managers

D.

Stakeholders

Buy Now
Questions 65

An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.

What should the program manager do next?

Options:

A.

Assign resources to the schedule and report the revised delivery date to the project managers.

B.

Work with the project managers to refine the project schedules and deliverables to align with the program milestones.

C.

Revise the project schedules to meet the program schedule and communicate to stakeholders.

D.

Integrate the project schedules into the program schedule and report the revised delivery date to the project managers.

Buy Now
Questions 66

When a change enters your program requirements you must update all of the following documents except for which one?

Options:

A.

Program work breakdown structure

B.

Program activity list

C.

Program charter

D.

Program scope

Buy Now
Questions 67

You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its

projects. What document is management asking you to create in this instance?

Options:

A.

Requirements document

B.

Project charter

C.

Business case

D.

Scope statement

Buy Now
Exam Code: PgMP
Exam Name: Program Management Professional (PgMP)
Last Update: Jun 15, 2025
Questions: 452
PgMP pdf

PgMP PDF

$29.75  $84.99
PgMP Engine

PgMP Testing Engine

$35  $99.99
PgMP PDF + Engine

PgMP PDF + Testing Engine

$47.25  $134.99