During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?
Which of the following best describes a program in the context of project management?
A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?
A company plans to install new servers. The project manager receives a notification that the manufacturer may be in financial trouble, so the servers will be sourced from another vendor. Which of the following risk management strategies should the project manager use?
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
Which of the following can a project manager infer from the following velocity chart?

Which of the following software programs would be BEST to use lo store information related to business transactions?
A program manager is reviewing the project portfolio and prioritizing each project based on the company ' s strategic plan. Which of the following should be considered in this evaluation? (Select TWO).
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization ' s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
Which of the following activities are performed during the closing phase? (Select three).
Given the information in the chart,

which of the following techniques should the project manager use to improve the project schedule in Sprint 1?
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?
A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?
A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in
the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click
the Reset All button.
Select the Appropriate Tool:


Select the new critical path.
Option A
Option B
Option C

Which of the following demonstrates awareness of regulations and standards when conducting a project?
A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?
A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?
A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?
During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?
Which of the following tasks should the project manager complete first when validating deliverables?
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
Which of the following tools is best to use when conducting project meetings across time zones?
A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?
A client continues to present the project team with additional changes. To help with agreeing upon an expected delivery date, the project manager sets up a meeting with stakeholders. Which of the following should this meeting identify?
A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?
A project sponsor is trying to use the ROI to determine if the project should be approved. Which of the following best describes what the project sponsor needs?
During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

Which of the following was the initial cause of the issue?
A project team is developing an application that will allocate a building ' s parking spaces. The building owner does not agree with using corporate colors in the application and has blocked
the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?
Which of the following is a consideration when determining a project ' s ESG factors?
A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?
A PM is working on the schedule for a project that has technical tasks and requires a SME ' s knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager Which of the following should the newly appointed project manager do next?
A project team has been assigned to improve the customer service of a retail company. The team has conducted a thorough analysis of the existing process, determined areas of improvement, and identified the desired outcomes of the project. Which of the following best describes this analysis?
A project sponsor requires a system that is capable of providing integrated management of all the business ' s core functions. Which of the following systems is the project sponsor describing?
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?
During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?
A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?
Which of the following best describes why conducting lessons learned sessions is important?
A project team is determining how an application will be moved to production, who the users will be, and what training is needed. Which of the following best describes what is being developed?
Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?
The PM is concerned with multiple copies of the same file causing confusion. Which of the following would prevent this issue?
A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?
A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?
During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?
A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?
Which of the following activities should a project manager perform during the closing phase? (Select three).
The executive leadership of an agile company has launched a new strategy. This new strategy impacts new features that are in development with the project team. Which of the following describes what the team should do next?
A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager ' s objective for the vendor meeting?
A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?
During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?
A project manager is reviewing sprint performance in a retrospective meeting.

Given the following chart, which of the following sprints shows the highest velocity?
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:
A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?
Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?
A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?
A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical. Which of the following should the project manager do first?
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project ' s production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
Which of the following would help a project manager identify that project goals have been reached?
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
A project team wants to compare two potential vendors ' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?
A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?
Which of the following situations would require a project manager to revise the communication plan during a project ' s execution?
Project+ |