Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
Who is responsible for developing the project management plan and all related component plans?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
A project manager who communicates to the project team though email is using which type of communication?
When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
The specific technique for identifying a problem, discovering the causes that lead to it, and developing preventive actions is:
Which item is a formal proposal to modify any document, deliverable, or baseline?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
Which of the following is a tool and technique for Estimate Activity Durations?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
The organizational process assets that are of particular importance to Plan Communications are:
Progressively elaborating high-level information into detailed plans is performed by the:
Which process involves identifying and documenting the logical relationships between project activities?
Which schedule development technique modifies the project schedule to account for limited resources?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6?
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
Which of the following involves making information available to project stakeholders in a timely manner?
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
The number of potential communication channels for a project with 5 stakeholders is:
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Which organizational process assets update is performed during the Close Procurements process?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?
Which of the following is a complete set of indexed contract documentation, including the closed contract?
Which is the correct formula for calculating expected activity cost for three-point estimating?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
What is the number of stakeholders, if the project has 28 potential communication channels?
During which process would you obtain stakeholders’ formal acceptance of the completed project scope?
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Which process determines the risks that may affect the project and documents their characteristics?
Which of the following lists contain processes that are included within Project Procurement Management?
What defines the portion of work included in a contract for items being purchased or acquired?
Within project integration management, the statement of work (SOW) references which aspects of the project?
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
Which of the following response strategies are appropriate for negative risks or threats?
What entity is assigned various responsibilities related to the centralized and coordinated management of those projects under its domain?
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Which Process Group contains those processes performed to define a new project?
Which tool or technique is used in the Develop Project Management Plan process?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?
The project scope statement and resource calendars are inputs to which Project Time Management process?
Project-Management-Professional | PMI-001 Questions Answers | PMI-001 Test Prep | Project Management Professional v5 Questions PDF | PMI-001 Online Exam | PMI-001 Practice Test | PMI-001 PDF | PMI-001 Test Questions | PMI-001 Study Material | PMI-001 Exam Preparation | PMI-001 Valid Dumps | PMI-001 Real Questions | Project-Management-Professional PMI-001 Exam Questions