Weekend Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: fifty75ct

PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) Questions and Answers

Questions 4

During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.

Is this an appropriate application of the ‘capture issues and risks’ activity, and why?

Options:

A.

Yes, because recording the concern in the project log is sufficient before allowing delivery to continue

B.

Yes, because the project manager may dismiss an informally raised concern without further investigation

C.

No, because the project manager should assess an informally raised concern before deciding what action to take

D.

No, because the team manager should report the concern only in the next scheduled checkpoint report

Buy Now
Questions 5

During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown’s ‘green town’ status.

During which ‘initiating a project’ activity should this workshop take place?

Options:

A.

Agree the tailoring requirements

B.

Agree the management approaches

C.

Prepare the project plan

D.

Prepare the full business case

Buy Now
Questions 6

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

Options:

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

Buy Now
Questions 7

The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because restricting the CTO’s involvement would protect the project’s reputation from untested proposals

B.

Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty

C.

No, because the project manager should record the technological concerns only as risks requiring formal responses

D.

No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem

Buy Now
Questions 8

During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.

The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?

Options:

A.

Yes, because evaluation confirms that completed quality activities are recorded and that the current status is understood by the relevant parties

B.

Yes, because the team manager should review the work-package information, report progress for the agreed period, and notify the project manager when a tolerance is forecast to be exceeded

C.

No, because only the project manager may evaluate the status of a work package and decide what it should report

D.

No, because a forecast work-package tolerance breach should be reported directly to the project board in an exception report

Buy Now
Questions 9

During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively

B.

Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case

C.

No, because stakeholder identification should not take place during project initiation

D.

No, because early identification of an opposing group will necessarily increase its opposition

Buy Now
Questions 10

At the start of stage 3, an approved request for change adds a promotional video to the stage. BuildyBrick has agreed to produce it, a product description has been prepared, and the project manager now needs to instruct the BuildyBrick team manager to begin the work.

During which ‘controlling a stage’ activity should this instruction be given?

Options:

A.

Authorize a work package

B.

Evaluate work package status

C.

Capture issues and risks

D.

Take corrective action

Buy Now
Questions 11

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Buy Now
Questions 12

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

Options:

A.

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.

No, because it is an exception which should be escalated in an exception report

Buy Now
Questions 13

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

Options:

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier

Buy Now
Questions 14

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

Options:

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

Buy Now
Questions 15

During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.

Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

Options:

A.

Yes, because standardized portfolio role descriptions give every project manager a consistent and well-understood baseline of responsibilities, removing the need for individual discussion

B.

Yes, because it is the project executive’s responsibility to appoint the project manager and establish their responsibilities as part of the ‘starting up a project’ process

C.

No, because each project manager must have a clear understanding of their own individual responsibilities and formally accept those responsibilities before commencing project work

D.

No, because it is the portfolio manager’s role, rather than the project executive’s, to define the project manager’s responsibilities for projects within the portfolio

Buy Now
Questions 16

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Buy Now
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Oct 3, 2026
Questions: 56
PRINCE2-7-Practitioner pdf

PRINCE2-7-Practitioner PDF

$21.25  $84.99
PRINCE2-7-Practitioner Engine

PRINCE2-7-Practitioner Testing Engine

$25  $99.99
PRINCE2-7-Practitioner PDF + Engine

PRINCE2-7-Practitioner PDF + Testing Engine

$33.75  $134.99