PRINCE2-Agile-Foundation PRINCE2 Agile Foundation (Version 2) Exam Questions and Answers

Questions 4

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

Options:

A.

How to adapt the PRINCE2 management products

B.

How to select which Agile framework should be favoured

C.

How to decide whether PRINCE2 is appropriate

D.

How to calculate the project budget and cost tolerance

Buy Now
Questions 5

Which workshop focuses on team growth and improvements in working practices?

Options:

A.

Project kickoff workshop

B.

Team retrospective workshop

C.

Progress review workshop

D.

Team planning workshop

Buy Now
Questions 6

What is an epic?

Options:

A.

A detailed user story with high business value

B.

The set of products handed over to the users

C.

A high-level user story that is quite broad or vague

D.

A prioritized list of requirements to be delivered in a sprint

Buy Now
Questions 7

Which workshop is used to assess the project’s status and address any challenges?

Options:

A.

Team planning workshop

B.

Project retrospective workshop

C.

Team retrospective workshop

D.

Progress review workshop

Buy Now
Questions 8

Which describes the Scrum Master role in Scrum?

Options:

A.

It is authorized to run the project on a day-to-day basis on behalf of the project board

B.

It is responsible for ensuring that product backlog items are clearly expressed on the product backlog

C.

It is empowered to organize and manage its own work to create a valuable, useful increment every sprint

D.

It is servant-leadership to help everyone change their interactions to maximize the value created by the team

Buy Now
Questions 9

Which statement about timeboxes is CORRECT?

Options:

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments

Buy Now
Questions 10

When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

Options:

A.

It should be used when planning at the delivery level

B.

It should be used when planning at the project level

C.

It should be used when controlling the quality of the products delivered

D.

It should be used when monitoring the amount of products delivered

Buy Now
Questions 11

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

Options:

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

Buy Now
Questions 12

Which of the following BEST describes stakeholders in a project?

Options:

A.

Those who have a formal role in the project team

B.

Those who will use project products

C.

Those who can affect or be affected by the project

D.

Those who can impact the project

Buy Now
Questions 13

When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

Options:

A.

Preferable

B.

Typical

C.

Effective

Buy Now
Questions 14

Which organizational level is responsible for day-to-day management and decision making within the constraints established by the project manager?

Options:

A.

Commissioning

B.

Directing

C.

Managing

D.

Delivering

Buy Now
Questions 15

Which is a purpose of the quality theme?

Options:

A.

To define the specific conditions that enable a product to be usable

B.

To determine how the means of delivering products is communicated

C.

To evaluate whether the project continues to be achievable

D.

To assess any potential improvements to a product

Buy Now
Questions 16

Which of the following is used to monitor progress?

Options:

A.

Delegation matrix

B.

Swarming

C.

T-shirt sizing

D.

Burn-down chart

Buy Now
Questions 17

What should the business case state about the minimum viable product (MVP)?

Options:

A.

When the MVP will be defined

B.

That the MVP must go into operational use

C.

What the MVP is

D.

That the MVP is the same as project viability

Buy Now
Questions 18

In which step of the approach to issue management are options to resolve an issue evaluated?

Options:

A.

Capture

B.

Implement

C.

Decide

D.

Recommend

Buy Now
Questions 19

How should team working agreements be created?

Options:

A.

By the supplier subject matter expert agreeing what should be included

B.

By the customer representative deciding what should be included

C.

By team members agreeing on what should be included

D.

By the project manager deciding what should be included

Buy Now
Questions 20

Which BEST describes the senior user role when tailoring the organization theme?

Options:

A.

An ‘agile sponsor’

B.

An ‘executive sponsor’

C.

A ‘coach’

D.

A ‘super product owner’

Buy Now
Questions 21

In which workshop are the project role descriptions created?

Options:

A.

Starting-up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Project canvas workshop

Buy Now
Questions 22

Which of the following describes shared attitudes, values, and goals?

Options:

A.

Culture

B.

Leadership

C.

Co-creation

D.

Management

Buy Now
Questions 23

Which is an advantage of frequent releases?

Options:

A.

Releases can be used to replace management stages

B.

A ‘one-team’ culture in the project team is encouraged

C.

Configuration management becomes less important

D.

The delivery team becomes more experienced at product handover

Buy Now
Questions 24

Which statement about velocity is CORRECT?

Options:

A.

It is based on the concept of rationalism

B.

It is shown by the ideal line on a bum-down chart

C.

It describes how much work is getting done

D.

It tracks the time and cost of a timebox

Buy Now
Questions 25

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

Options:

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Buy Now
Questions 26

How are user inputs FIRST gathered in the 'quality' practice?

Options:

A.

As user stories in the product backlog

B.

As epic user stories in the project backlog

C.

As the project Definition of Done in the quality management approach

D.

As a quality control activity in the quality register

Buy Now
Questions 27

Why are team working agreement produced?

Options:

A.

To create structure so that the team manager can assess individual performance

B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

C.

To make the team rules visible to the project manager for monitoring purposes

D.

To ensure that the delivery team members comply with company policy

Buy Now
Questions 28

Which is a collaborative technique for defining decision-making within teams?

Options:

A.

Delegation poker

B.

Team skills matrix

C.

Personas

D.

Magic estimation

Buy Now
Questions 29

Which of the following uses a flow-based approach to control work in progress?

Options:

A.

Agilometer

B.

Lean

C.

Kanban

D.

Scrum

Buy Now
Questions 30

To help with prioritization, what is MOST important when understanding the difference between scope and quality?

Options:

A.

Combining functional and non-functional requirements

B.

Creating non-functional requirements with user stories

C.

Differentiating functional from non-functional requirements

D.

Defining non-functional requirements before functional requirements

Buy Now
Questions 31

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 32

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It minimizes the time needed to train a new team member

B.

It reduces the planning of dependencies between projects

C.

It reduces testing in order to meet deadlines

D.

It encourages the customer to raise new ideas

Buy Now
Questions 33

Which statement about the waterfall methodology definition is CORRECT?

Options:

A.

It states that deadlines should not be moved

B.

It has distinct goals for each stage of development

C.

It is a behavior that involves making things transparent

D.

It promotes the use of experiments carried out in a scientific way

Buy Now
Questions 34

Which of the following is a benefit of an organization being and doing agile?

Options:

A.

Faster time-to-market

B.

Using agile techniques

C.

Focusing on completing tasks

D.

Setting all tolerances to zero

Buy Now
Questions 35

What information is NOT typically displayed on a burn chart?

Options:

A.

Effort remaining

B.

Team working agreements

C.

Actual amount of work done

D.

Amount of time elapsed

Buy Now
Questions 36

In Lean Startup, what is based on the concept of ‘learn the most with the least effort’?

Options:

A.

A structured, timeboxed event

B.

A minimum viable product

C.

A measurement of lead times

D.

A set of criteria to determine whether work can be started

Buy Now
Questions 37

Which process can take place during a release review workshop?

Options:

A.

Controlling a stage

B.

Managing product delivery

C.

Managing a stage boundary

D.

Directing a project

Buy Now
Questions 38

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 39

Which role is responsible for facilitating the Agilometer assessment?

Options:

A.

Project board

B.

Project manager

C.

Team manager

D.

Customer subject matter expert

Buy Now
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Aug 17, 2025
Questions: 132
PRINCE2-Agile-Foundation pdf

PRINCE2-Agile-Foundation PDF

$29.75  $84.99
PRINCE2-Agile-Foundation Engine

PRINCE2-Agile-Foundation Testing Engine

$35  $99.99
PRINCE2-Agile-Foundation PDF + Engine

PRINCE2-Agile-Foundation PDF + Testing Engine

$47.25  $134.99