PRINCE2-Agile-Foundation PRINCE2 Agile Foundation (Version 2) Exam Questions and Answers

Questions 4

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 5

Which statement defines a PRINCE2 principle?

Options:

A.

A PRINCE2 project defines its quality management approach

B.

A PRINCE2 project is monitored and controlled on a stage-by-stage basis

C.

A PRINCE2 project ensures a consistent approach to risk management

D.

A PRINCE2 project is tailored to suit the competitor’s environment

Buy Now
Questions 6

Which of the following transforms an organization from “doing” to “being Agile” by emphasizing a culture of flexibility and learning?

Options:

A.

Agile Onion

B.

Psychological safety

C.

Agile mindset

D.

Agile sustainability

Buy Now
Questions 7

Which technique is used in the ’Issues' practice?

Options:

A.

Trading/swapping

B.

Objectives and key results

C.

Refactoring

D.

Delegation poker

Buy Now
Questions 8

Which practice supports identification and assessment of uncertainties?

Options:

A.

Risk

B.

Plans

C.

Quality

D.

Business case

Buy Now
Questions 9

To help with prioritization, what is MOST important when understanding the difference between scope and quality?

Options:

A.

Combining functional and non-functional requirements

B.

Creating non-functional requirements with user stories

C.

Differentiating functional from non-functional requirements

D.

Defining non-functional requirements before functional requirements

Buy Now
Questions 10

How does PRINCE2 Agile describe Scrum?

Options:

A.

Scrum is an IT method

B.

Scrum is agile and agile is Scrum

C.

Scrum is the most well-known agile framework

D.

Scrum is a project management framework

Buy Now
Questions 11

Which statement about the ‘directing a project’ process is CORRECT?

Options:

A.

The project board may pull reports from the information radiator

B.

As a minimum, the project board should receive oral reports from the project manager

C.

The project board should attend the delivery team’s daily stand up meeting

D.

The project board should receive regular reports focusing on cost and time overruns

Buy Now
Questions 12

Which workshop enables participants to collaboratively define the Definition of Ready?

Options:

A.

Starting up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Agile enablement workshop

Buy Now
Questions 13

How does AI align with PRINCE2 Agile’s iterative approach?

Options:

A.

By reducing the need for continuous feedback

B.

By offering predictive insights to respond to change

C.

By defining the Definition of Done

D.

By reducing the need for frequent testing

Buy Now
Questions 14

In which process is a workshop conducted to agree the Definition of Ready (DoR) and Definition of Done (DoD)?

Options:

A.

Initiating a project

B.

Directing a project

C.

Controlling a stage

D.

Managing product delivery

Buy Now
Questions 15

How should team working agreements be created?

Options:

A.

By the supplier subject matter expert agreeing what should be included

B.

By the customer representative deciding what should be included

C.

By team members agreeing on what should be included

D.

By the project manager deciding what should be included

Buy Now
Questions 16

Which statement about the waterfall methodology definition is CORRECT?

Options:

A.

It states that deadlines should not be moved

B.

It has distinct goals for each stage of development

C.

It is a behavior that involves making things transparent

D.

It promotes the use of experiments carried out in a scientific way

Buy Now
Questions 17

How is the ‘tailor to suit the project’ principle applied in an agile context?

Options:

A.

By flexing what is produced to stay in control and deliver value

B.

By emphasizing tolerances on what is being delivered

C.

By using the Agilometer to assess the project environment

D.

By fitting releases into planned management stages

Buy Now
Questions 18

Which statement about the ‘directing a project’ process is CORRECT?

Options:

A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

Buy Now
Questions 19

What is typically added to a user story as the understanding of the requirement evolves?

Options:

A.

An epic

B.

Acceptance criteria

C.

Definition of ‘ready’

D.

Effort actually expended

Buy Now
Questions 20

Which of the following integrated elements defines who is working on the project and who is affected by the project?

Options:

A.

The project context

B.

The PRINCE2 practices

C.

The PRINCE2 processes

D.

The “people” element

Buy Now
Questions 21

What is an epic?

Options:

A.

A low-level requirement

B.

A fine-grained user story

C.

A detailed feature

D.

A high-level requirement

Buy Now
Questions 22

Which statement about the waterfall methodology definition is CORRECT?

Options:

A.

It prevents earlier phases of development being revisited

B.

It uses an iterative and incremental approach

C.

It focuses on responding to changing requirements

D.

It delivers products more frequently in shorter phases

Buy Now
Questions 23

Which two statements about tailoring the business case in an agile environment are CORRECT?

1. It should be unnecessary because products of the highest value will be delivered first.

2. It should identify the minimum viable product and when it will be delivered.

3. It should take into account that the scope may be reduced during the course of the project.

4. It should show the features, the order in which they will be delivered and any dependencies.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 24

Which statement about timeboxes is CORRECT?

Options:

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments

Buy Now
Questions 25

When should the project canvas be BOTH updated and used to assess whether the intended benefits have been or will be realized?

Options:

A.

At the end of the pre-project stage

B.

At the end of the initiation stage

C.

At the end of each delivery stage

D.

At the end of the final delivery stage

Buy Now
Questions 26

Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

Options:

A.

It reduces testing in order to meet deadlines

B.

It sets the project baseline at the correct level

C.

It enables team dynamics to remain the same

D.

It improves the supplier's reputation with the customer

Buy Now
Questions 27

In which step of the approach to issue management are options to resolve an issue evaluated?

Options:

A.

Capture

B.

Implement

C.

Decide

D.

Recommend

Buy Now
Questions 28

Which of the following is a common challenge when merging project management and Agile?

Options:

A.

Lack of clear processes

B.

The use of different terminology

C.

Lack of guidance at project level

D.

The use of a flexible framework

Buy Now
Questions 29

What should be emphasized when tailoring the PRINCE2 Progress theme?

Options:

A.

Monitoring what is being delivered

B.

Tracking time and cost

C.

Planning resources

D.

Assessing the impact of risks

Buy Now
Questions 30

Which principle supports a “fail-fast-learn-fast” environment?

Options:

A.

Manage by stages

B.

Manage by exception

C.

Define roles, responsibilities, and relationships

D.

Tailor to suit the project

Buy Now
Questions 31

How are user inputs FIRST gathered in the 'quality' practice?

Options:

A.

As user stories in the product backlog

B.

As epic user stories in the project backlog

C.

As the project Definition of Done in the quality management approach

D.

As a quality control activity in the quality register

Buy Now
Questions 32

What is the purpose of the “agile enablement” workshop?

Options:

A.

To identify, assess, and plan for risks associated with project delivery

B.

To identify, assess, and plan for risks associated with team delivery

C.

To identify, assess, and plan for risks associated with Agile adoption

D.

To identify, assess, and plan for risks associated with enterprise agility

Buy Now
Questions 33

Which TWO are the purposes of a highlight report?

1. To describe the MoSCoW priority of user stories.

2. To summarize the status of a work package.

3. To summarize the stage status.

4. To report any potential issues and risks

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 34

How is the “closing a project” process used?

Options:

A.

By controlling the link between the project manager and the delivery team

B.

By ensuring that the project is viable

C.

By accepting the project product

D.

By ensuring the focus remains on delivering the stage’s products

Buy Now
Questions 35

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

Options:

A.

To use empiricism, based on knowledge that comes from experience

B.

To build, measure, learn from your experiences

C.

To create a minimum viable product to manage uncertainty

D.

To fail fast, if you are going to fail

Buy Now
Questions 36

Which artifact provides a list of user stories?

Options:

A.

Project backlog

B.

Project canvas

C.

Product backlog

D.

Release map

Buy Now
Questions 37

In which workshop does planning for the next stage occur?

Options:

A.

Team planning workshop

B.

Release planning workshop

C.

Team retrospective workshop

D.

Progress review workshop

Buy Now
Questions 38

Which Agile approach is an iterative and timeboxed approach to product delivery?

Options:

A.

Scrum

B.

Kanban

C.

Agilometer

D.

Lean

Buy Now
Questions 39

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.

2. They are partially assigned to the delivery team.

3. They create the project's specialist products.

4. They prioritize requirements.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 40

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

Options:

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Buy Now
Questions 41

In which area is Agile strongest when blending with PRINCE2?

Options:

A.

Product delivery

B.

Project management

C.

Project direction

D.

Product management

Buy Now
Questions 42

Which artifact identifies risks associated with using an iterative project management approach?

Options:

A.

Project backlog

B.

Agilometer

C.

Risk management approach

D.

Definition of Done

Buy Now
Questions 43

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 44

Which statement about the ‘protect the level of quality’ target is CORRECT?

Options:

A.

It is achieved by allowing enough time for testing

B.

It is achieved by using the same team members

C.

It gives confidence on the progress of the project

D.

It delivers the early realization of benefits

Buy Now
Questions 45

Which is a reason for releasing a product into a staging area?

Options:

A.

It enables the faster delivery of changes

B.

It supports regulatory compliance checking

C.

It enables a phased Waterfall approach

D.

It supports management by exception

Buy Now
Questions 46

What is typically displayed on a board to show progress to people working on a project?

Options:

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

Buy Now
Questions 47

What role does AI play in addressing project complexity within PRINCE2 Agile?

Options:

A.

It helps reduce all sources of project complexity

B.

It adds layers of complexity through excessive automation

C.

It helps reduce uncertainty and ambiguity associated with change initiatives

D.

It ensures stakeholder involvement in all decision-making

Buy Now
Questions 48

Which workshop is used to assess the project’s status and address any challenges?

Options:

A.

Team planning workshop

B.

Project retrospective workshop

C.

Team retrospective workshop

D.

Progress review workshop

Buy Now
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Feb 21, 2026
Questions: 162
PRINCE2-Agile-Foundation pdf

PRINCE2-Agile-Foundation PDF

$25.5  $84.99
PRINCE2-Agile-Foundation Engine

PRINCE2-Agile-Foundation Testing Engine

$30  $99.99
PRINCE2-Agile-Foundation PDF + Engine

PRINCE2-Agile-Foundation PDF + Testing Engine

$40.5  $134.99