Questions 4

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

Options:

A.

An activated Scheduling indicator in the control key of the internal processing activity

B.

Whether the work for the internal activity is greater than its duration

C.

The unit (for example, hour, day) of the field Normal Duration field of the activity

D.

The relationships between activity elements

E.

The factory calendar in the work center used for the internal processing activity

Buy Now
Questions 5

Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

Options:

A.

Schedule Manager

B.

Project Builder

C.

Project planning board

D.

Easy Cost Planning

Buy Now
Questions 6

Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

Options:

A.

Project versions can be changed

B.

Project versions are mandatory for Milestone Trend Analysis (MTA)

C.

Project versions can be created automatically based on user status

D.

Manually Created project versions always require a project version profile

Buy Now
Questions 7

For which objects can billing plans be created? Note: There are 2 correct answers to this question

Options:

A.

WBS elements

B.

Project definition

C.

Sales order items

D.

Milestones

Buy Now
Questions 8

Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.

Note : there are 3 correct answers for this question.

Options:

A.

Display of production orders assigned to WBS element.

B.

Display of plant maintenance orders for activities.

C.

Display of project cost plan.

D.

Display of project -relevant purchase order.

E.

Using specific color management for Gantt Chart.

Buy Now
Questions 9

Project Structures

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the

project.

What are the prerequisites?

Note: There are 3 correct answers to this question

Options:

A.

A bill of material with sales views

B.

A material master with sales views

C.

Assignment between material and standard network

D.

Standard network with activities

E.

A production order

Buy Now
Questions 10

What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

Options:

A.

A delivery document type must be configured

B.

A sold to party is necessary

C.

A shipping point is necessary

D.

A sales order must be created in advance

Buy Now
Questions 11

You want to exchange data between SAP Project System and Microsoft What interface do you use?

Options:

A.

The EPS interface (External Project Software).

B.

No interface to Microsoft Project is available.

C.

The catalog interface.

D.

you do not need and interface. You can exchange data using object link.

Buy Now
Questions 12

Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

Options:

A.

Structure overview for budgets

B.

Hierarchical report on budget updates

C.

Cost element report on budget updates

D.

Line item report for budgets

Buy Now
Questions 13

What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question

Options:

A.

Confirm production order

B.

Stock transfer posting

C.

Generate purchase requisition

D.

Generate delivery

E.

Cancel goods issue

Buy Now
Questions 14

Cost & Budget.

A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

Options:

A.

Settlement rules

B.

Costing Sheet

C.

Investment profile.

D.

Results analysis key

Buy Now
Questions 15

How can you update the degree of processing for an activity?

Options:

A.

By using results analysis

B.

By changing the activity

C.

By scheduling the activity

D.

By confirming the activity

Buy Now
Questions 16

You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question

Options:

A.

Automatic activation with budget assignment

B.

Automatic activation with assignment to an investment program

C.

Background activation (CJBV - Activate Availability Control) l

D.

Automatic activation with the first actual posting

Buy Now
Exam Code: C_TS412_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Last Update: May 1, 2024
Questions: 110