TGY Ltd is a manufacturing organisation which produces five major components for use in the transport sector. Each component is produced by a different Project Team. Below are details of the five projects.
Project 1: The team are looking at where the material originates and how much of this natural resource is left in the ground.
Project 2: The team are focused on what happens when the product is no longer required by the customer and whether the product can be repurposed to save it going to landfill.
Project 3: The team are keen to ensure the customer is happy with the product and that it meets safety standards. The focus of the Life Cycle Analysis is on what happens inside the factory.
Project 4: The team are looking at the longevity of the item once purchased by the customer.
Project 5: The team are exploring the additional overhead costs associated with the production of the item and the way in which the item is produced.
Complete the table below by listing the area of life cycle analysis being looked at, and the area of the Balanced Scorecard this relates to (some options may be used twice); energy consumption, use, disassembly, extraction, manufacturing, transportation, sustainability x2, quality, environment, value for money, processes.
Which of the following will you put into box 1?
What are the four key performance outcome themes of a Joint Performance Appraisal Framework?
Swift Manufacturing is currently seeking new suppliers to create a new product that will be launched next year. They are keen to enter a new market and expand their customer base and ensure the new product provides value for money to the customer. The procurement department is currently conducting market research which will inform upon possible designs for the new product.
Simultaneously they are also speaking with suppliers regarding the specification. Swift Manufacturing are keen to ensure the new product is as environmentally friendly as possible, so are researching different raw materials that can be used and their impact upon the environment.
When designing the tender process, Swift Manufacturing would like the successful supplier to have an environmental management system in place and will incorporate this as part of the ‘essential criteria’ of the specification and tested on the PQQ stage of the tender.
It is important for the CEO of Swift Manufacturing that the supplier hits the ground running on this contract as soon as it is signed, given the importance of the new product to the organisation’s competitive advantage strategy. He is therefore keen to ensure that the procurement department include strict performance targets within the contract.
For the tender, which of the following standards should be mandated?
A supplier who provides a low value item to a supplier, but holds the monopoly in the marketplace is a provider of which type of good?
In order to achieve competitive advantage, it is important that an organisation with several suppliers asks all of its suppliers to innovate, as this will lead to new ideas and cost savings. Is this TRUE?
Julie is the CEO of a small manufacturing company which is struggling to compete in the marketplace. Julie is considering implementing Simultaneous Engineering processes, what would be the benefit of this to her organisation? Select all that apply
Below are details of five companies who all have different types of relationships with their suppliers. For each company, select the corresponding relationship type and the main relationship- influencing KPI monitored by the company.
Company 1: The relationship is characterised by high levels of conflict, but is one in which there is mutual respect for each other’s ideas and innovative solutions are often formed from the conflict. This KPI is measured by the level of information sharing between the buyer and supplier and the level of reliability of both parties.
Company 2: There is a low level of co-operation between Company 2 and its main supplier. The contract is not expected to last much longer due to conflicts that cannot be resolved amicably. There is a low level of dependency on the supplier and a number of alternative providers in the marketplace.
Company 3: The relationship is characterised by a win-win approach and both parties consider themselves equal. The relationship is measured based on its openness, honesty and levels of information sharing, particularly in the disclosure of sensitive information.
Company 4: Company 4 works well with their supplier and there is little conflict. The relationship is important due to the high value of the contract and the two parties work together to meet the same goals. The KPI measures the exchanges and levels of collaboration between the parties.
Company 5: The supplier does not place much importance on the relationship with Company 5 due to the low value of the contract. Company 5 is worried that the supplier is not willing to invest in the contract and therefore are measuring the loyalty of the supplier as a KPI.
Complete the table below with the correct relationship type and relationship influencing KPI: nice, creative, marginal, hostile, partnership arm’s length, power, trust, co-operation, communication, commitment, transparency.
Which of the following will you put into box 6?
Below are details of 5 companies who are all embarking on the launch of a new product. For each company, you must decide which innovation tactic they are using and the priority for the new contract.
Company 1: The company aims to design the specification around customers’ requirements. They are keen to ensure a balance between costs and the service provided.
Company 2: This company attends regular conferences held by a professional body and will use the information discussed to inform upon the specification. They are keen to ensure sufficient interest from the marketplace so are placing a priority on networking at the conferences.
Company 3: There is a small group of internal stakeholders who meet regularly at Company 3 who discuss supply chain and organisational integration. The priority for the group is to ensure that the supplier of the new product’s raw materials meets the company’s standards for environmental protection.
Company 4: This company has regular phone calls with suppliers discussing ideas for the new product. Once the product is launched, the focus will be on ensuring that the supplier is held to account.
Company 5: Equipment has been loaned to a supplier to produce a prototype of the new product. The aim of the project is to ensure the supplier is capable of producing the components required for the product before the contract is signed.
Complete the table below by listing the innovation tactic and contract priority for each company; focus group, innovation council, technology transfer, collaboration, supplier forum, early supplier involvement, supplier development, balanced scorecard, contract management, selection, value for money, bidding.
Which of the following will you put into box 9?
The costs associated with inspection and testing of products to ensure they meet statutory requirements is known as what type of cost?
Groupthink and Cultural Silos can be avoided by the successful implementation of which of the following processes?
Mohammed has recently been hired as the new CEO of ABC Ltd, a large manufacturing organisation. The organisation has struggled in recent years due to the highly competitive nature of the marketplace and Mohammed has been brought in to radically change the organisation’s approach to procurement and supply chain management.
Traditionally the organisation has dictated its requirements to suppliers with stringent penalty clauses for non-compliance. Mohammed is keen to change this approach and leverage the knowledge of suppliers to ABC’s advantage.
XYZ is the main supplier to ABC Ltd and Mohammed has set up a meeting to discuss the relationship and contract currently in place. He wishes the relationship to be win-win and wishes to share ideas on potential efficiencies that can be gained for both organisations. He will propose a new mechanism for monitoring the performance of the contract based on four key parameters; cost, customer satisfaction, innovation and operational processes.
XYZ provides raw materials such as iron and steel and Mohammed is keen to gain an understanding of the environmental impact of the extraction, transportation and usage of these materials, the findings of which will impact the company’s mission statement, which will be re-written next year.
In terms of other suppliers, where spend is minimal and risk is low, Mohammed plans to introduce Standard Operating Procedures for the procurement of supplies and is looking into various tools which will save the procurement team time and money.
What form of relationship is Mohammed seeking to have with XYZ Ltd?
Screws and Hammers Ltd is a wholesale retailer of small items used in the construction trade, and is popular with small and medium sized maintenance and construction businesses. Sarah, the head of Marketing, has decided that a good way to increase sales is to put a list of the stock they carry on their website, along with the price of each item. What is this known as? Select TWO
The Plan-Do-Check-Act cycle provides a Framework for an organisation to follow under which ISO standard?
An organisation is attempting to increase the value for money of its own products by making improvements with its suppliers and supply chain. Which category of supplier will have the largest impact on this?
Pentagon Services have a partnership type of relationship with their main supplier and introduced a Joint Performance Appraisal scheme for a new venture which they are embarking on together. This process includes an ' open-loop feedback ' mechanism, what will this aid?
The introduction of e-procurement tools has led directly to which of the following? Select ALL that apply
Which of the following technologies creates physical objects, reduces a company ' s carbon footprint and saves on costs over traditional manufacturing processes?
An ' Enterprise Service Bus ' is an example of which of the following, which is a tool that may be used by the procurement professional?
Below are details of five companies who all have different types of relationships with their suppliers. For each company, select the corresponding relationship type and the main relationship- influencing KPI monitored by the company.
Company 1: The relationship is characterised by high levels of conflict, but is one in which there is mutual respect for each other’s ideas and innovative solutions are often formed from the conflict. This KPI is measured by the level of information sharing between the buyer and supplier and the level of reliability of both parties.
Company 2: There is a low level of co-operation between Company 2 and its main supplier. The contract is not expected to last much longer due to conflicts that cannot be resolved amicably. There is a low level of dependency on the supplier and a number of alternative providers in the marketplace.
Company 3: The relationship is characterised by a win-win approach and both parties consider themselves equal. The relationship is measured based on its openness, honesty and levels of information sharing, particularly in the disclosure of sensitive information.
Company 4: Company 4 works well with their supplier and there is little conflict. The relationship is important due to the high value of the contract and the two parties work together to meet the same goals. The KPI measures the exchanges and levels of collaboration between the parties.
Company 5: The supplier does not place much importance on the relationship with Company 5 due to the low value of the contract. Company 5 is worried that the supplier is not willing to invest in the contract and therefore are measuring the loyalty of the supplier as a KPI.
Complete the table below with the correct relationship type and relationship influencing KPI: nice, creative, marginal, hostile, partnership arm’s length, power, trust, co-operation, communication, commitment, transparency.
Which of the following will you put into box 9?
Below are details of five companies who all have different types of relationships with their suppliers. For each company, select the corresponding relationship type and the main relationship- influencing KPI monitored by the company.
Company 1: The relationship is characterised by high levels of conflict, but is one in which there is mutual respect for each other’s ideas and innovative solutions are often formed from the conflict. This KPI is measured by the level of information sharing between the buyer and supplier and the level of reliability of both parties.
Company 2: There is a low level of co-operation between Company 2 and its main supplier. The contract is not expected to last much longer due to conflicts that cannot be resolved amicably. There is a low level of dependency on the supplier and a number of alternative providers in the marketplace.
Company 3: The relationship is characterised by a win-win approach and both parties consider themselves equal. The relationship is measured based on its openness, honesty and levels of information sharing, particularly in the disclosure of sensitive information.
Company 4: Company 4 works well with their supplier and there is little conflict. The relationship is important due to the high value of the contract and the two parties work together to meet the same goals. The KPI measures the exchanges and levels of collaboration between the parties.
Company 5: The supplier does not place much importance on the relationship with Company 5 due to the low value of the contract. Company 5 is worried that the supplier is not willing to invest in the contract and therefore are measuring the loyalty of the supplier as a KPI.
Complete the table below with the correct relationship type and relationship influencing KPI: nice, creative, marginal, hostile, partnership arm’s length, power, trust, co-operation, communication, commitment, transparency.
Which of the following will you put into box 8?
Below are details of five different companies and the data they collect. For each company, select the characteristic of the data collected and the business area it relates to.
Company 1: This company is collecting data which will assist in the designing of products- ensuring functionality at the lowest cost. The issue with the data is its seasonality.
Company 2: This company has a high number of data files. They are dismantling current ways of working to figure out if there is a more effective way to do things.
Company 3: Data collected by company 3 is collected at speed in real time. They are attempting to find any underlying patterns in the data to inform on better decision making.
Company 4: Company 4’s objective is to reduce the risk of exposure of the company to unforeseen events. Data is being collected in many different formats.
Company 5: This data is similar in format and content but is collected from a wide range of sources. The data looks at the costs and implications of raw materials used in production.
Complete the table below by listing the characteristic of the data and the corresponding business area (some options may be used twice); volume (x2), variety, velocity, variability, complexity, concurrent engineering, process design, statistical analysis, life cycle analysis, risk reduction, value engineering.
Which of the following will you put into box 1?
Pink Logistics is categorising the relationships it has with several suppliers. They have worked with Blue Trucks Ltd for seven years but the contract is of small value and therefore of little importance to Pink Logistics. There have been no issues of conflict during the lifetime of the contract and the relationship is transactional. According to the Relationship Interaction Matrix, how would the relationship between Pink Logistics and Blue Trucks Ltd best be characterised?
Below are details of 5 companies who are all embarking on the launch of a new product. For each company, you must decide which innovation tactic they are using and the priority for the new contract.
Company 1: The company aims to design the specification around customers’ requirements. They are keen to ensure a balance between costs and the service provided.
Company 2: This company attends regular conferences held by a professional body and will use the information discussed to inform upon the specification. They are keen to ensure sufficient interest from the marketplace so are placing a priority on networking at the conferences.
Company 3: There is a small group of internal stakeholders who meet regularly at Company 3 who discuss supply chain and organisational integration. The priority for the group is to ensure that the supplier of the new product’s raw materials meets the company’s standards for environmental protection.
Company 4: This company has regular phone calls with suppliers discussing ideas for the new product. Once the product is launched, the focus will be on ensuring that the supplier is held to account.
Company 5: Equipment has been loaned to a supplier to produce a prototype of the new product. The aim of the project is to ensure the supplier is capable of producing the components required for the product before the contract is signed.
Complete the table below by listing the innovation tactic and contract priority for each company; focus group, innovation council, technology transfer, collaboration, supplier forum, early supplier involvement, supplier development, balanced scorecard, contract management, selection, value for money, bidding.
Which of the following will you put into box 5?
Below are details of five different companies and the data they collect. For each company, select the characteristic of the data collected and the business area it relates to.
Company 1: This company is collecting data which will assist in the designing of products- ensuring functionality at the lowest cost. The issue with the data is its seasonality.
Company 2: This company has a high number of data files. They are dismantling current ways of working to figure out if there is a more effective way to do things.
Company 3: Data collected by company 3 is collected at speed in real time. They are attempting to find any underlying patterns in the data to inform on better decision making.
Company 4: Company 4’s objective is to reduce the risk of exposure of the company to unforeseen events. Data is being collected in many different formats.
Company 5: This data is similar in format and content but is collected from a wide range of sources. The data looks at the costs and implications of raw materials used in production.
Complete the table below by listing the characteristic of the data and the corresponding business area (some options may be used twice); volume (x2), variety, velocity, variability, complexity, concurrent engineering, process design, statistical analysis, life cycle analysis, risk reduction, value engineering.
Which of the following will you put into box 6?
Below are details of 5 companies who are all embarking on the launch of a new product. For each company, you must decide which innovation tactic they are using and the priority for the new contract.
Company 1: The company aims to design the specification around customers’ requirements. They are keen to ensure a balance between costs and the service provided.
Company 2: This company attends regular conferences held by a professional body and will use the information discussed to inform upon the specification. They are keen to ensure sufficient interest from the marketplace so are placing a priority on networking at the conferences.
Company 3: There is a small group of internal stakeholders who meet regularly at Company 3 who discuss supply chain and organisational integration. The priority for the group is to ensure that the supplier of the new product’s raw materials meets the company’s standards for environmental protection.
Company 4: This company has regular phone calls with suppliers discussing ideas for the new product. Once the product is launched, the focus will be on ensuring that the supplier is held to account.
Company 5: Equipment has been loaned to a supplier to produce a prototype of the new product. The aim of the project is to ensure the supplier is capable of producing the components required for the product before the contract is signed.
Complete the table below by listing the innovation tactic and contract priority for each company; focus group, innovation council, technology transfer, collaboration, supplier forum, early supplier involvement, supplier development, balanced scorecard, contract management, selection, value for money, bidding.
Which of the following will you put into box 7?
When a buyer and supplier use the same electronic system, what is this known as?
Wesley is putting together a Business Case to implement ' green ' procurement practices at his organisation. He is listing external drivers for sustainability- which of the following could he include within the list?
Jonah is looking at the relationship his organisation has with various suppliers. He is keen to work with a supplier on an upcoming project which is of high risk and requires a high degree of supplier responsibility. For this he is looking to select the right supplier. What type of development is this?
The SCAMPER technique suggested by Eberle (2018) provides suggestions on which of the following?