11.11 Big Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

PSP Planning & Scheduling Professional (PSP) Exam Questions and Answers

Questions 4

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

Options:

A.

Finish-no-earlier constraint on the first activity

B.

Finish-no-earlier constraint on the last activity

C.

Finish-no-later constraint on the last activity

D.

Start-no-later constraint on the first activity

Buy Now
Questions 5

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

Options:

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Buy Now
Questions 6

: 20

Constraints control events or activities that __________________.

Options:

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Buy Now
Questions 7

What problems can a soils engineer deal with on a project?

Options:

A.

Survey error.

B.

Hidden subsurface conditions.

C.

Archeological findings.

D.

Toxic soils.

Buy Now
Questions 8

At a minimum, periodic reporting must be done at what interval?

Options:

A.

Monthly.

B.

As requested by the project manager.

C.

As requested by the owner.

D.

As specified in the contract documents.

Buy Now
Questions 9

What is accurate about Activity 7001 in the precedence diagram?

Options:

A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Buy Now
Questions 10

For which of these delays should an owner grant a time extension?

Options:

A.

Structural steel shop drawings.

B.

Shop drawings and centrifuge delay.

C.

Differing site conditions at parking structure.

D.

Differing site conditions and centrifuge delay.

Buy Now
Questions 11

Estimate to complete (ETC) is __________________.

Options:

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work

Buy Now
Questions 12

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

Options:

A.

ADM is limited to finish-to-start logic relationships, while PDM is not.

B.

PDM is a bar chart with network logic, while ADM is a pure logic network.

C.

ADM is manual CPM calculations, while PDM is computerized.

D.

ADM uses arrows, while PDM uses boxes.

Buy Now
Questions 13

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

Options:

A.

91 days

B.

183 days

C.

145 days

D.

53 days

Buy Now
Questions 14

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

Options:

A.

$195 per day

B.

S1.772 per day

C.

General conditions do not need to be reduced to break even

D.

$1.223 per day

Buy Now
Questions 15

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Options:

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

Buy Now
Questions 16

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Buy Now
Questions 17

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Buy Now
Questions 18

What is the relationship depicted between Activity G and Activity H?

Options:

A.

You cannot tell with the supplied information.

B.

Start-to-start.

C.

Finish-to-start.

D.

Finish-to-finish.

Buy Now
Questions 19

The Baseline Plan does NOT reflect which of the following:

Options:

A.

scope of worn and work plans

B.

stakeholders deliverables

C.

approved budget

D.

schedule milestones

Buy Now
Questions 20

The Work Breakdown Structure (WBS) is established to reflect the:

Options:

A.

lowest level of the project estimate

B.

lowest level reporting back to the program WBS

C.

lowest level of effort scope

D.

lowest level where the work is managed

Buy Now
Questions 21

What is the free float for Activity F?

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Buy Now
Questions 22

Who can define KPls?

Options:

A.

The client and the performing/contracting entity

B.

Environmental regulators

C.

The subcontractors and suppliers

D.

Accounting and Finance

Buy Now
Questions 23

How much Total Float does drafting the product manual have?

Options:

A.

15 workdays.

B.

0 workdays.

C.

10 workdays.

D.

5 workdays.

Buy Now
Questions 24

Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

Options:

A.

After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B.

After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C.

After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Buy Now
Questions 25

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Buy Now
Questions 26

Using the normal schedule, what is the early finish date and total float of Activity 10002?

Options:

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Buy Now
Questions 27

Control Level Schedule activities are NOT one of the following:

Options:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

Buy Now
Questions 28

What is the result of a forward pass calculation?

Options:

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Buy Now
Questions 29

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Options:

A.

8 days

B.

6 days

C.

4 days

D.

5 days

Buy Now
Questions 30

How many work days does it take to move the product from testing to sale?

Options:

A.

60.

B.

70.

C.

100.

D.

90.

Buy Now
Questions 31

Should activities be coded with the EBS value?

Options:

A.

Yes. the project coding should roll up to EBS values

B.

No. only a few EBS values exist at the activity level

C.

No. the EBS Is much higher than activity coding

D.

Yes. the EBS is the most important project coding level

Buy Now
Questions 32

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

Options:

A.

Avoiding a late delivery penalty from the owner

B.

Maximizing the $500,000 bonus

C.

Avoiding the 2023-2024 winter/wet weather season

D.

Minimizing the indirect expenditure chargeable to the contractor

Buy Now
Questions 33

Identify the minimum project duration.

Options:

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.

Buy Now
Questions 34

Which of the following procedures is generally recognized as acceptable when updating a schedule?

Options:

A.

Report an actual date when the activity is on a non-work calendar for that date

B.

Change a previously reported actual date

C.

Change the WBS assignment for an activity

D.

Change a calculated date in the future

Buy Now
Questions 35

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Options:

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Buy Now
Questions 36

Time-scaled logic diagrams are

Options:

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Buy Now
Questions 37

What is a key first step in developing a critical path method schedule?

Options:

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

Buy Now
Questions 38

The Organizational Breakdown Structure (OBS) is a hierarchical structure that does NOT include which of the following:

Options:

A.

subcontractors

B.

stakeholders

C.

sub-subcontractors

D.

project director

Buy Now
Questions 39

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Buy Now
Questions 40

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

Options:

A.

Proceed with company processes even if they conflict with the client

B.

The client contract specifications always have priority

C.

Review any differences and negotiate workable specifications

D.

Suggest that the client issue a change order, accepting the contractor's processes

Buy Now
Questions 41

The schedule or budget at completion less the estimate at completion is___________.

Options:

A.

the schedule variance

B.

the variance at completion

C.

the cost variance

D.

the profit or loss for the project

Buy Now
Questions 42

Which of the following is NOT a tool or technique used to perform scope planning?

Options:

A.

Benefit cost analysis.

B.

Schedule performance indexing.

C.

Expert Judgment.

D.

Alternatives identification.

Buy Now
Questions 43

You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?

Options:

A.

Group schedule activities together based on their start dates

B.

Display detailed information regarding the sequencing of activities in the schedule

C.

Organize reports to group related work activities

D.

Display resources me contractor plans to use on each activity

Buy Now
Questions 44

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

Options:

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

Buy Now
Questions 45

At the end of month one, did the delay to the parking structure foundation delay the project?

Options:

A.

NO.

B.

Yes, by 4 calendar days.

C.

Yes, by 14 calendar days.

D.

Yes, by 9 calendar days.

Buy Now
Questions 46

NO: 98

The activity with the most total float is:

Options:

A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

Buy Now
Questions 47

What activities are concurrent to Activity 2001 in the "normal" schedule?

Options:

A.

7001.

B.

1001.

C.

1000.

D.

2003.

Buy Now
Questions 48

What is the remaining work duration of Active D?

Options:

A.

4.

B.

11

C.

8.

D.

3.

Buy Now
Questions 49

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Buy Now
Questions 50

EBS is an acronym for:

Options:

A.

Elongated Budget Synopsis

B.

European Basic Schedule

C.

Enterprise Breakdown Structure

D.

Eventual Base Structure

Buy Now
Questions 51

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

Options:

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don't follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

Buy Now
Questions 52

How could the structural steel drawing delay have been prevented?

Options:

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Buy Now
Questions 53

What project cost elements would NOT normally be reflected in the Activity 1000?

Options:

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Buy Now
Questions 54

The BEST reason to use multiple calendars is to:

Options:

A.

more accurately show how the project will be built

B.

allow each specialty contractor to have a unique schedule of work/non-work periods

C.

track owner activities according to their specific calendar in order to develop a good

working relationship

D.

evaluate float for the benefit of the contractor

Buy Now
Questions 55

Which of the following is NOT true?

Options:

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Buy Now
Questions 56

Determine the driving activity for Activity 10001.

Options:

A.

Activity 11001.

B.

Activity 10002.

C.

Activity 9005.

D.

There is no driving activity for Activity 10001 in the backward pass.

Buy Now
Questions 57

Free float is the

Options:

A.

Difference between the early dates and late dates of an activity.

B.

Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.

C.

Difference between the early finish dates and late finish dates of an activity.

D.

Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Buy Now
Questions 58

A KPI is an acronym for:

Options:

A.

Key Planning Index

B.

Known Planning Impediments

C.

Keep Parameter Integrity

D.

Key Performance Indicator

Buy Now
Questions 59

What owner action could have mitigated the late completion of the project?

Options:

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Buy Now
Questions 60

Schedule Risk may affect the following:

Options:

A.

Activity resource allocation

B.

Long-duration activities

C.

The final milestones phase milestones, critical and non-critical activities

D.

Calendar shifts

Buy Now
Questions 61

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

Options:

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Buy Now
Questions 62

When project risk is reflected in scheduled activities, what is the most significant characteristic of those activities?

Options:

A.

The level of resources available to the activity

B.

The Remaining Duration of the activity

C.

The criticality of toe activities

D.

The Late Start of the last activity in that float path

Buy Now
Questions 63

If Activity E's duration changes to 4 months, what is the overall duration of the project.

Options:

A.

19 months.

B.

20 months.

C.

22 months.

D.

21 months.

Buy Now
Questions 64

Is activity 7001 pictured correctly in the precedence diagram?

Options:

A.

No, the total float is not shown correctly.

B.

Yes, except the early finish date is not shown.

C.

No, the start-to-start and finish-to-finish relationships are backwards.

D.

Yes, the duration is 48 days.

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Nov 16, 2025
Questions: 216
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$30  $99.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99