If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Using the normal schedule, what is the early finish date and total float of Activity 10002?
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?
Which of the following procedures is generally recognized as acceptable when updating a schedule?
In a "crashed" schedule, which is a chain of activities that precede activity 2004?

The Organizational Breakdown Structure (OBS) is a hierarchical structure that does NOT include which of the following:
If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?
The schedule or budget at completion less the estimate at completion is___________.
Which of the following is NOT a tool or technique used to perform scope planning?
You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

At the end of month one, did the delay to the parking structure foundation delay the project?
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
What project cost elements would NOT normally be reflected in the Activity 1000?
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

When project risk is reflected in scheduled activities, what is the most significant characteristic of those activities?
If Activity E's duration changes to 4 months, what is the overall duration of the project.

Professional Level Certifications | PSP Questions Answers | PSP Test Prep | Physical Security Professional Exam Questions PDF | PSP Online Exam | PSP Practice Test | PSP PDF | PSP Test Questions | PSP Study Material | PSP Exam Preparation | PSP Valid Dumps | PSP Real Questions | Physical Security Professional PSP Exam Questions