Weekend Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

RCDDv14.1 BICSI Registered Communications Distribution Designer - RCDDv14.1 Questions and Answers

Questions 4

When should a program manager approve the closure of a component project?

Options:

A.

When acceptance criteria of the project are met

B.

When the project has delivered the protect benefits

C.

When program deliverables are complete

D.

When project deliverables are complete

Buy Now
Questions 5

When designing a video communications network, which type of video communication link is two-person videoconferencing?

Options:

A.

Point-to-multipoint bidirectional

B.

Point-to-multipoint unidirectional

C.

Unidirectional

D.

PTP unidirectional

E.

PTP bidirectional

Buy Now
Questions 6

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program. The benefits register should include which of the following?

Options:

A.

List of planned benefits, earned value (EV) and responsible person

B.

List of planned benefits, measurement method, and component mapping

C.

List of planned benefits, benefit creator and realization date

D.

List of planned benefits, stakeholders, and risk level

Buy Now
Questions 7

A project's closeout plan will be executed by the project manager (PM) and will be managed and approved by the

Options:

A.

owner

B.

contractor

C.

lCT distribution designer

D.

projects installation supervisor

Buy Now
Questions 8

Which two of the following components are included in a backbone distribution system (BDS)? (Choose two.)

Options:

A.

Work area outlets

B.

Telecommunications enclosures

C.

Equipment Cord

D.

Equipment rooms

E.

Horizontal Cable

Buy Now
Questions 9

A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component protect requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.

What is a critical component of the Program Schedule Management Process?

Options:

A.

A list of all the projects that team members are working on

B.

Activity or component start and finish dates, as well as intermediate milestones

C.

Time management training programs for all team members, as well as the project managers

D.

Skill levels of the various project team members, as well as the project managers

Buy Now
Questions 10

When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)

Options:

A.

handle only the day one needs as the future is unknown.

B.

minimize occupant disruption when horizontal pathways are accessed.

C.

handle at least 3 different cabling media types.

D.

accommodate cabling changes

E.

accommodate at least 50 percent future growth

Buy Now
Questions 11

A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete

What should the program manager do to understand the financial environment?

Options:

A.

Map costs to the expected benefits realization

B.

Establish intermediate budget based on historical information

C.

Establish program financial framework

D.

Obtain intermediate funding from the executive sponsor

Buy Now
Questions 12

The program manager takes over a poorly performing program After a review of the documentation and interviews with the program sponsor, stakeholders and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent protects and components to meet the program's needs

What action should the program manager take to realign the program?

Options:

A.

Assess the program schedule and determine how to maintain all projects and components within the program

B.

Discuss the situation with the program stakeholders and let them decide which projects to accelerate and which to close

C.

Discuss the situation with the program sponsor(s) and let the sponsor(s) make the decision as to which projects to accelerate and which to close

D.

Develop a change request to present to the governance board, accelerate some projects, close some projects and reassign some resources

Buy Now
Questions 13

The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.

Which of the following should the program manager do first?

Options:

A.

Direct the three project managers to crash their projects to allow project A the two months of scheduling needed

B.

Review the program resource management plan with the three project managers emphasizing their critical paths and shared critical resources to understand the possibility of accelerating the schedule

C.

Convene the change board to evaluate the cost benefit of the compression and the impact on the overall program

D.

Engage the executive sponsor and program board to evaluate the CEO's request and determine if the project manager should act on it

Buy Now
Questions 14

What is the MAXIMUM length of continuous conduit allowed before a pull point or pull box needs to be installed?

Options:

A.

≈15.20 m (50 ft)

B.

≈22.90 m (75 ft)

C.

≈30.50 m (100 ft)

D.

≈45.70 m (150 ft)

Buy Now
Questions 15

A company CEO meets with key customers to learn how they can be better served Alter discovering that some executive team members disagree with each other, the CEO asks the program management office (PWO) to develop a program to better serve key customers based on their strategic importance to the company's long-term goals.

What should the program manager do to establish and successfully manage the program's direction?

Options:

A.

Create a program strategy to obtain the required funding from the portfolio decision team

B.

Develop and foster relationships with stakeholders to improve communication

C.

Conduct stakeholder interviews to address their concerns and expectations

D.

Identify a list of projects, and then assign them suitable project managers

Buy Now
Questions 16

A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment and is intolerant of processes to the point of being considered process-adverse However, the company's culture is tolerant of long-term program activities, and provided there is continuous progress on improving the protection of its intellectual property Expectations for rapid progress are low

What should the program manager do next?

Options:

A.

Tailor program sponsor and stakeholder engagement and communications activities to meet the company's expectations.

B.

Insist on maintaining a set of tightly controlled stakeholder register and engagement plan documents to meet expectations

C.

Provide detailed information to the most influential program sponsors and stakeholders

D.

Ensure that the component stakeholders have the appropriate level of communications required to meet their needs

Buy Now
Questions 17

A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap which consists of six program components Approval from the program governance board has been obtained.

What is the program manager's next step?

Options:

A.

Assign project managers and resources

B.

Classify the program's benefits

C.

Identify the program sponsor and program stakeholders

D.

Develop the program business case

Buy Now
Questions 18

What is used to facilitate MINOR changes to the Project Requirements?

Request lot Information (RFI)

Options:

A.

Punch list

B.

Field order

C.

Change order

D.

Change order request

Buy Now
Questions 19

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

Options:

A.

Program performance report

B.

Communications management plan

C.

Communications log updates

D.

Information gathering and retrieval system

Buy Now
Questions 20

A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams.

Some potential stakeholders have conflicting program expectations

What should the program manager do next/?

Options:

A.

Conduct interviews with key stakeholders, and document the results in the program management plan

B.

Update the stakeholder register to document stakeholders' positions relative to the program

C.

Document stakeholder expectations in the program's risk register to determine their influence

D.

Send out satisfaction surveys and document the results in the program's stakeholder engagement plan.

Buy Now
Questions 21

Coupling with electrical circuits can create inductive interference to telecommunications facilities. Which of the following can decrease the coupling effect?

Options:

A.

Decrease the exposure length

B.

Make sure that the single-phase components add in phase

C.

Decrease the physical separation

D.

Increase the earth resistance

Buy Now
Questions 22

The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee

What do the current findings show?

Options:

A.

Project C is running behind schedule and is over budget, projects A, B and D are on schedule

B.

Project A is running ahead of schedule and is under budget projects B, C and D are behind schedule

C.

The overall program is performing within an acceptable level of variance

D.

Project A is running behind schedule and is over budget projects B, C. and D are on schedule

Buy Now
Questions 23

How does a portfolio’s collection of work differ from that of a program's collection of work?

Options:

A.

Outcomes are interdependent

B.

Benefits are achieved only when managed collectively

C.

Components may be independent

D.

Outcomes are time bound

Buy Now
Questions 24

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000

Based on this information, the program manager determines which of the following?

Options:

A.

The schedule is US%30.000 under budget

B.

The cost is US$20.0O0 under budget

C.

The schedule is US$10.000 over budget

D.

The cost is USS20.000 over budget

Buy Now
Questions 25

A commercial office building floor has a usable floor space of ≈1858 m2 (20,000 ft2). What is the MINIMUM number of 103 mm (4 trade size) conduits that shall be required to interconnect the telecommunications rooms on this floor?

Options:

A.

0

B.

1

C.

2

D.

3

Buy Now
Questions 26

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.

What should be done with the identified potential risk?

Options:

A.

Incorporate it into the risk register and perform a thorough analysis

B.

Mitigate the risk before it is incorporated into the risk management plan

C.

Document the risk in the program transition plan and identify it as a potential issue

D.

Document it m the issue log and immediately notify the steering committee

Buy Now
Questions 27

Which service is NOT typical of Grade 1?

Options:

A.

Telephone

B.

Multimedia

C.

Data

D.

Television

Buy Now
Questions 28

Identify the fibers below as either single mode (SM) or multi-mode (MM) by dragging the appropriate term into each oval.

Options:

Buy Now
Questions 29

A system integration approach of a BAS on to a LAN can usually reduce the cost of cabling-related changes by

Options:

A.

10 to 20 percent

B.

25 to 40 percent

C.

45 percent

D.

50 percent

Buy Now
Questions 30

During program execution, how does a program manager ensure that benefits are being realized in accordance with program governance*?

Options:

A.

By reviewing the benefits management plan

B.

By updating the benefits register

C.

By conducting benefits analysis and planning

D.

By reviewing the program business case

Buy Now
Questions 31

In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.

To assure positive performance in the current environment, the program manager should do which of the following?

Options:

A.

Ensure the new processes will perform better than the current processes

B.

Ask the program steering committee to endorse the new processes and current program schedule and deliverables

C.

Meet with stakeholders to ensure they understand that the expectations for the new processes are superior to the current processes

D.

Discuss concerns with stakeholders and mitigate them by changing the processes that will be delivered

Buy Now
Questions 32

Which of the following is the process of limiting fire and smoke using fire-resistive barriers?

Options:

A.

Detection

B.

Compart mentation

C.

Suppression

D.

Prevention

Buy Now
Questions 33

A program management team is invited to a company's annual strategy planning session The CEO discusses the mission and vision of the organization, and how the strategic plan will create opportunities to fulfill them

How can the program manager use the company's vision to establish a program?

Options:

A.

Define the program and component projects to enable the fulfillment ol strategic goals

B.

Set the priority matrix and map the projects" priorities that will be included in the program

C.

Define the program roadmap, and highlight the individual protects' benefits

D.

identity program benefits that will enable the fulfillment of strategic goals

Buy Now
Questions 34

Using an earth ground resistance tester, what is the recommended MAXIMUM value for resistance between any two points along the entire length of a bonding or grounding conductor (not including the earth electrode system)?

Options:

A.

0.10 ohm

B.

0.25 ohm

C.

0.50 ohm

D.

1 ohm

E.

2 ohms

Buy Now
Questions 35

A program manager learns that their company's organizational strategy has changed This change impacts one component project of a program misaligning it with both the program objectives and the new organizational strategy This component project, however, is already 90 percent complete.

What should the program manager do next?

Options:

A.

Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.

B.

Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board

C.

Recommend that the component project manager complete work activity to deliver benefits to the organization

D.

Update the benefits management plan to reflect the impact of the change on the program and its intended benefits

Buy Now
Questions 36

A two-year program is coming to an end Many of the initial governance board members have moved from their current posts or left the company Several new members have joined but have a shod association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.

How should the program manager handle this situation?

Options:

A.

Review the final program outcome with the program sponsor

B.

Prepare a program change request utilizing new board member input

C.

Review the strategic plan and benefits management plan with the board

D.

Present the final program status, costs, and schedule reports

Buy Now
Questions 37

Program manager B leaves the program and program manager A takes over the program responsibilities Program manager A wants to ensure that all expected benefits of the program are realized.

What is used to assess the program cost/benefit justification?

Options:

A.

Program charter

B.

Benefits management plan

C.

Program business case

D.

Program scope statement

Buy Now
Questions 38

Which of the following is a method that an ICT distribution designer would use for clash detection with other disciplines?

Options:

A.

Statistical Quantitative Analysis

B.

Interference Fit Verification

C.

ICT pathway design

D.

Building Information Modeling Coordination

Buy Now
Questions 39

The transfer of unwanted signals may occur over one path or several paths. What method addresses the mitigation or suppression of unwanted signals?

Options:

A.

Mounting heights in racks and cabinets

B.

Bonding and grounding

C.

Signal coupling

D.

The use of unshielded cables

Buy Now
Questions 40

Exhibit:

What does this international symbol stands for?

Options:

A.

Teletypewriter/text telephone

B.

Public internet station

C.

Public telephone

D.

Public telephone with a shelfette

E.

Public telephone with access to high-speed internet connection

Buy Now
Questions 41

A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?

Options:

A.

Update the program stakeholder engagement plan with stakeholders from the transition organization

B.

Define the component protects business value in the benefits management plan

C.

Update the program roadmap to reflect completion of a key end-point objective

D.

Initiate a program change request to close out the component project

Buy Now
Questions 42

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program

As a result, the program manager must do which of the following'?

Options:

A.

Utilize team members that are currently available, even though they do not have the expertise needed.

B.

Assign the tasks on the critical path to the resources available to adhere to the project schedule

C.

Delay the start of the program until the assigned resources are available

D.

Apply resource leveling considering the constraints of time, budget, and quality

Buy Now
Questions 43

When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)

Options:

A.

Request a Change Order from the client for the extra work performed.

B.

Document the reviewer's status and/or comments

C.

Review the contract requirements and revise the submittal to comply with these requirements

D.

Request a variance from the contract requirements from the client.

E.

Submit an alternate product in lieu of one that was previously submitted, even if it does not meet all of the contract requirements

Buy Now
Questions 44

The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter What increase in usable floor space should another 103 mm (four trade size) sleeve be added?

Options:

A.

=929 m2 (10,001 ft2)

B.

=1858m2 (20,001 ft2)

C.

=3716 m2 (40,001 ft2)

D.

=4645 m2 (50,001 ft2)

Buy Now
Questions 45

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate reviews.

What should the program manager do next?

Options:

A.

Ask the stakeholders what they want and proceed with their recommendations

B.

Agree with the customer and Initiate change control procedures

C.

Continue periodic gate reviews to maintain program effectiveness for benefits realization

D.

Replace program reviews with periodic communications of the program's status

Buy Now
Questions 46

For a cable tray installed within an ER, the RECOMMENDED access headroom is:

Options:

A.

≈ 152 mm (6 in).

B.

≈ 203 mm (8 in).

C.

≈ 254 mm (10 in).

D.

≈ 305 mm (12 in).

Buy Now
Questions 47

A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program's completion date

What is the next step for the program manager?

Options:

A.

Apply resource leveling to ensure the program is completed on schedule

B.

Update the schedule to reflect the extended completion date

C.

Adjust working hours to ensure the program is completed on schedule

D.

Submit a change request to extend the program schedule

Buy Now
Questions 48

A company is evaluating the implementation of enterprise resource planning (ERP) software.

The program manager performs an analysis to confirm the program's feasibility

What other important step should the program manager complete^

Options:

A.

Development of the program's vision statement

B.

Review of strategic goals against any external environmental factors

C.

Identification and documentation of the initial risks for ERP software Implementation

D.

Mapping of the financial benefits to the ERP software's functionality

Buy Now

RCDD |

Exam Code: RCDDv14.1
Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14.1
Last Update: May 16, 2024
Questions: 320
RCDDv14.1 pdf

RCDDv14.1 PDF

$28  $80
RCDDv14.1 Engine

RCDDv14.1 Testing Engine

$33.25  $95
RCDDv14.1 PDF + Engine

RCDDv14.1 PDF + Testing Engine

$45.5  $130