A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?
A user wants to notify a team of a new work request for them to work on.
Where would the user set the team so they are notified of the new work request?
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.
What action should the task owner take?
Which date type should an assignee update to change the completion date of a task?
A team member needs to review all records showing charges, payments, and invoicing details for a specific project.
Which section in Workfront should they access to locate this information?
Which group of project elements can be used to monitor an active project’s progress?
Which project status will default the automatic Project Condition to “On Time”?
A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.
What steps should the project manager take to create a custom Workfront report with this information?
A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?
The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?
Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?
A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?
A project manager is assigned to a new Workfront request. The request specifies that the management team’s sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
A user wants to know if a task is pending approval.
Which task field would the user review?
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads " Project cannot be marked Complete if there are open issues and tasks that are not complete. " How can the Project Owner determine which tasks are incomplete?
A client has negotiated a discounted billing rate for video editing in a specific initiative.
How can the project manager override the default billing rate for the Video Editor within a project?
Which field is used to create a milestone step on a milestone path in the Setup area?
A project manager is managing a project and realizes a task is delayed. They want to see how downstream tasks are impacted.
Which feature of the Gantt chart will help them understand this?