Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

AD0-E911 Adobe Workfront Project Manager Certified Professional Questions and Answers

Questions 4

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

Options:

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Buy Now
Questions 5

A user wants to notify a team of a new work request for them to work on.

Where would the user set the team so they are notified of the new work request?

Options:

A.

Request > Request Details

B.

Request > Updates

C.

Request > Assignments

Buy Now
Questions 6

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Options:

A.

Actual Completion Date

B.

Progress Status

C.

Status

Buy Now
Questions 7

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a Project report. In the filter, update the actual completion date value to " past year " and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select " month. "

B.

Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select " month of year. "

C.

Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to " past year " and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select " month of year. "

Buy Now
Questions 8

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Options:

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible

Buy Now
Questions 9

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Buy Now
Questions 10

Which aspect of a project determines the Progress Status?

Options:

A.

Timeline

B.

Critical Path

C.

Milestone Tasks

Buy Now
Questions 11

Which date type should an assignee update to change the completion date of a task?

Options:

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date

Buy Now
Questions 12

A team member needs to review all records showing charges, payments, and invoicing details for a specific project.

Which section in Workfront should they access to locate this information?

Options:

A.

Project Details

B.

Billing Records

C.

Expenses

Buy Now
Questions 13

Which group of project elements can be used to monitor an active project’s progress?

Options:

A.

Gantt chart, project Condition, and Metrics

B.

Risks, planned hours, and resource utilization

C.

Project status, Updates, and Sharing

Buy Now
Questions 14

Which project status will default the automatic Project Condition to “On Time”?

Options:

A.

Idea

B.

Planning

C.

On Hold

Buy Now
Questions 15

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

Options:

A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.

B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.

C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.

Buy Now
Questions 16

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

Options:

A.

The next team member cannot start his task.

B.

No impact as the task is not overdue.

C.

The project shows an At Risk automatic condition.

Buy Now
Questions 17

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.

B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.

C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.

Buy Now
Questions 18

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

Options:

A.

Utilization section

B.

Hours tab

C.

Finance section

Buy Now
Questions 19

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Buy Now
Questions 20

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

Options:

A.

Status

B.

Condition

C.

Progress Status

Buy Now
Questions 21

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Options:

A.

Projected Date

B.

Planned Date

C.

Estimated Date

Buy Now
Questions 22

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

Options:

A.

Assigned To

B.

Assignments

C.

Assigned

Buy Now
Questions 23

A project manager is assigned to a new Workfront request. The request specifies that the management team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

Options:

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Buy Now
Questions 24

A user wants to know if a task is pending approval.

Which task field would the user review?

Options:

A.

Status

B.

Critical Path

C.

Priority

Buy Now
Questions 25

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads " Project cannot be marked Complete if there are open issues and tasks that are not complete. " How can the Project Owner determine which tasks are incomplete?

Options:

A.

There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

B.

There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.

C.

The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

Buy Now
Questions 26

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

Options:

A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.

B.

Add a new billing rate to all tasks that involve video editing.

C.

Add a new billing rate within the project.

Buy Now
Questions 27

Which field is used to create a milestone step on a milestone path in the Setup area?

Options:

A.

Status

B.

Description

C.

Key

Buy Now
Questions 28

A project manager is managing a project and realizes a task is delayed. They want to see how downstream tasks are impacted.

Which feature of the Gantt chart will help them understand this?

Options:

A.

Actual Dates

B.

% Complete

C.

Critical Path

Buy Now
Exam Code: AD0-E911
Exam Name: Adobe Workfront Project Manager Certified Professional
Last Update: Jun 9, 2026
Questions: 0
AD0-E911 pdf

AD0-E911 PDF

$25.5  $84.99
AD0-E911 Engine

AD0-E911 Testing Engine

$30  $99.99
AD0-E911 PDF + Engine

AD0-E911 PDF + Testing Engine

$255  $850