A data center has its own power supply from the public utility and receives chilled water supply from the building owner.
What needs to be taken into consideration when calculating the PUE?
You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?
What is the floor loading requirement for a Rated-3 data center according to ANSI/TIA-942?
EMF shielding material needs to be installed as EMF levels from the transformer room into the computer room are measured at 100 mG. The transformer room is ~10 meters away, separated by a corridor. Where should shielding be installed?
What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?
What is the calculation for the desired attenuation factor for shielding material?
A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.
The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.
The exhaust temperature is 29 °C/84 °F and 45% RH.
The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.
The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.
Analyze the situation and indicate what the most likely cause is for this server to crash.
What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?
The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

Which efficiency indicator accounts for all cooling costs (installation, operation, disposal)?
Which gas-based system in general requires a larger amount of gas in order to be effective, a halocarbon gas-based fire suppression system or an inert gas-based fire suppression system?
A data center scores Rated-3 in mechanical, Rated-4 in electrical, and Rated-2 in architectural.
What is the overall Rating of this data center when the Rating is based on the ANSI/TIA-942?
An air-conditioner unit needs to be selected. Two types are available:
Unit-A has a Sensible Heat Ratio (SHR) of 0.7.
Unit-B has a Sensible Heat Ratio (SHR) of 0.9.
From an efficiency point of view, which one should be selected?
From the options indicated, what is the correct starting point for the raised floor installation?

You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.
Which location for the temperature/humidity measurement should you recommend for the audit?
The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.
What would be the best option?
What is the risk of high levels of hydrogen sulfide (H₂S) in the computer room?
You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.
What should you recommend?
A data center is in an area where utility power is highly available—only a few outages per year, typically <1 hour per event and <50 hours/year not available. What type of generators should be installed?
The temperature in the computer room is being increased from 18°C/64°F to 27°C/81°F.
What is the impact, if any, on the amount of gas required to suppress a fire assuming the gas is a Halocarbon?
FM-200 is phasing out as a halocarbon gas and management has decided to replace this with the more environmentally friendly Novec-1230 gas. Should you use exactly the same formula and parameters to calculate the gas content for the Novec-1230 gas?
Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
•Rated power: 30 kVA
•Rectifier input voltage: 400 V/3 phase
•Rectifier input power factor: 0.8
•Battery rated voltage: 384 V
•Number of cells: 192
•End of discharge voltage: 308 V
•Inverter output voltage: 400 V/3 phase
•Inverter output power factor: 0.8
What information is missing to perform the battery calculation?
When designing a data center network, your company wants to minimize the number of network cables to install. What type of physical cabling layout would be the best choice?
A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.
What type of generators should be installed?