A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?
In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?
When eliciting requirements, a good time to consider using the interviewing method is when:
A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.
What would be the most viable technique to use in this scenario?
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?
A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation
process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume
reporting required by the company's financial department. The business analyst for the project determines that the selection criteria
needed was not specified in the system requirements or design specifications.
Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement
was missed?
An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.
What analysis should the business analyst conduct to facilitate a successful migration?
A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.
Which technique will allow the business analyst to determine this information?
A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.
What technique could the business analyst use to help alleviate this concern?
What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?
Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.
Which type of elicitation technique did the business analyst use in this instance?
A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.
Which analysis technique has the business analyst used?
After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?
A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.
Which critical field is needed to ensure that the traceability matrix is usable?
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.
How can the business analyst determine how well the solution meets the business case?
The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.
Which course of action should the business analyst take?
Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?
A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?
Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:
A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:
Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?
A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.
The business analyst should:
A company is in the final phases of implementing a project for a client. Which tool or technique could the business analyst use to iteratively validate the solution?
A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.
The customer is having difficulty determining if the product is meeting the requirements during the test event because the:
A business analyst has been asked to investigate a problem. This investigation will provide input towards developing a business case. The business analyst wants to first understand the company's current business processes.
Which technique should the business analyst use?
A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.
Which technique or tool should be used?
A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?
A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.
Which key factor drives the selection of business analyst activities to be included in the project?
A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.
Which of the following is the best strategy to define the appropriate acceptance criteria?
A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?
A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?
A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.
Which of the following components will the business analyst use as input to the business case?
Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.
What should the business analyst have documented?
The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client's business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.
Which technique is being used?
A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may
face monetary penalties.
What should the business analyst do next?
The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.
Which technique should the business analyst have followed to ensure consensus?
A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.
This problem could have been avoided by:
A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.
How would the business analyst define the scope of this project?
Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?
Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?
The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.
What should the business analyst have done to complete this request?
Which of the following actions will contribute most to the success of the initial stage of the project?
During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.
Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?
The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?
During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.
Which corrective action should the business analyst take?
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be
reported.
What should the business analyst use?
The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?
A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?
The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?
PMI Professional in Business Analysis | PMI-PBA Questions Answers | PMI-PBA Test Prep | PMI Professional in Business Analysis (PMI-PBA) Questions PDF | PMI-PBA Online Exam | PMI-PBA Practice Test | PMI-PBA PDF | PMI-PBA Test Questions | PMI-PBA Study Material | PMI-PBA Exam Preparation | PMI-PBA Valid Dumps | PMI-PBA Real Questions | PMI Professional in Business Analysis PMI-PBA Exam Questions