C_TS412_1909 SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Questions 4

What could be a reason to use expert mode in the valuation method for results analysis?

Options:

A.

Billing WBS elements belonging to different company codes

B.

Assignments of different accounts for postings to financial accounting

C.

Usage of different line ID

D.

Valuation in different currencies

Buy Now
Questions 5

Material

How can the system activate requirements (such as reservations or purchase requisitions)?

Note: There are 2 correct answers to this question

Options:

A.

Immediately, by saving the project

B.

Automatically, using the requirement date and the replenishment lead time

C.

Using a standard milestone activity

D.

When releasing a network or an activity

Buy Now
Questions 6

How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question

Options:

A.

By searching for the status profile

B.

By searching via status selection profile

C.

By searching via status combination code

D.

By searching for the individual status

Buy Now
Questions 7

Cost & Budget.

A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

Options:

A.

Settlement rules

B.

Costing Sheet

C.

Investment profile.

D.

Results analysis key

Buy Now
Questions 8

You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

Options:

A.

Maintain subordinate internal activity elements assigned to other work centres

B.

Increase the capacities of the work center in the project planning board.

C.

Trigger automatic capacity leveling inside the project planning board

D.

Shift activities backward or forward on the time axis where more capacities are available

Buy Now
Questions 9

Resources

Which of the following transactions can you use to post actual cost for external processing.

Note : there are 2 correct answer for this question.

Options:

A.

Approval of a service entry sheet

B.

Posting a goods receipt

C.

Creating a service entry sheet

D.

Approval of a good receipt.

E.

Creating a purchase order.

Buy Now
Questions 10

Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

Options:

A.

In the project profile

B.

In the project version

C.

In the project type

D.

In the project definition of a standard WBS

E.

In the operative WBS element

Buy Now
Questions 11

A service company uses project management and they complain that the system does not prevent

their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

Options:

A.

Activate availability control for the WBS elements. Define the tolerance limits on each WBS element

B.

Activate availability control in the assigned budget profile. Define the tolerance limits in customizing

C.

Activate commitment management in the project definition Enter the budget in the master data of the top WBS element

D.

Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Buy Now
Questions 12

Material

Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement

scheduling of events.

What is the requisites for implement scheduling of events?

Options:

A.

Priority of events must be set.

B.

Scheduling parameters for material scheduling must be set.

C.

Events must be released manually.

D.

Event scenarios must be defined.

Buy Now
Questions 13

Project structure

You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?

Note : there are 3 correct answer for this question.

Options:

A.

Project milestone

B.

Standard network

C.

Standard Project definition

D.

Project version.

E.

Project definition

Buy Now
Questions 14

A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question

Options:

A.

Resource reports

B.

Cost element reports

C.

Structure information system reports

D.

Hierarchical reports

Buy Now
Questions 15

What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question

Options:

A.

Confirm production order

B.

Stock transfer posting

C.

Generate purchase requisition

D.

Generate delivery

E.

Cancel goods issue

Buy Now
Questions 16

Cost and budget

A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do

not want to produce..

Which setup do you recommend?

Options:

A.

Assign a sales order to a project with appropriate hierarchy levels.

B.

Assign a network to a sales order

C.

Assign Several production orders to a sales order

D.

Assign One production order to a sales order

Buy Now