New Year Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

CDT Construction Documents Technologist Questions and Answers

Questions 4

Which construction agreement provision establishes the duration of the work or a specific date when the owner can occupy the project completely or partially for its intended use?

Options:

A.

Cutoff date

B.

Date of commencement of the work

C.

Date of substantial completion

D.

Scope of work

Buy Now
Questions 5

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Buy Now
Questions 6

Which party has the ultimate authority to approve a change order?

Options:

A.

Architect/engineer

B.

Contractor

C.

Owner

D.

Construction manager

Buy Now
Questions 7

Which of the following establishes a baseline from which deviations are identified?

Options:

A.

General requirements

B.

Supplementary conditions

C.

Project manual

D.

General conditions

Buy Now
Questions 8

Which of the following is an example of preconstruction submittals?

Options:

A.

Product data

B.

Shop drawings

C.

Schedule of values

D.

Warranty documentations

Buy Now
Questions 9

When innovative or unusual design techniques are proposed, it is advised to have what type of review?

Options:

A.

Sustainability

B.

Budget

C.

Constructability

D.

Design

Buy Now
Questions 10

During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?

Options:

A.

Allowances

B.

Unit prices

C.

Unknown factors

D.

Alternates

Buy Now
Questions 11

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

Options:

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Buy Now
Questions 12

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

Options:

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Buy Now
Questions 13

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

Options:

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

Buy Now
Questions 14

During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?

Options:

A.

After the authorities having jurisdiction issues a permit

B.

Closeout phase

C.

Preconstruction phase

D.

Construction phase

Buy Now
Questions 15

Standards for sustainable facilities, products, and fundamental approaches emphasize the needs of what?

Options:

A.

Architect, supplier, and contractor

B.

Owner, stakeholders, and participants

C.

Public, private, and environmental health

D.

Owner team, contractor team, and design team

Buy Now
Questions 16

Within a project budget, which item falls into the category of a hard cost?

Options:

A.

Architect/engineer design fees

B.

Commissioning fees

C.

Project financing

D.

Land acquisition

Buy Now
Questions 17

During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?

Options:

A.

Solicitation

B.

Instructions for Procurement

C.

Instructions to Bidders

D.

Request for Scope of Work

Buy Now
Questions 18

The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as "taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances" is known by what term?

Options:

A.

Professional standard of care

B.

Due diligence

C.

Performance based requirement

D.

Spearin doctrine

Buy Now
Questions 19

Who is responsible for accepting and inspecting for damage of the owner-furnished products delivered to the project site?

Options:

A.

Contractor

B.

Installer

C.

Owner

D.

Subcontractor

Buy Now
Questions 20

Which document obligates the architect/engineer to review submittals during construction administration?

Options:

A.

AIA Document A201, General Conditions of the Contract for Construction

B.

AIA Document B101, Standard Form of Agreement Between Owner and Architect

C.

AIA Document D200, Project Checklist

D.

AIA Document G612, Owners Instructions to the Architect

Buy Now
Questions 21

Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?

Options:

A.

Conformed set

B.

Record set

C.

Change order log

D.

Request for information documents

Buy Now
Questions 22

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

Options:

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Buy Now
Questions 23

An architect/engineer wants to schedule monthly meetings with a contractor and owner to discuss matters pertinent to timely and successful completion of the work. Which type of meeting should they schedule?

Options:

A.

Workflow meeting

B.

Preinstallation meeting

C.

Progress meeting

D.

Schedule monitoring meeting

Buy Now
Questions 24

What is a primary disadvantage in using the design-bid-build method?

Options:

A.

It attracts too many bidders

B.

All of the bids may exceed the owner's budget

C.

It requires a higher level of bid document quality

D.

It reduces the owner's control over the project during the construction phase

Buy Now
Questions 25

An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?

Options:

A.

There was active interference by the owner.

B.

There were conditions beyond the control of the contractor or owner.

C.

The A/E modified the contract documents.

D.

There is defective work needing repair.

Buy Now
Questions 26

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Buy Now
Questions 27

Which party is usually required to maintain record drawings during the project according to the Project Delivery Practice Guide?

Options:

A.

Architect

B.

Contractor

C.

Owner

D.

Authority having jurisdiction

Buy Now
Questions 28

Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?

Options:

A.

Warranty of title

B.

Implied warranty of merchantability

C.

Purchase warranty

D.

Extended warranty

Buy Now
Questions 29

Which of the following is a scaled view?

Options:

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Buy Now
Questions 30

Which of the following is an example of quality assurance?

Options:

A.

Performing compaction testing

B.

Field observations

C.

Validating quantities for payment

D.

Scheduling and sequencing of the work

Buy Now
Questions 31

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Buy Now
Questions 32

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

Options:

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Buy Now
Questions 33

What four considerations are included in site selection programming?

Options:

A.

Use, space, funds, date

B.

Function, form, economy, time

C.

Purpose, shape, cost, schedule

D.

Goal, condition, budget, calendar

Buy Now
Questions 34

Who is responsible for job site security?

Options:

A.

Owner

B.

Architect/engineer

C.

Contractor

D.

Construction manager

Buy Now
Questions 35

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Buy Now
Questions 36

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: Jan 2, 2026
Questions: 120
CDT pdf

CDT PDF

$25.5  $84.99
CDT Engine

CDT Testing Engine

$30  $99.99
CDT PDF + Engine

CDT PDF + Testing Engine

$40.5  $134.99