Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

Buy Now
Questions 5

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Options:

A.

Adopt a predictive approach to manage the risks.

B.

Adopt agile approaches to manage the risks.

C.

Utilize proper documentation to help manage the risks.

D.

Conduct weekly risk management meetings with all stakeholders.

Buy Now
Questions 6

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Buy Now
Questions 7

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Buy Now
Questions 8

A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

What should the project manager do next to determine risk impact of assumptions and constraints?

Options:

A.

Add all assumptions and constraints to the risk register.

B.

Add the risk impact of the assumptions in the risk register.

C.

Add the assumptions and constraints to the assumption log.

D.

Add the assumptions and constraints in the project charter.

Buy Now
Questions 9

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

Options:

A.

Document the concern over the potential excessive additional cost.

B.

Manage the potential excessive additional cost as a new risk.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

 

Buy Now
Questions 10

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?

Options:

A.

Sensitivity analysis

B.

simul-ation analysis

C.

Monte Carlo simul-ation

D.

Quantitative analysis

Buy Now
Questions 11

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Options:

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Buy Now
Questions 12

A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.

What should the risk manager do?

Options:

A.

Increase the residual risk monitoring.

B.

Increase the inherent risk monitoring.

C.

Reassess the inherent risk level.

D.

Reassess the residual risk level.

Buy Now
Questions 13

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Options:

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.

D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Buy Now
Questions 14

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Buy Now
Questions 15

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered.

 

Buy Now
Questions 16

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project

 

Buy Now
Questions 17

In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

Options:

A.

Probabilistic and quantitative risk analyses to get the overall risk score

B.

Quantitative risk analysis to get the overall risk score

C.

Probabilistic risk analysis to get the overall risk score

D.

Qualitative risk analysis to get the overall risk score

 

Buy Now
Questions 18

Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simu-lation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.

Which tool should the risk manager consider for assessing the test risk?

Options:

A.

Scenario analysis

B.

Sensitivity analysis

C.

Probability and impact matrix

D.

Monte Carlo simul-ation

 

Buy Now
Questions 19

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

Options:

A.

Enhance the process of identification of different Individual project risks.

B.

Allows monitoring the impact against the overall project risk exposure.

C.

Establishes risk sources and ownership for trigger monitoring.

D.

Creates a single repository for all project risk documents.

Buy Now
Questions 20

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Buy Now
Questions 21

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?

Options:

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

Buy Now
Questions 22

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis.

 

Buy Now
Questions 23

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.

Project contracts

B.

Lessons learned registers from analogous projects

C.

Risk register

D.

Risk management plan

E.

Code of regulations

Buy Now
Questions 24

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

Options:

A.

Perform a probability and impact assessment

B.

Perform Monte Carlo simul-ations

C.

Perform a sensitivity analysis

D.

Perform a risk data quality assessment

Buy Now
Questions 25

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Buy Now
Questions 26

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Buy Now
Questions 27

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project's total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Options:

A.

Activity 3.2

B.

Activity 2.3

C.

Activity 3.5

D.

Activity 1.2

Buy Now
Questions 28

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account.

 

Buy Now
Questions 29

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Buy Now
Questions 30

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact

 

Buy Now
Questions 31

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:

A.

Risk management plan

B.

Clients' credit scores

C.

Organization's mission and vision

D.

Historical data from the credit portfolio

Buy Now
Questions 32

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

Buy Now
Questions 33

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Options:

A.

Establish a formal and upfront risk identification process.

B.

Use a detailed and quantitative risk assessment process.

C.

Create an effective and clear risk communication process.

D.

Adopt a dynamic and frequent risk management process.

Buy Now
Questions 34

A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.

What is the first resource the project manager should reference?

Options:

A.

Benefits management plan

B.

Enterprise environmental factors (EEFs)

C.

Project charter

D.

Requirements management plan

Buy Now
Questions 35

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

Options:

A.

Applying modern risk management techniques.

B.

Aligning to project constraints and priorities.

C.

Ensuring risk response strategies mitigate all risks.

D.

Minimizing implementation costs.

E.

Obtaining stakeholder acceptance

Buy Now
Questions 36

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

Options:

A.

Confirm the risk triggers are still valid.

B.

Ask the architect to develop acceptance criteria.

C.

Review the feature with the project team.

D.

Escalate the issue to the project board.

Buy Now
Questions 37

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Options:

A.

Exclude risk averse stakeholders from future risk discussions

B.

Explain risk handling and mitigation strategies

C.

Increase the impact of all risks in the risk breakdown structure (RBS)

D.

Develop a generous probabilistic cash flow model

Buy Now
Questions 38

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

Options:

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

Buy Now
Questions 39

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project

B.

By helping to determine the overall project risks

C.

By helping the lessons learned from previous risks to be efficiently utilized

D.

By helping to update the project scope statement document

E.

By helping update the risk register and close out expired risks

 

Buy Now
Questions 40

A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.

What should the risk manager do to address this situation?

Options:

A.

Implement a disciplined tracking method and report to stakeholders accordingly.

B.

Call for a project team meeting to review risk strategies and make required adjustments.

C.

Escalate the staffing topic to the sponsor and request more budget for contingencies.

D.

Revisit the project charter for scope adjustments and sign them off with the customer.

Buy Now
Questions 41

What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

Options:

A.

Organizational communication requirements

B.

Organizational standard policies, processes, and procedures

C.

Formal knowledge sharing and information sharing procedures

D.

Confidentiality of project information

Buy Now
Questions 42

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

Options:

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

Buy Now
Questions 43

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Options:

A.

To enable the team in identifying the specific causes of risks associated with project objectives.

B.

To ensure that project priorities are being appropriately factored into risk response plans.

C.

To determine there more attentive project leadership and organizational involvement is needed.

D.

To assign risks and risk severities to functional discipline and departments effectively.

Buy Now
Questions 44

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

Options:

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

Buy Now
Questions 45

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Buy Now
Questions 46

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability

 

Buy Now
Questions 47

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Options:

A.

Accept actively

B.

Mitigate

C.

Accept passively

D.

Share

Buy Now
Questions 48

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

Options:

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment

 

Buy Now
Questions 49

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.

B.

Refer to the team’s ground rules on how to resolve conflicts.

C.

Run a sensitivity analysis to check which risks have the most impact.

D.

Use the assumption analysis techniques to validate the assumptions.

Buy Now
Questions 50

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis

 

Buy Now
Questions 51

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options:

A.

Scope of work and requirements

B.

Monte Carlo analysis from a similar project

C.

List of pre-approved contractors

D.

Organization chart for city permit department

E.

Risk management plan

Buy Now
Questions 52

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options:

A.

Risk trigger

B.

Risk escalation

C.

Risk urgency

D.

Risk time impact

Buy Now
Questions 53

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis.

 

Buy Now
Questions 54

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

Options:

A.

Stakeholder management and communication tools

B.

Team performance reports and analysis tools

C.

Schedule management tools (i.e., Gantt Charts)

D.

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations)

 

Buy Now
Questions 55

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Options:

A.

Include all stakeholders in the project's governance.

B.

Communicate response strategies to all stakeholders.

C.

Ignore any risks beyond stakeholders' tolerance.

D.

Consider stakeholders' positions and opinions regarding the project’s output.

Buy Now
Questions 56

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

B.

Regularly check and report on the status of risks identified according to their prioritization.

C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Buy Now
Questions 57

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options:

A.

Risks that are tied to the success of the organization

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

E.

Risk mitigation actions that will require work from stakeholders

Buy Now
Questions 58

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Buy Now
Questions 59

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.

 

 

Buy Now
Questions 60

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Buy Now
Questions 61

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Buy Now
Questions 62

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Options:

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks' severity, and update the risk register.

Buy Now
Questions 63

Which statement describes the risk portrayed on the risk matrix heat map below?

Options:

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

Buy Now
Questions 64

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Buy Now
Questions 65

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Buy Now
Questions 66

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

Options:

A.

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

B.

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

C.

Prepare a list of the key resources that will be used to compile a risk management plan.

D.

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

Buy Now
Questions 67

A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.

What should the risk manager advise the team to do first?

Options:

A.

Mitigate the risk by asking the team member to gather more information.

B.

Add the risk to the issue log and revisit it when there is more information.

C.

Arrange a meeting with the stakeholder to discuss the risk and information.

D.

Add the risk to the risk register and gather information about its probability and impact.

 

Buy Now
Questions 68

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.

Review and revise the strategies periodically.

B.

Implement the strategies after completing the risk analysis.

C.

Implement the strategies immediately.

D.

Ensure the strategies are approved by the stakeholders.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Jun 15, 2025
Questions: 227
PMI-RMP pdf

PMI-RMP PDF

$29.75  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$35  $99.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$47.25  $134.99