Pre-Summer Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

CAPM Certified Associate in Project Management (CAPM) Questions and Answers

Questions 4

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Buy Now
Questions 5

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Questions 6

What communication methods would a project manager use for overall effective project communication?

Options:

A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

Buy Now
Questions 7

Risk categorization is a tool or technique used in which process?

Options:

A.

Plan Risk Responses

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 8

Tools and techniques used in Direct and Manage Project Work include:

Options:

A.

Process analysis and expert judgment

B.

Analytical techniques and a project management information system

C.

Performance reviews and meetings

D.

Expert judgment and meetings

Buy Now
Questions 9

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Buy Now
Questions 10

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

Options:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Buy Now
Questions 11

What is the purpose of the project management process groups?

Options:

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Buy Now
Questions 12

Which type of organizational structure is displayed in the diagram provided?

Options:

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

Buy Now
Questions 13

What causes replanning of the project scope?

Options:

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Buy Now
Questions 14

Which tool or technique is used in the Develop Project Management Plan process?

Options:

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Buy Now
Questions 15

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Buy Now
Questions 16

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

Options:

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

Buy Now
Questions 17

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

Options:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

Buy Now
Questions 18

Which is the communication method used in the Report Performance process?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Buy Now
Questions 19

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

Options:

A.

Project Plan

B.

Responsibility Matrix

C.

Issue Log

D.

Scope Document

Buy Now
Questions 20

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

Options:

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Buy Now
Questions 21

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

Options:

A.

Storyboarding

B.

Wireframes

C.

Data simulation

D.

Report prototyping

Buy Now
Questions 22

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller ' s performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Buy Now
Questions 23

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

Options:

A.

work package

B.

deliverable

C.

milestone

D.

activity

Buy Now
Questions 24

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Buy Now
Questions 25

Which of the following is an input to the Direct and Manage Project Execution process?

Options:

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Buy Now
Questions 26

What does expert judgment provide as an input to the resource management plan?

Options:

A.

Geographic distribution of facilities and resources

B.

Physical resource management policies and procedures

C.

Estimated lead times based on lessons learned

D.

Templates for the resource management plan

Buy Now
Questions 27

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

Options:

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.

B.

Change it to a negative value to show that the project is falling behind.

C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.

D.

Change it to a positive value to show that the project is ahead of its baseline schedule.

Buy Now
Questions 28

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

Options:

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Buy Now
Questions 29

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

Options:

A.

Adaptive

B.

Hybrid

C.

Extreme

D.

Traditional

Buy Now
Questions 30

What is an output of the plan resource management process

Options:

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Buy Now
Questions 31

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Buy Now
Questions 32

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 33

A project manager should communicate to stakeholders about resolved project issues by updating the:

Options:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

Buy Now
Questions 34

What is the difference between verified and accepted deliverables?

Options:

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Buy Now
Questions 35

Which of the following tasks is related to perform the qualitative risk analysis process?

Options:

A.

Identify the project risks and assign a probability of occurrance

B.

Perform a sensitivity analysis to determine which risk has the most potential for impacting the project

C.

Analyze the effect of identified project risks as numerical data

D.

Prioritize each project risk and assign the probability of occurrence and impact for each one

Buy Now
Questions 36

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Questions 37

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Buy Now
Questions 38

Success is measured by benefits realization for a:

Options:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Buy Now
Questions 39

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Options:

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Buy Now
Questions 40

A project manager is leading a project in a volatile industry. Industry standards are updated often, which requires the project team to make frequent adjustments to their work.

What should the project manager create to manage the possible changes?

Options:

A.

Communications management plan

B.

Cost management plan

C.

Risk management plan

D.

Quality management plan

Buy Now
Questions 41

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Buy Now
Questions 42

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Buy Now
Questions 43

Due to today ' s competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?

Options:

A.

Planning and risk management skills

B.

Communication and time management skills

C.

Business intelligence and leadership skills

D.

Strategic and business management skills

Buy Now
Questions 44

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Buy Now
Questions 45

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options:

A.

0.88

B.

1.12

C.

0.58

D.

1.58

Buy Now
Questions 46

A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?

Options:

A.

Analyzing the change

B.

Approving the change

C.

Reviewing the change

D.

Discussing the change

Buy Now
Questions 47

Which term refers to the work performed to deliver results with specified features and functions?

Options:

A.

Project scope

B.

Product scope

C.

Change request

D.

Acceptance criteria

Buy Now
Questions 48

What is the purpose of the project schedule management.

Options:

A.

Estimates specific time and the deadline when the products, services and results will be delivered.

B.

Determines in details the resources and time that each task will require to be done

C.

Represents how and when the project will deliver the results defined in the project scope.

D.

It provides the relationships among the project activities and their risks.

Buy Now
Questions 49

Which tool or technique is required in order to determine the project budget?

Options:

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Buy Now
Questions 50

Lessons learned are created and project resources are released in which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Questions 51

In a typical project, project managers spend most of their time:

Options:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

Buy Now
Questions 52

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Buy Now
Questions 53

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Questions 54

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options:

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Buy Now
Questions 55

Which of the following is a project constraint?

Options:

A.

Twenty-five percent of staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to a volatile political environment.

D.

The product is needed in 250 days.

Buy Now
Questions 56

Which is a major component of an agreement?

Options:

A.

Change request handling

B.

Risk register templates

C.

Lessons learned register

D.

Procurement management plan

Buy Now
Questions 57

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Options:

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Buy Now
Questions 58

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Options:

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 59

What is one of the main purposes of the project chatter?

Options:

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definition of stakeholder roles and responsibilities

Buy Now
Questions 60

What can increase the complexity of the Manage Stakeholder Engagement process?

Options:

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

Buy Now
Questions 61

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Buy Now
Questions 62

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Options:

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

Buy Now
Questions 63

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Buy Now
Questions 64

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Options:

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Buy Now
Questions 65

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit

B.

Share

C.

Enhance

D.

Transfer

Buy Now
Questions 66

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.

Which process is the project manager executing?

Options:

A.

Manage Quality

B.

Plan Quality Management

C.

Control Quality

D.

Plan Scope Management

Buy Now
Questions 67

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

Options:

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Buy Now
Questions 68

What important leadership quality/qualities should project managers possess?

Options:

A.

Skills and behaviors related to specific domains of project management

B.

Skills and behaviors needed to guide a team and help an organization reach its goals

C.

Industry expertise that helps to better deliver business outcomes

D.

Industry and organizational expertise that enhances performance

Buy Now
Questions 69

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Options:

A.

Verified deliverables.

B.

Validated deliverables.

C.

Acceptance criteria.

D.

Activity resource requirements.

Buy Now
Questions 70

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

Options:

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Buy Now
Questions 71

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

Buy Now
Questions 72

Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two)

Options:

A.

Project management plan

B.

Pareto chart

C.

Gantt chart

D.

Responsible, accountable, consult, inform (RACI) matrix

E.

Process flows

Buy Now
Questions 73

An input to the Plan Stakeholder Management process is:

Options:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

Buy Now
Questions 74

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

Options:

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Buy Now
Questions 75

What is the primary benefit of the Manage Quality process?

Options:

A.

Increases the probability of meeting quality objectives

B.

Enhances the performance of the product berg created

C.

Defines quality roles and responsibilities

D.

Ensures that the project is completed as originally planned

Buy Now
Questions 76

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Buy Now
Questions 77

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Buy Now
Questions 78

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (TandM)

Buy Now
Questions 79

In the Plan Procurement Management process, which source selection criteria analyzes if the seller ' s proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

Options:

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Buy Now
Questions 80

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Options:

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Buy Now
Questions 81

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Options:

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

Buy Now
Questions 82

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Buy Now
Questions 83

The Identify Stakeholders process is found in which Process Group?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Buy Now
Questions 84

On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.

What is the advantage of using this tool?

Options:

A.

Scope creep will be prevented.

B.

Resource allocation will be kept to a minimum.

C.

Project closure will be established.

D.

Project costs will be controlled.

Buy Now
Questions 85

Which of the following are components of the technical project management skill?

Options:

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.

B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.

C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.

D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.

Buy Now
Questions 86

Which tool or technique is used in Close Procurements?

Options:

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Buy Now
Questions 87

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?

Options:

A.

Take control of all decisions and product planning.

B.

Build a team that can respond to changes within a collaborative, decision-making environment.

C.

Promote a team with a narrow specialization within a hierarchical environment.

D.

Delegate project decisions to the product owner and sponsor.

Buy Now
Questions 88

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Questions 89

Administer Procurements is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Buy Now
Questions 90

Project Stakeholder Management focuses on:

Options:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Buy Now
Questions 91

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?

Options:

A.

Recommend, accountable, consult, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, approve, coordinate, and inform

D.

Responsible, accountable, coordinate, and inform

Buy Now
Questions 92

Which stakeholder approves a project ' s result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Buy Now
Questions 93

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two

B.

Four

C.

Five

D.

Twelve

Buy Now
Questions 94

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

Options:

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Buy Now
Questions 95

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Buy Now
Questions 96

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Buy Now
Questions 97

A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

Options:

A.

Rolling wave planning

B.

Expert Judgement

C.

Decomposition

D.

Data analysis

Buy Now
Questions 98

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Buy Now
Questions 99

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Buy Now
Questions 100

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)

Options:

A.

High-level deliverables

B.

Phase transitions

C.

Project objectives

D.

Success criteria

E.

Cost

Buy Now
Questions 101

The process of defining how the project scope will be validated and controlled is known as:

Options:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Buy Now
Questions 102

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project ' s components. What should be included in the WBS?

Options:

A.

Activity dependencies

B.

Work package risks

C.

Description of work

D.

Resource estimates

Buy Now
Questions 103

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

Options:

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

Buy Now
Questions 104

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Buy Now
Questions 105

Which of the following is a goal of the project charter?

Options:

A.

Detail requirements for the project tasks.

B.

Empower the project manager to manage the project.

C.

List all tasks the team should perform in the project.

D.

Develop a business case to support the project.

Buy Now
Questions 106

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Buy Now
Questions 107

Which method should be used to elicit a cross-functional requirement?

Options:

A.

Focus groups

B.

Prototyping

C.

Facilitated workshops

D.

Interviews

Buy Now
Questions 108

What is the purpose of an adaptive standup meeting?

Options:

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

Buy Now
Questions 109

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

Options:

A.

Risk register

B.

Sprint board

C.

Sprint planning

D.

User story

Buy Now
Questions 110

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Buy Now
Questions 111

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Buy Now
Questions 112

Which tools or techniques will a project manager use for Develop Project Team?

Options:

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Buy Now
Questions 113

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

Options:

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Buy Now
Questions 114

Which of the in an adaptive project environment, which action helps the project manager?

Options:

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Buy Now
Questions 115

The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

Options:

A.

Technical project management skills

B.

Time management skills

C.

Strategic and business management skills

D.

Leadership skills

Buy Now
Questions 116

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Buy Now
Questions 117

The process to ensure that appropriate quality standards and operational definitions are used is:

Options:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Buy Now
Questions 118

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

Options:

A.

Mitigate

B.

Transfer

C.

Share

D.

Avoid

Buy Now
Questions 119

An element of the project scope statement is:

Options:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Buy Now
Questions 120

High-level project risks are included in which document?

Options:

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Buy Now
Questions 121

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Buy Now
Questions 122

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project ' s:

Options:

A.

Level of control.

B.

Communication channels.

C.

Scope.

D.

Strategic alignment.

Buy Now
Questions 123

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Buy Now
Questions 124

Construction of a building has stopped due to a supplier ' s failure to deliver concrete. The project schedule is behind by three months.

What should the project manager do to overcome this problem and put the project back on track?

Options:

A.

Follow the risk response plan and allocate resources, if needed, to overcome the issue.

B.

Consult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.

C.

Extend the time of product delivery and use management reserve to cover any losses.

D.

Accept any penalties that might occur and continue working as initially planned.

Buy Now
Questions 125

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

Options:

A.

Control Quality

B.

Monitor and Control Project Work

C.

Control Scope

D.

Perform Integrated Change Control

Buy Now
Questions 126

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

Options:

A.

Initiate change control.

B.

Address risk mitigation.

C.

Escalate this to the project sponsor.

D.

Initiate project closure.

Buy Now
Questions 127

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Buy Now
Questions 128

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Buy Now
Questions 129

When managing costs in an agile environment, what should a project manager consider?

Options:

A.

Lightweight estimation methods can be used as changes arise.

B.

Agile environments make cost aggregation more difficult.

C.

Agile environments make projects more costly and uncertain.

D.

Detailed cost calculations benefit from frequent changes.

Buy Now
Questions 130

Which tool should a project manager consider to deal with multiple sources of risk?

Options:

A.

An updated risk register

B.

Risk breakdown structure

C.

Issue log

D.

Stakeholder register

Buy Now
Questions 131

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

Options:

A.

Project

B.

Scope

C.

Contract

D.

Program

Buy Now
Questions 132

When should quality planning be performed?

Options:

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Buy Now
Questions 133

A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.

What should the project manager do next to avoid project failure?

Options:

A.

Adopt a change management approach and delay the project to decide on the direction.

B.

Develop a focus group to face the issue and decide on the appropriate direction.

C.

Request a meeting with top management to state concerns about their ability to handle the situation.

D.

Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.

Buy Now
Questions 134

Which activity may occur at project or phase closure?

Options:

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking

Buy Now
Questions 135

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?

Options:

A.

Ask the project coordinator to facilitate some of the workshops.

B.

Invite both internal and external stakeholders to the workshops.

C.

Engage a consultant that is familiar with the community needs.

D.

Organize a workshop with the sponsor and major stakeholders.

Buy Now
Questions 136

An input to the Perform Quantitative Risk Analysis process is the:

Options:

A.

quality management plan.

B.

project management plan.

C.

communications management plan.

D.

schedule management plan.

Buy Now
Questions 137

The diagram below is an example of a:

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Buy Now
Questions 138

What does earned value (EV) measure?

Options:

A.

Budgeted work that has been completed

B.

Total costs incurred while accomplishing work

C.

Budget associated with planned work

D.

Cost efficiency of budgeted resources

Buy Now
Questions 139

What are the project management processes associated with project quantity management?

Options:

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Buy Now
Questions 140

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Buy Now
Questions 141

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

Options:

A.

Project activities

B.

Work packages

C.

Planning packages

D.

Project deliverables

Buy Now
Questions 142

A tool and technique used during the Define Scope process is:

Options:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Buy Now
Questions 143

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Buy Now
Questions 144

How can you describe the role of the project.... of influence concept?

Options:

A.

The proiect manager proactivnly interacfS with other project managers creating a positive influence Km fulfilling project needs, working with other managers and sponsor to address internal political and strategic issues and ensunng that the project managemenl plan aligns with the portfolio or program plan

B.

The project manager leads the team, performs communication roles between stakeholders, and uses interpersonal sills to balance conflicting goals

C.

The proiect manager stays informed about current technology developments lakes into account new quality management standards, and uses relevant technical support tools

D.

The proiect manager participates in project management trainings, contributes to the organization professional community sharing knowledge, and maintains subied matter expertise

Buy Now
Questions 145

Match each tool or technique with its corresponding Project Cost Management process.

Options:

Buy Now
Questions 146

Which of the following factors within a company cloud trigger the creation of a project?

Options:

A.

Need to lower production costs to remain competitive

B.

Need to submit a warranty claim for a faulty product

C.

Need to submit the monthly production report

D.

Need to define next month ' s production goals

Buy Now
Questions 147

The process of identifying and documenting relationships among the project activities is known as:

Options:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Buy Now
Questions 148

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Buy Now
Questions 149

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Buy Now
Questions 150

In which project risk management process is the data analysis technique not used?

Options:

A.

Plan Risk Management

B.

Implement Risk Response

C.

Monitor Risks

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 151

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

Options:

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Buy Now
Questions 152

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

Options:

A.

Video conferencing

B.

Audio conferencing

C.

Shared portal

D.

Email/chat

Buy Now
Questions 153

In a project using agile methodology, who may perform the quality control activities?

Options:

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Buy Now
Questions 154

To ensure stakeholder satisfaction; identified stakeholder needs should all be

Options:

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Buy Now
Questions 155

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Buy Now
Questions 156

Who should the stakeholders consult to discuss concerns about the current work package?

Options:

A.

Project manager

B.

Business analyst

C.

Project coordinator

D.

Project sponsor

Buy Now
Questions 157

Which of the following tools and techniques is used in the Verify Scope process?

Options:

A.

Inspection

B.

Variance analysis

C.

Expert judgment

D.

Decomposition

Buy Now
Questions 158

Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?

Options:

A.

lan Communications Management

B.

Manage Communications

C.

Monitor Communications

D.

Develop Project Management Plan

Buy Now
Questions 159

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.

Which evaluation technique is most effective for this situation?

Options:

A.

Day-in-the-life testing

B.

Exploratory testing

C.

User acceptance testing

D.

Integration testing

Buy Now
Questions 160

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

Options:

A.

Iterative

B.

On-demand

C.

Interactive

D.

Quality

Buy Now
Questions 161

Which component of the project management plan should be updated if a change occurs?

Options:

A.

Project charter

B.

Project baseline

C.

Assumption log

D.

Schedule forecast

Buy Now
Questions 162

Which of the following can a project manager use to represent dellned team member roles in a group of tasks?

Options:

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Organizational breakdown structure (OBS)

D.

Resource breakdown structure (RBS)

Buy Now
Questions 163

The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?

Options:

A.

Co-location

B.

Lite-cycle

C.

Diversity

D.

Management

Buy Now
Questions 164

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Buy Now
Questions 165

Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

Options:

A.

Resource breakdown structure

B.

Physical resources assignment

C.

Team building activities

D.

Integrated Change Control

Buy Now
Questions 166

Which Process Group typically consumes the bulk of a project ' s budget?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Buy Now
Questions 167

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

Options:

A.

Daily scrum

B.

Increments

C.

Sprint retrospective

D.

Sprint backlog

E.

Product backlog

Buy Now
Questions 168

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Buy Now
Questions 169

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Buy Now
Questions 170

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Buy Now
Questions 171

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Buy Now
Questions 172

Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Buy Now
Questions 173

What do top project managers do to maximize their sphere of influence within a project team?

Options:

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project ' s viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Buy Now
Questions 174

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Options:

A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

Buy Now
Questions 175

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

Options:

A.

Portfolios

B.

Standards

C.

Concepts

D.

Programs

Buy Now
Questions 176

The project manager needs to review the templates in use. The templates are part of the:

Options:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Buy Now
Questions 177

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Buy Now
Questions 178

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

Buy Now
Questions 179

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Options:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

Buy Now
Questions 180

During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?

Options:

A.

Product release plan

B.

Project release plan

C.

Project management plan

D.

Product management plan

Buy Now
Questions 181

The executive committee of a company is reviewing its portfolios. Which of the following would be helpful to evaluate success?

Options:

A.

Charter the strategic objectives.

B.

Control environmental changes.

C.

Monitor changes continuously.

D.

Aggregate benefits realization.

Buy Now
Questions 182

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

Buy Now
Questions 183

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

Options:

A.

Activity level

B.

Deliverable level

C.

Task level

D.

Work package level

Buy Now
Questions 184

A software team has completed a critical feature and demonstrated it to the project sponsor.

What kind of stakeholder communication was used in this scenario?

Options:

A.

Informal written

B.

Formal verbal

C.

Formal written

D.

Informal verbal

Buy Now
Questions 185

Match the process with its corresponding Process Group:

Options:

Buy Now
Questions 186

Which project risk listed in the table below is most likely to occur?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 187

Select two key benefits of the Control Procurements process

Options:

A.

Enables the development of make-or-buy decisions

B.

Ensures that contract performance meets the terms of the legal agreement

C.

Guarantees that legal agreements influence vendor selection

D.

Assures that legal agreements guide contract closings

E.

Helps determine whether a certain type of contract should be used

Buy Now
Questions 188

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Buy Now
Questions 189

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Buy Now
Questions 190

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Questions 191

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

Options:

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Buy Now
Questions 192

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

Options:

A.

Project charter and stakeholder engagement plan

B.

Risk management plan and stakeholder engagement plan

C.

Communications management plan and stakeholder engagement plan

D.

Project charter and communications management plan

Buy Now
Questions 193

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Buy Now
Questions 194

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Buy Now
Questions 195

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Buy Now
Questions 196

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources

B.

Control Resources

C.

Manage Team

D.

Develop Team

Buy Now
Questions 197

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Buy Now
Questions 198

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

Options:

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Buy Now
Questions 199

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

Options:

A.

Final phase of the project

B.

Start of the project

C.

End of the project

D.

Midpoint of the project

Buy Now
Questions 200

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

Options:

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Buy Now
Questions 201

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Buy Now
Questions 202

Which format can a network diagram take?

Options:

A.

Flow chart

B.

Control chart

C.

Affinity diagram

D.

Cause-and-effect diagram

Buy Now
Questions 203

Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?

Options:

A.

Learn methods

B.

collaborative teams

C.

Generalizing specialists

D.

Knowledge sharing

Buy Now
Questions 204

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Buy Now
Questions 205

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Buy Now
Questions 206

Which statement about identification and engagement of stakeholders during a project is correct?

Options:

A.

Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.

B.

Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.

C.

Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.

D.

Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.

Buy Now
Questions 207

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 208

A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)

Options:

A.

Project management plan

B.

Product roadmap

C.

Requirements traceability matrix

D.

Business goals and objectives

E.

Risk register

Buy Now
Questions 209

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Buy Now
Questions 210

One of the tools and techniques of the Manage Project Team process is:

Options:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Buy Now
Questions 211

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Buy Now
Questions 212

What organizational process asset (OPA) can impact a project?

Options:

A.

Marketplace conditions

B.

Preapproved supplier lists

C.

Physical environmental elements

D.

Legal restrictions

Buy Now
Questions 213

Projects programs subsidiary portfolios.... objectives refer to?

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?

Options:

A.

Operations Management

B.

Project Management

C.

Program Management

D.

Portfolio Management

Buy Now
Questions 214

Which is an input to the Verify Scope process?

Options:

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Buy Now
Questions 215

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

17

Buy Now
Questions 216

A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.

How can the manager document the business value for the Portfolio Steering Committee?

Options:

A.

Conduct a feasibility study to determine the business impact of the new product.

B.

Prepare a benefits management plan to capture target benefits and strategic alignment.

C.

Execute a market study for similar products and demonstrate a market need.

D.

Create a presentation outlining the business benefits of the new product.

Buy Now
Questions 217

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Buy Now
Questions 218

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

Options:

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

Buy Now
Questions 219

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

Options:

A.

Predictive

B.

Hybrid

C.

Iterative

D.

Adaptive

Buy Now
Questions 220

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Options:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Buy Now
Questions 221

What tern describes an intentional activity to modify a nonconforming product or product component?

Options:

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Buy Now
Questions 222

Which task will a project manager undertake while conducting Project Resource Management?

Options:

A.

Identity the different aspects of me team to manage and control physical resources efficiently.

B.

Procure equipment, materials, facilities, and infrastructure for the project.

C.

Train the team members in project skill sets.

D.

Define the roles and responsibilities of each team member.

Buy Now
Questions 223

Which type of project life cycle uses an iteration plan?

Options:

A.

Agile

B.

Predictive

C.

Waterfall

D.

Product

Buy Now
Questions 224

An adaptive team ' s velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.

How should the project manager calculate the anticipated velocity for future sprints?

Options:

A.

Use the velocity of the last sprint, as it is the most recent one to share.

B.

Add a 30% buffer to the velocity to calculate future velocity.

C.

Calculate the average of the past five sprints to predict future velocity.

D.

Change the adaptive tool that the team is using to calculate velocity.

Buy Now
Questions 225

Which of the following tasks focuses on decomposing work packages?

Options:

A.

Adjust duration estimates

B.

Define activities

C.

Complete rolling wave planning

D.

Develop milestone list

Buy Now
Questions 226

Which is a key skill set in PMI’s Talent Triangle?

Options:

A.

Project excellence and scope management

B.

Strategic and business management

C.

Scope management and business management

D.

Financial management and people management

Buy Now
Questions 227

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Buy Now
Questions 228

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)

Options:

A.

Many expected simple scope change requests

B.

Few expected simple scope change requests

C.

Routine and repetitive activities

D.

Collocated project teams

E.

Use of established templates

Buy Now
Questions 229

Which of the following is an example of an internal factor that influences the outcome of the project?

Options:

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Buy Now
Questions 230

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Buy Now
Questions 231

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Buy Now
Questions 232

What communications management process enables an effective information flow among project stakeholders ' ?

Options:

A.

Monitor Stakeholder Engagement

B.

Manage Communications

C.

Monitor Communications

D.

Manage Stakeholder Engagement

Buy Now
Questions 233

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio

B.

Process

C.

Project

D.

Program

Buy Now
Questions 234

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

Buy Now
Questions 235

Select three elements that apply to agile/ adaptive environments

Options:

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

Buy Now
Questions 236

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

Options:

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

Buy Now
Questions 237

Which of the following does a portfolio combine?

Options:

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Buy Now
Questions 238

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 239

A tool and technique used during the Perform Qualitative Risk Analysis process is:

Options:

A.

risk data quality assessment.

B.

variance and trend analysis.

C.

data gathering and representation techniques.

D.

risk audits.

Buy Now
Questions 240

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

Options:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Buy Now
Questions 241

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?

Options:

A.

Perform Integrated Change Control.

B.

Conduct a risk assessment with the team.

C.

Update the schedule to include compliance.

D.

Manage Stakeholder Engagement.

Buy Now
Questions 242

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

Buy Now
Questions 243

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Options:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Buy Now
Questions 244

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Buy Now
Questions 245

A project team is working on a complex product and the work breakdown structure (WBS) is finalized. The team determines that the best approach is to use an adaptive delivery method and is now tasked with converting the WBS for adaptive delivery.

How can the team manage the conversion of the existing WBS to an adaptive approach?

Options:

A.

Generate use cases for each WBS element and prepare a requirements document.

B.

Produce a release plan for each WBS element and organize them into iterations for delivery.

C.

Create themes for each WBS element and organize them into iterations for delivery.

D.

Organize the WBS into a set of related themes, epics, and user stories.

Buy Now
Questions 246

A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?

Options:

A.

Forward the status reports to the stakeholder.

B.

Manage stakeholder engagement.

C.

Consult the communications management plan.

D.

Update the communications management plan.

Buy Now
Questions 247

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Buy Now
Questions 248

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.

Which of the following elements is the team using?

Options:

A.

Definition of ready (DoR)

B.

Burndown chart

C.

Backlog refinement

D.

Definition of done (DoD)

Buy Now
Questions 249

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Buy Now
Questions 250

What is a tool or technique used in the Control Quality process?

Options:

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Buy Now
Questions 251

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Buy Now
Questions 252

Which of the following are components of the project management plan?

Options:

A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan

B.

Scope management plan, issue log, risk register and project schedule network diagram

C.

Scope management plan, schedule baseline, milestone list, and assumption log

D.

Scope management plan, cost estimates, duration estimates, and resource calenders

Buy Now
Questions 253

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Buy Now
Questions 254

Which type of graphic is displayed below?

Options:

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Buy Now
Questions 255

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Buy Now
Questions 256

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Options:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Buy Now
Questions 257

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

Options:

A.

Plan Communications Management

B.

Plan Stakeholder Engagement

C.

Perform Integrated Change Control

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 258

A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?

Options:

A.

Ask each stakeholder for their preferred communication method.

B.

Confirm the time zone and work days in each location.

C.

Check with the IT department to see if there is a technical issue.

D.

Assume the meeting request is accepted unless declined.

Buy Now
Questions 259

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two)

Options:

A.

Daily scrum

B.

Sprint backlog

C.

Sprint review

D.

Increments

E.

Sprint retrospective

Buy Now
Questions 260

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Buy Now
Questions 261

A stakeholder is reading project documents given by the project manager. The stakeholder is

curious about the difference between a verified deliverable and an accepted deliverable.

Which of the following definitions can the project manager use to explain the difference?

Options:

A.

An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.

B.

An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.

C.

An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor, a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process

D.

An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.

Buy Now
Questions 262

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Buy Now
Questions 263

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

Options:

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

Buy Now
Questions 264

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

Options:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Buy Now
Questions 265

A project charter is an output of which Process Group?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Closing

Buy Now
Questions 266

Which of the following is an input to Control Scope?

Options:

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Buy Now
Questions 267

Which Manage Communications tool or technique focuses on identifying and managing barriers?

Options:

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Buy Now
Questions 268

The completion of the project scope is measured against the:

Options:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Buy Now
Questions 269

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives ' ?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

Buy Now
Questions 270

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Buy Now
Questions 271

Due to organizational changes, a new product owner joins a project The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

Options:

A.

Acquire Resources

B.

Plan Resource Management

C.

Estimate Activity Resources

D.

Control Resources

Buy Now
Questions 272

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Buy Now
Questions 273

A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?

Options:

A.

Discuss this with the department head and arrive at an acceptable solution to expedite the approval process.

B.

Report the issue to major stakeholders and explore possible corrective actions along with legal assistance.

C.

Mitigate the risk by requesting an alternative public authority to participate in the approval process.

D.

Visit the public authority headquarters and formally petition them, demanding an explanation about the delay.

Buy Now
Questions 274

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100

B.

120

C.

1,000

D.

1,200

Buy Now
Questions 275

A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?

Options:

A.

It will give the project manager Independence to make decisions without other departmental input.

B.

It Integrates organizational data and information to ensure that strategic objectives are fulfilled.

C.

The project management office can execute administrative tasks.

D.

The project management office can coordinate projects.

Buy Now
Questions 276

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.

What should the business analyst do?

Options:

A.

Organize a workshop with the sponsor and major stakeholders.

B.

Engage a consultant that is familiar with the community needs.

C.

Ask the project coordinator to facilitate some of the workshops.

D.

Invite both internal and external stakeholders to the workshops.

Buy Now
Questions 277

Which of the following strategic considerations often results in project authorization?

Options:

A.

Customer requests and/or issue resolution

B.

Stakeholder expectations and/or strategic opportunity (business need)

C.

Technological advancement and/or senior executive request

D.

Market demand and/or legal requirements

Buy Now
Questions 278

An input to the Create WBS process is a:

Options:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

Buy Now
Questions 279

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

Options:

A.

Project

B.

Functional

C.

Program

D.

Portfolio

Buy Now
Questions 280

While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)

Options:

A.

Project sponsor

B.

Portfolio manager

C.

End user

D.

Program manager

E.

Internal inspector

Buy Now
Questions 281

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

Options:

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating

Buy Now
Questions 282

Which is the tool or technique that is used to obtain the list of activities from the work packages?

Options:

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

Buy Now
Questions 283

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

Options:

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Buy Now
Questions 284

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Buy Now
Questions 285

The definition of operations is a/an:

Options:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

B.

temporary endeavor undertaken to create a unique product, service, or result.

C.

organization that provides oversight for an administrative area.

D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

Buy Now
Questions 286

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?

Options:

A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.

B.

Share the project management plan with the team members again to bring them up to speed on the requirements.

C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.

D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.

Buy Now
Questions 287

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Buy Now
Questions 288

A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.

Which modeling tool best describes this process?

Options:

A.

Traceability

B.

User interface design

C.

Use case

D.

Wireframe

Buy Now
Questions 289

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options:

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Buy Now
Questions 290

Which Process Group and Knowledge Area include the Sequence Activities process?

Options:

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Buy Now
Questions 291

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

Options:

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Buy Now
Questions 292

Which project documents can determine the budget?

Options:

A.

Procurement documents, contracts, requirements documentation, and basis of estimates

B.

Basis of estimates, cost estimates, project schedule, and risk register

C.

Business case, project charter, statement of work, and cost estimates

D.

Scope baseline, resource management plan, activity list, and assumption log

Buy Now
Questions 293

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Buy Now
Questions 294

To which knowledge area does the Collect Requirements process belong?

Options:

A.

Quality Management

B.

Scope Management

C.

Cost Management

D.

Integration Management

Buy Now
Questions 295

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

Options:

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Buy Now
Questions 296

What internal enterprise environmental factor (EEF) can impact a project?

Options:

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Buy Now
Questions 297

The number of potential communication channels for a project with 5 stakeholders is:

Options:

A.

10.

B.

12.

C.

20.

D.

24.

Buy Now
Questions 298

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Buy Now
Questions 299

What is one of the objectives of Project Risk Management?

Options:

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Buy Now
Questions 300

Which of these is true project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects

B.

Project Integration Management and Expert Judgement are mutually exclusive

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero

Buy Now
Questions 301

How does a requirements traceability matrix help to determine whether a product is ready for delivery?

Options:

A.

It captures assigned tasks and their estimated durations.

B.

It confirms the completion of all stories in the backlog.

C.

It assesses the quality of test cases and expected results.

D.

It tracks links between the approved requirements and each work product.

Buy Now
Questions 302

Which is an example of analogous estimating?

Options:

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Buy Now
Questions 303

Which tool or technique is effective in a project in which the deliverable is not a service or result?

Options:

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Buy Now
Questions 304

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Buy Now
Questions 305

In which domain of project management would a Pareto chart provide useful information?

Options:

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Buy Now
Questions 306

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Buy Now
Questions 307

What is the first step in the Stakeholder Management process?

Options:

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

Buy Now
Questions 308

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.

Buy Now
Questions 309

A product owner wants to ensure that the project ' s requirements, including product requirements, are met and validated. To do this project manager wants.

Match each process to its definition.

Options:

Buy Now
Questions 310

A project manager needs information to finish their work on the project charter for a clinical trial.

Which procedure is used to obtain the requirements information?

Options:

A.

Forecasting

B.

Simulations

C.

Elicitation

D.

Quantitative analysis

Buy Now
Questions 311

Which of the following is provided by the critical path method?

Options:

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

Buy Now
Questions 312

When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?

Options:

A.

Update the schedule baseline

B.

Review the schedule baseline

C.

Initiate a change request

D.

Update the risk register

Buy Now
Questions 313

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Buy Now
Questions 314

Which are examples of processes that may be used once or at predefined points in the project life cycle?

Options:

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Buy Now
Questions 315

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

Options:

A.

Strategic and business management skills

B.

Leadership skills

C.

Technical project management

D.

Organizational management

Buy Now
Questions 316

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

Options:

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

Buy Now
Questions 317

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Buy Now
Questions 318

What is a key benefit of using virtual project teams?

Options:

A.

Ensures appropriate behavior, security, and the protection of proprietary information

B.

Reduces the risk of conflict due to interpersonal communications and other interactions

C.

Assures that all team members have a clear and common understanding of the project

D.

Reduces project cost by use of modern technologies allowing seamless team collaboration

Buy Now
Questions 319

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

Options:

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Buy Now
Questions 320

During what project management process does the project team begin identifying risks?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 321

Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

Options:

A.

Cause and effect diagram

B.

Control charts

C.

Pareto chart

D.

Histogram

Buy Now
Questions 322

Which are the competing constraints that project manager should address when tailoring a project?

Options:

A.

Cost, scope, schedule

B.

Sponsorship, risk, quality

C.

Schedule, sponsorship, scope

D.

Resources, Quality, Communication

Buy Now
Questions 323

Which of the following is an input to the Perform Qualitative Risk Analysis process?

Options:

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Buy Now
Questions 324

Project reporting is a tool that is most closely associated with which process?

Options:

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Buy Now
Questions 325

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager ' s disposal?

Options:

A.

Resource leveling and fast tracking

B.

Fast tracking and crashing

C.

Crashing and applying leads and lags

D.

Scheduling tools and applying leads and lags

Buy Now
Questions 326

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

Options:

A.

Policy compliance and auditing

B.

Standards and compliance

C.

Review of lessons learned

D.

Test and inspection planning

Buy Now
Questions 327

How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?

Options:

A.

Adopt co-creation, sharing responsibilities with stakeholders

B.

Adopt participation of stakeholders in main meetings, listening to their opinion.

C.

Adopt social media tools, improving communication with stakeholders

D.

Adopt involvement of stakeholders in lessons learned sessions, sharing experiences with them

Buy Now
Questions 328

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Buy Now
Questions 329

Which of the following is TRUE about most project life cycles?

Options:

A.

Staffing level is highest at the start.

B.

The stakeholders ' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Buy Now
Questions 330

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Buy Now
Questions 331

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

Options:

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Buy Now
Questions 332

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Buy Now
Questions 333

Which of the following documents ate created as part of Project Integration Management?

Options:

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Buy Now
Questions 334

Which action should the project manager take after the team finishes executing the scope?

Options:

A.

Verify the deliverables to ensure that they are correct and meet the customer ' s satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

Buy Now
Questions 335

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Buy Now
Questions 336

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Buy Now
Questions 337

Tools and techniques used for Plan Communications include the communication:

Options:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Buy Now
Questions 338

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Buy Now
Questions 339

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Options:

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

Buy Now
Questions 340

What is the difference between the critical path and the critical chain?

Options:

A.

Scope changes

B.

Resource limitations

C.

Risk analysis

D.

Quality audits

Buy Now
Questions 341

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

Options:

A.

Sensitivity analysis

B.

Simulation

C.

Decision tree analysis

D.

Influence diagram

Buy Now
Questions 342

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Options:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

Buy Now
Questions 343

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Cash Flow Statement of the Project Investment Unit: US$ Billion

Period: 0, 1, 2, 3, 4, 5, 6, 7, 8

Cash inflow: 0, 0, 0, 0, 1200, 1200, 1200, 1200

Cash outflow: 0, 700, 800, 500, 700, 700, 700, 700, 700

Net cash flow (NCF): 0, -700, -800, 300, 500, 500, 500, 500, 500

Accumulative total of net cash flow: 0, -700, -1500, -1200, -700, -200, 300, 800, 1300

Options:

A.

Static payback period = 3 + |-1200| / 500 = 5.4

B.

Static payback period = 6 + |300| / 500 = 6.6

C.

Static payback period = 5 + |-200| / 500 = 5.4

D.

Static payback period = 4 + |-700| / 500 = 5.4

Buy Now
Questions 344

Which two processes should be used to influence costs in the early stages of a project?

Options:

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Buy Now
Questions 345

Which of these is a hybrid contract?

Options:

A.

Cost plus award fee (CPAF)

B.

Firm fixed price (FFP)

C.

Fixed price incentive fee (FPIF)

D.

Time and material (TandM)

Buy Now
Questions 346

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

Options:

A.

Interpersonal communication

B.

Feedback response communication

C.

Push communication

D.

Pull communication

Buy Now
Questions 347

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

Options:

A.

Current state analysis

B.

Facilitated workshops

C.

Scheduled interviews

D.

Shop floor observation

E.

Brainstorming sessions

Buy Now
Questions 348

What earned value (EV) measure indicates the cost efficiency of the work completed?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

To-complete performance index (TCPI)

D.

Variance at completion (VAC)

Buy Now
Questions 349

A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?

Options:

A.

Forming

B.

Norming

C.

Storming

D.

Performing

Buy Now
Questions 350

A procurement management plan is a subsidiary of which other type of plan?

Options:

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Buy Now
Questions 351

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Buy Now
Questions 352

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Buy Now
Questions 353

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1

B.

0.4

C.

0.5

D.

0.8

Buy Now
Questions 354

What can a requirements traceability matrix enable regardless of the project methodology being used?

Options:

A.

Creation of a solid business case

B.

Investigation of the viability of a new product

C.

Identification of missing and superfluous requirements

D.

Evaluation of solution and system performance

Buy Now
Questions 355

An issue log is an input to which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Buy Now
Questions 356

Which item is an example of personnel assessment?

Options:

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Buy Now
Questions 357

Which of the following correctly explains the term " progressive elaboration ' ?

Options:

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Buy Now
Questions 358

A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.

Which activity is the project team conducting?

Options:

A.

Project execution

B.

Benchmarking

C.

Brainstorming

D.

Project initiation

Buy Now
Questions 359

Which role does the project manager resemble best?

Options:

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Buy Now
Questions 360

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Buy Now
Questions 361

When should Project Risk Management be conducted?

Options:

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

Buy Now
Questions 362

The features and functions that characterize a result, product, or service can refer to:

Options:

A.

project scope

B.

product scope

C.

service scope

D.

product breakdown structure

Buy Now
Questions 363

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

Options:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Buy Now
Questions 364

Which can be used to determine whether a process is stable or has predictable performance?

Options:

A.

Matrix diagram

B.

Histogram

C.

Control chart

D.

Flowchart

Buy Now
Questions 365

What should be the frequency for meetings when transitioning from Scrum to Kanban?

Options:

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Buy Now
Questions 366

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Buy Now
Questions 367

What type of change requires the submission of a change request?

Options:

A.

Changes in assigned resources

B.

Changes in a technical solution

C.

Changes in status reporting

D.

Changes in the project ' s scope

Buy Now
Questions 368

A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?

Options:

A.

Linear project management; project schedule and project backlog

B.

Adaptive project management; project schedule and work breakdown structure

C.

Linear project management; project schedule and work breakdown structure (WBS)

D.

Adaptive project management; project schedule and project backlog

Buy Now
Questions 369

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Buy Now
Questions 370

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

Options:

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Buy Now
Questions 371

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Buy Now
Questions 372

During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?

Options:

A.

Bonuses based on accomplishment criteria

B.

New working contract with more benefits

C.

Promotion opportunities with this project

D.

Assignment of key roles and responsibilities

Buy Now
Questions 373

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Buy Now
Questions 374

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Buy Now
Questions 375

Which organizational process asset can make an impact on the outcome of a project?

Options:

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

Buy Now
Questions 376

In an agile or adaptive environment. when should risk be monitored and prioritized?

Options:

A.

Only during the initiation and Closing phases

B.

During the initiation and Planning phases

C.

During each iteration as the project progresses

D.

Throughout the Planning process group and retrospective meeting

Buy Now
Questions 377

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Buy Now
Questions 378

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Buy Now
Questions 379

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

Options:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Buy Now
Questions 380

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Buy Now
Questions 381

What purpose does the hierarchical locus of stakeholder communications serve?

Options:

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Buy Now
Questions 382

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Buy Now
Questions 383

To which process is work performance information an input?

Options:

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 384

What risk response strategy involves removing high- risk scope elements from a project?

Options:

A.

Transfer

B.

Avoid

C.

Exploit

D.

Accept

Buy Now
Questions 385

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

Options:

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix

Buy Now
Questions 386

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

Options:

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

Buy Now
Questions 387

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Buy Now
Questions 388

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Buy Now
Questions 389

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

Options:

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Buy Now
Questions 390

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?

Options:

A.

3 days

B.

5 days

C.

7 daysD .10 days

Buy Now
Questions 391

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Buy Now
Questions 392

Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?

Options:

A.

Project management plan, data gathering, and stakeholder engagement plan

B.

Business documents, meetings, and stakeholder register

C.

Organizational process assets, data gathering, and project document updates

D.

Project management plan, data analysis, and change requests

Buy Now
Questions 393

A tool and technique used in the Develop Project Charter process is:

Options:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Buy Now
Questions 394

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Buy Now
Questions 395

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?

Options:

A.

Develop consensus among stakeholders

B.

Get the budget approved for change

C.

Make sure management is aware of the change

D.

Get approval from the change control board

Buy Now
Questions 396

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

Options:

A.

Schedule network analysis

B.

Reserve analysis

C.

Alternative analysis

D.

Variance analysis

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: May 20, 2026
Questions: 1320
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$30  $99.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99