Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi? 1 credit
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits
Since the system is in the medical domain and therefore in the safety critical area, testing needs to be rigorous and evidence is required that the system has been adequately tested. Identify THREE measures that would typically be part of the test approach in this domain and which are not always applicable in other domains! 1 credit
You are considering involving users during test execution. In general, what is the main reason for involving users during test execution? 1 credit
Which of the following are most likely to be used when developing a test strategy or test approach?
(i) Failure-based approach
(ii)Test specification approach
(iii) Model-based approach
(iv)Finance-based approach
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Given the following figures for the testing on a project, and assuming the failure rate for initial tests remains constant and that all retests pass, what number of tests remain to be run? 3 credits
In general which part of the testing activity is most difficult to estimate? 1 credit
In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons. 1 credit
Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits
Which of the following comparisons of component testing and system testing are TRUE?
Based on the information given in the scenario, identify how the team could be improved most effectively? 2 credits
What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk? 2 credits
You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report? 1 credit
Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV. Defect trend (number of defects found per test run over time
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy? 1 credit
Which test management control option is most appropriate to adopt under these circumstances? 2 credits
Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits
Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
What other details should be included in the following incident report when it is first submitted?
Date of Issue: 23/11/05
Severity: P1
Build: Version15.6
Details: Expected field to be limited to 15 chars, able to enter 27
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 credit
The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage? 2 credits
Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit
During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 credit
Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement? 1 credit
A garden irrigation system allows the user to specify 2 inputs:
1. Frequency - The number of times the system should be automatically switched on per day; minimum once per day, maximum 5 times
2. Duration - The duration of operation, in whole minutes, each time it is switched on; ranging from 1 to 60
Applying 2-value boundary value analysis which of the following options has the correct test set of valid and invalid boundary values?
The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits
Which of the following product risks would be most effectively addressed just by static testing? 3 credits
Test script TransVal 3.1 tests transaction validation via screen TRN 003B. According to the specification (PID ver 1.3 10b iv) the validation screen should not accept future dated transactions. Test script TransVal 3.1 passes. Test script eod 1.4 tests end of day processing and is run after the execution of TransVal 3.1 using data entered during that test
Which of the following is the BEST detail on an incident report? [K3]
Which of the following is a characteristic of good testing in any life cycle model? 1 credit
Which of the following would be the TWO most appropriate examples of entry criteria documented in the system integration test plan? 2 credits
Foundation Level | CTFL-Foundation Questions Answers | CTFL-Foundation Test Prep | ISTQB Certified Tester Foundation Level Questions PDF | CTFL-Foundation Online Exam | CTFL-Foundation Practice Test | CTFL-Foundation PDF | CTFL-Foundation Test Questions | CTFL-Foundation Study Material | CTFL-Foundation Exam Preparation | CTFL-Foundation Valid Dumps | CTFL-Foundation Real Questions | Foundation Level CTFL-Foundation Exam Questions