Weekend Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtreat

MSP-Foundation MSP Foundation Exam (5thEdition) Questions and Answers

Questions 4

Which of the following statements about the core elements of successful communications is true?

1.Stakeholder analysis is required

2.Audit trail is established

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Buy Now
Questions 5

Which role provides a home for governance and control?

Options:

A.

Sponsoring group

B.

Programme board

C.

Programme assurance

D.

Programme office

Buy Now
Questions 6

Which role is MOST likely to have a focus on managing the costs of training operational teams during transition?

Options:

A.

Business Change Manager

B.

Programme Manager

C.

Senior Responsible Owner

D.

Programme Office

Buy Now
Questions 7

Which is the BEST description of the purpose of the Projects Dossier?

Options:

A.

Lists the projects involved in the delivery of the Blueprint

B.

Specifies a thorough brief for starting each project

C.

Describes the context when starting up projects

D.

Provides detailed requirements for each project

Buy Now
Questions 8

Which of the following statements about business change and transition costs in the business case are true?

1.Include the costs of any interim operational resources required to embed the change.

2.Include the costs of a contingency budget for dealing with risk.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 and 2 are true

Buy Now
Questions 9

Which of the following statements about programme dependencies is true?

1.Internal dependencies include dependencies on strategic decisions

2.Internal dependencies are likely to be linked to the scope of a corporate portfolio

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Buy Now
Questions 10

In a multiple programme environment, which role may be performed by a ‘corporate portfolio board’?

Options:

A.

Sponsoring group

B.

Programme board

C.

Design authority

D.

Programme office

Buy Now
Questions 11

Which is NOT a reason for Managing the Tranches?

Options:

A.

To implement the Risk Management Strategy

B.

To coordinate and manage project delivery

C.

To maintain focus on stable operations

D.

To maintain information and asset integrity

Buy Now
Exam Code: MSP-Foundation
Exam Name: MSP Foundation Exam (5thEdition)
Last Update: May 17, 2024
Questions: 75
MSP-Foundation pdf

MSP-Foundation PDF

$28  $80
MSP-Foundation Engine

MSP-Foundation Testing Engine

$33.25  $95
MSP-Foundation PDF + Engine

MSP-Foundation PDF + Testing Engine

$45.5  $130