A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.
How should the project manager have handled this situation earlier in the project?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.
Which of the documents was likely missed or outdated?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.
What is the budget at completion (BAC)?
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
An agile team has released the second version of its product, but the feedback is that the software has many bugs that compromise the user experience. What should the
project manager do?
A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.
Which estimation technique should the project manager recommend?
An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?
A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.
What should the project manager do?
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the
original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.
How should the project manager handle this situation?
During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.
What should the project manager do first?
A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users.
What should the project manager do?
During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The
project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.
Which project document should the project manager review in order to determine the reason for this issue?
After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.
What should the project manager do?
A stressful situation has presented some challenges for the team. The project manager notices stress behavior in some of the team members, and it is beginning to spread across the group. The project manager needs to coach the team to change their mindset in order to be more efficient.
What should the project manager do?
An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager
advises the product owner that some of the functional requirements are not aligned with the chief information technology officer's (CTO) strategy.
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
A project manager is working with an agile team. A key stakeholder who does not
join the sprint planning session is very unhappy, as the delivery date for the final product has
been pushed back three times. What should the project manager do?
A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project
manager use to manage these risks using an agile approach?
A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within
the organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the
projects to use more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?
In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.
Which two actions should the project manager take? (Choose 2)
A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget
What should the project manager do?
A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on
the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are
being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting
market requirements.
What should the project manager do?
A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.
What should the project manager do?
A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.
What should the project manager do?
Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two
members are tense around each other and are taking everything personally.
What should the project manager do?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be
consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated
with the other reports. This demonstrates a lack of teamwork and impacts project success.
What should the project manager do to resolve this issue?
After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)
During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style
What should the project manager do?
A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for
several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.
What should the project manager do next?
A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,
the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.
What should the project manager have done to prevent this from happening?
A project manager is leading a long-term project, executed in stages, to set up a complex communications network in many rural areas. The project is being executed in stages.
What should the project manager do to ensure that monetized business value is generated as planned?
A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.
How should the project lead respond?
While reviewing a project with high-level executives, the project manager realizes that the conversation always deviates to other topics instead of the project itself.
What two actions should the project manager take? (Choose 2)
Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of
the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that
quality has been maintained.
How should the project manager communicate with the customer to help assure them that the project has produced quality products?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.
What should the project manager do next?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
A team has had issues with behavior on an ongoing project, which is causing conflicts. As a result, the team is losing momentum and falling
behind in its sprints.
How should the project manager handle this situation?
A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.
What should the project manager do?
The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.
What should the project manager do first?
Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?
During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.
What should the project manager do first to resolve this issue?
A project manager is leading a project team composed of members with varying levels of knowledge and
experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.
What should the project manager do?
All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.
What should the project manager do to prevent these delays?
A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project
After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.
What should the protect manager do?
While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?
An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?
A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.
What should the project manager have done to prevent this from happening?
The project manager of a globally dispersed team evaluates the organization's current virtual engagement tools and strategies. A couple of the remote team members are not participating effectively in virtual meetings.
Which action should the project manager take to improve remote engagement?
A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that
there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.
What should the project manager do?
A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.
Drag each stakeholder scenario on the left to the correct engagement level on the right.
A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members
What is the cause for this communication gap?
During a weekly status update meeting with the project management office (PMO), the assigned project manager notices some stakeholders raise concerns about the implementation plan even though the status was regularly communicated to all stakeholders.
What should the project manager do?
In a product development project, the project manager is constantly receiving complaints from stakeholders about functionalities being delivered, but not required by the business departments. The project sponsor wants to know if the project resources are being used effectively.
What should the project manager have done to avoid delivering work that is not adding value to the business?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project
and will be actively trying to prevent its success by reailocating key team members to another critical project.
What should the project manager do?
A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.
What should the project manager do?
During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?
During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining
What should the project manager do?
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns
that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.
Which action should the project manager take to procure the vehicles?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
A company is working on a project to develop an integration of their existing systems. There are known issues in production.
What should the project manager do?
A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs
to be delivered to the customer as a ready-to-use product .
Based on this scenario, what should the project manager focus on throughout the project life cycle?
A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?
A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.
What should the project manager do?
While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid
What should the project manager do?
A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.
How should the project manager resolve this conflict and reach a consensus?
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?
A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.
What should the project manager do to integrate the diverse stakeholder groups?
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this project?
During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project
manager ensure the team is fully productive?
One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended
What should the project manager do next?
A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year
What has happened in this situation?
Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.
What should the project manager do to obtain agreement from both companies and acceptance from marketing?
A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.
What should the project manager do?
Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.
What should the project manager do next to address this issue?
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the
scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,
among other critical blockers.
What should the project manager do?
At the beginning of a project, a project manager is asked to provide human resources (HR) with an evaluation of every team member's performance. This evaluation will be delivered at the end of the project.
How should the project manager approach this request?
An organization is altering their schedule, and the project team is now expected to be in the office together once a week. Despite everyone being dedicated to the project, the team members all follow their functional teams' schedules, which differ from one another.
How should the project manager address this situation?
A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for
the project. The customer has informed the project manager to disregard the group as they are not in support of the project.
What should the project manager do next?
A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.
What should the project manager do?
A government procurement team has been running a vendor selection process for more than 1 year, going beyond the originally planned 6 months due to a variety of factors. Two vendors have submitted proposals that were evaluated. The project manager asked for an estimated completion date 4 weeks ago, but it was not provided.
What should the project manager do?
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict
How should the project manager resolve the problem?
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team
What should the project manager do?
The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?
Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.
What should the project manager do to resolve this issue and help the team move on to the next iteration?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal
impact on project resources. However, the client has only been focused on the next milestone.
How should the project manager approach this situation?
A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?
The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?
Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings
What should the project manager do?
The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .
What should be the priority order in the product backlog?
An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?
As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change
What should the project manager do?
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks
Drag each risk type on the left to its correct example on the right
The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements
How should the project manager address this situation?
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement
What should the project manager do next?
A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information
How should the project manager handle this situation?
A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog
What should the project manager do?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email
What should the project manager do?
During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right
An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework
What should the project manager do in this situation?
A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?
A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule
What should the project manager do to keep the project on schedule while still meeting project objectives'?
During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.
What should the project manager do next in this situation?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.
What action should the project manager take to motivate the project team's performance?
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product
What should the project manager do?
A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?
A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.
What should the project lead do in this situation?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?
The CFO has stated in a conversation with a project team member that they do not believe the project will be a success due to the high cost of implementation.
What should the project manager do?
The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources
What strategy should the project manager use in order to keep delivering value in a restricted environment?
A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch
What should the project manager do to realize benefits?
A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials
What should the project manager do next?
Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager's first step in addressing the problem?
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.
How will the project manager be able to complete this task?
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project
What should the project manager do?
A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase
What item(s) should the project manager develop first?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget
What should the project manager do next?
An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?
A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter
What should the project manager do?
A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?
A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component
What should the project manager have done to prevent this delay from happening?
A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
A company is conducting a digital transformation project that has a hard deadline.
The marketing team wants to combine this implementation with a new product, and the newly
assigned project manager is not aware of all the dependencies.
Using a hybrid approach, what should the project manager do to ensure the dependencies are
taken into consideration?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.
What should the project manager have done to prevent this?
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals
What two options will help the team initially address this obstacle? (Choose two)
According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right
The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.
What should the project manager do to obtain the support?
A project manager is leading an electrical project that spans five towns. The project
manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
A customer calls the project manager to express concern about a project team
member who has been making changes within the live environment without approval. The
team member mentioned that the customer called and asked them to make the changes.
What should the project manager do next?
A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,
What should the project manager do first?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members
What two actions should project manager take? (Choose two)
A company has always acquired very specialized services from local companies for
its projects. During the planning stage for a regulatory project, the project manager is informed
that local vendors would not be able to operate due to an unexpected major event. There is an
option to hire the same services from companies in other countries.
What should the project manager do in this situation?
In an ongoing project, stakeholders have been approaching team members for status
reports and changes without consulting the project manager. What should the project
manager do to ensure a successful project?
A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?
One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority
What should the project manager do to mitigate the risk of not having the materials printed on time?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline
What should the project manager do next?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status
What should the project manager do?
A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.
What should the project manager do to address this issued
The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.
What should the project manager do?
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
During project execution, an important stakeholder threatens to withdraw support
for the project, citing a lack of transparency and accountability in the way the project is being
executed. What should the project manager do to handle this situation?
The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?
Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
A project manager receives a request for proposal (RFP) from a client. The client
is very clear about the requirements. A requirements analysis must be done in the first
month of the project, and the client wants to see a demo of the work completed every two
weeks.
What project approach should the project manager use?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible
What approach should be used in this situation?
A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose three)
Drag the communication event on the left to the mam subject discussed during the event on the right.
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion
What are two issues that these actions by the project manager could cause? (Choose two)
A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery
How should the project manager avoid this situation in the future?
A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using
What should the project manager have done to avoid this issue?
A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team
How can the project manager ensure knowledge transfer across the team?
The following table shows the business value created and the development effort required to implement various features in a product
Which feature should the team prioritize first? Enter the feature name in the box below
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team
members and stakeholders who have contradictory opinions.
What should the project manager do?
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required
What should the project manager do?
A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution
What should the project manager do?
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards
in order to ensure this, what should the project manager define and document?
During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables
How should the project manager mitigate this risk without compromising the completion date?
An agile team is funded for a fixed 6-month period. The sponsor's request will take at least 12 months to complete.
What should the project manager do?
A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members
Which three actions should the project manager take? (Choose three)
A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project
What should the project manager do?
A project manager is leading a project that is implementing an assembly line.
During the quality review meeting, a team member reports an issue stating that the product
being developed has discrepancies with the one requested by the customer.
What should the project manager do?
A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation
What should the project manager do next?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
The change control board (CCB) has approved a change request to add a new
component within a product. The operations manager discovers the change after its approval
and complains that the implementation of the change will cause significant disruption to the
production line.
What should the project manager do first?
A project manager is assigned to a new water treatment plant project that has been
delayed for many years. It is revealed in the project charter that the sponsors of this project
are from three different business units. This is the first time the sponsors have ever
implemented such a project.
What should the project manager do?
A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.
What should the project manager do to address this issue?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.
How should the team share tacit knowledge?
A project manager for a construction site realizes the importance of stakeholder
relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.
What should the project manager do to customize the stakeholder engagement plan?
An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.
A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.
What should the project manager do given the urgency?
A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.
What should the project manager do?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.
How should the project manager plan this project?
A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.
What should the project manager do?
An agile team recently started working on a project for a financial institution. The
project sponsor is concerned that an agile approach will not provide enough support for the
organization's compliance standards.
In order to mitigate this risk and avoid problems, what should the project manager do?
A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.
What strategy should the project manager use to ensure on-time delivery of the solution?
A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?
A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed.
What should the project manager do next?
Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the
project. How should the project manager resolve this?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.
What should the project manager do?
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value
What should the new project manager do next?
A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment
What should the project manager do?
A project manager is tasked with developing a coaching model to support and recognize team members' growth.
What should the project manager consider when defining their coaching strategy?
In the middle of an iteration, the product owner tells the agile team that the
government has updated legal requirements. This will result in some changes in the product
definition.
How should the project manager handle this situation?
During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead
handle this situation?
A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.
A project manager has been assigned with initiating a large project to deliver
complex equipment. Part of the project will be the result of a long research process, but once
this is completed, the other part of the project must be incrementally delivered to the
customer.
Which approach should the project manager choose for this project?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
What should the project manager do?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.
What should the project manager do to support the team?
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.
What should the project manager do to keep the stakeholders engaged?
A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.
What should the project manager do?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.
What should the project manager do next?
A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.
What should the project manager have done to avoid this situation?
In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track.
What should the project manager do?
A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team
What should the project manager do first to ensure the project is compliant?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
In a software project using an agile approach, there have recently been work
overruns. After assessing the situation, the project manager concluded that the overruns are
occurring because of insufficiently refined product backlog items.
What should the project manager do to correct this issue?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.
How should the project manager handle this situation?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis? (Choose two)
A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?
A project team member has lost enthusiasm and is experiencing low morale for a
project they were once excited about. What should the project manager do?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project
How should the project manager report this cost?
A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.
Which action should the project manager take?
A project manager is establishing a project management office (PMO) for a
company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.
Which activity should the project manager use to help train the stakeholders?
A project team is executing a project to replace an existing system with a new one.
A new project manager has been hired and observes that the team consist of professionals
who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
A project manager is developing a project baseline schedule and has started to
assign team members to the project activities according to their function. What should the
project manager do in this phase?
At the end of a project, one of the suppliers is facing financial difficulties and is
pushing the project manager to obtain financial, legal, and administrative approval in order to
communicate formal project closure and ensure the transfer of liability. What should the
project manager do next?
A project manager is appointed to manage an infrastructure project that spans
across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.
What should the project manager do to ensure good collaboration between the remote project team members?
A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.
What should the project manager do first?
An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?
A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.
How should the project manager handle this situation?
A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items
What should the project manager do as a servant leader?
A project stakeholder has expressed concern that the established success criteria for
the project are not being met. What should the project manager do next?
A project manager has noticed that a critical team member is consistently arguing
with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
During the planning for a long project, the project manager recognized that several
members of the team are new to their roles. How should the project manager incorporate this
into planning?
An organization started the process of a digital transformation and is trying to change
its culture from a predictive to a more agile approach. The project manager leading the
change management process identified some knowledge gaps of key team members, which
could prevent the transformation from happening as planned.
What should the project manager do?
A key resource is newly assigned to a project. The project manager and the resource
did not get along well in a previous project. This resource is needed to ensure the completion
of a major component for the project.
What should the project manager do?
A project manager is in the process of creating a strengths-based team and is
organizing a series of workshops to identify and document the strengths of each project team
member. During this session, there are multiple team members who are not actively
participating. These meetings are becoming futile due to a lack of participation.
What should the project manager do?
During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?
A project requires testing of the final product to be done at another department's
testing facility, which is known for having low availability. This situation could potentially
impact the project schedule.
What should the project manager do next?
A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.
Which document should the project managefve?
A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.
In what type of analysis should the project manager use this information?
A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.
What should the project manager do?
A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.
Why did this action occur?
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification for the product.
What should the project manager do to proceed with the project management plan?
A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.
Which action should the project manager take?
The sponsor approaches the project manager with new features they want added to
the project. The project is 95% complete, but the sponsor insists that continued support for the
project relies on the addition of the new features.
What should the project manager do?
A leader from project B consistently reaches out to a team member in project A for
assistance. What should project A's project manager do?
A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?
A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.
What should the project manager do in this situation?
An organization is adopting an agile mindset. On the first agile project, the project
manager faced an issue because the team was unable to make decisions on time.
What should the project manager do to address the problem?
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concem9
A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
Throughout an entire project, the project manager took notes at every meeting with
team members. These notes provided useful insights from key stakeholders, which later
resulted in increased value to the project. The project manager thought it would be helpful to
keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?
An agile project manager is evaluating the method that will be used to display the
value of the work performed to date. Which method will they select to display to the project stakeholder?
A hybrid project is experiencing several issues with both the agile delivery of the
product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
A project manager receives a serious complaint from a functional manager about a
team member. What should the project manager do?
A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted
What should the project manager do?
A key project team member has exhibited high interest in a project. The input from
this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.
What should the project manager do?
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule
What should the project manager do?
A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.
What should the project manager do?
During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?
A project manager is leading an automation project. The project team is colocated
and includes people from both the technical and business units. The project manager
discovers that personal differences and work styles are affecting the project negatively.
How should the project manager address this?
During the setup of an agile project, the product owner expressed clear interest in
having features released during product development over having the product completed in
one year. What should the project manager do?
Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
A project team consists of members based in country A and subject matter experts
(SMEs) based in country B with a 12-hour time difference. What can the project manager do
to improve interactions between the team members in both countries?
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?
A project manager is working with a team that is new to agile. One of the more
influential stakeholders struggles with the nature of agile. The project manager knows that this
stakeholder is needed as an advocate and wants to do everything possible to make the
stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's
performance?
A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other
What should the project manager do first to resolve this situation?
The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.
What should the project leader do to solve this situation?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A project manager is leading a hybrid project. The self-organizing teams are
continually late in delivering their demos, resulting in low morale. The steering committee is
familiar with the reporting and planning associated with a predictive approach and is
concerned about the project because it is unclear if the expected value will be delivered.
What should the project manager do?
A project manager is working with an agile team to enhance a product. Due to a
tight deadline, the team is trying to crash the schedule by engaging multiple resources to work
on the project simultaneously. However, the technical environment is configured to allow only
one resource to work on a feature at a time. The team plans to upgrade the technical
environment but is unable to agree on a way forward.
What should the project manager do first?
A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback
What should the project manager do to resolve the issue?
A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?
The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.
What should the project manager do to ensure timely delivery?
A large organization decided to adopt an agile methodology based on the trends
seen in the industry. The organization invested a large amount of money in adopting it, but
after a few months, the implementation failed.
What should the project manager have done differently to avoid the implementation failure?
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?
During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?
An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.
What should the agile leader do?
An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives
What should the project manager do?
One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.
What should the project manager do next?
A project manager is assigned midway through a project. The team members are in
different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.
What should the project manager do first?
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?
An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?
A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time
What kind of conflict resolution did the project manager apply in this situation?
A project manager is assigned to a new project and is allocated with virtual team
members. Later, two more members from a recently acquired company join as additional
resources to the project team.
In order to ensure that there are no potential misunderstandings, what should the project
manager do?
A project manager is leading a major water pipeline project and realizes midway into
the project that the project completion date is not achievable. Local farmers who rely on the
water for irrigation may be affected due to the delay. The project manager is afraid of their
displeasure and reaction, which will affect the project.
How should the project manager plan the communication to the stakeholders?
During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?
A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed
To what type of communication is the team member referring?
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?
A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.
What should the project manager do to integrate the new team member effectively?
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
A junior team member escalates an issue to the project manager about another
member's interpersonal skills causing the team to be less effective.
What should the project manager do first?
A project manager prepared a project benefits management plan. Which of the following should be included in this document?
A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?
In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.
Match the project manager's goals on the left with the relevant risk parameter on the right.
A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be
engaged in how the project will be executed.
How should the project manager proceed?
At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
A project manager is using a hybrid approach for project delivery. The
development team was sized, but is not yet fully resourced. The project manager is working
on defining the project schedule.
What should the project manager do to address the issue of developer availability?
Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not
delivered, the company could receive a fine from the government. What should the project manager do?
During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?
An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.
What should the project manager do?
A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.
What should the project manager do next?
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.
What should the project manager use to document the project deliverables?
A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?
In the past, the project manager and the project team performed well using
predictive methodology. However, the organization recently decided to adopt agile
approaches, and the project sponsor wants to use an agile approach in an upcoming project.
Before initiating the project, what should the project manager do?
A team has been working together for several months and has successfully
delivered work. A new team member has joined the team but is having difficulty
contributing.
What should the project manager do to help the new team member integrate effectively?
A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?
A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?
A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.
What should the project manager do to help the team and the customer?
A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.
What should the project manager do to manage this conflict?
A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?
A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.
What should the project manager do?
A product owner has provided the team with a prioritized backlog for the initial
launch of a new product. After analysis, the team concludes that some work is missing to
support the initial launch and provides this information to the product owner. The product
owner acknowledges the missing work and adds it to the bottom of the backlog. The team is
not happy with the prioritization that the missing work received.
What should the project manager do in this situation?
A large company has agreed on a business case for an environmental project. The
project will cause some major changes in their operations, such as reduction in paper use,
which will obviously affect all of the users.
What is the first thing the appointed project manager should do?
A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.
The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.
Match the stakeholders on the left with the appropriate frequency for updates.
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?
A project manager has been asked to participate in the procurement process for a
software application that allows customers to buy online e-learning courses. The project
manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?
A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.
How should the project manager proceed?
A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?
The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors
What should the project manager do?
A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.
At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.
How should the project manager ensure project success?
A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.
What should the project manager do?
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?
An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.
Which ceremony should be used in developing this register?
A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.
Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?
A contractor delivering construction services to a company is using agile principles
to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design
changes or performing rework.
What should the project manager do to minimize the cost?
At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.
What should have been done to avoid this situation?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.
What should the project manager do?
A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?
A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.
What should the new project manager do next?
A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.
What should the project manager do to prevent this frustration going forward?
A project manager is assigned to oversee the deployment of a new product that
will be used by the entire organization. A key success factor for the project is the timely
and successful adoption of the new solution by all entities.
What should the project manager do to ensure the success of this critical project?
In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.
After getting more information about the new manager, what is the project manager's next step?
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior''
A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is
frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.
What should the project manager do?
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager
do with many tasks still open on the Kanban board?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.
What should the project manager do next?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?
A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?
A product owner has an idea for a new product but is struggling to define the
features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?
A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?
In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement
How should the project manager respond to the suggestion?
A project manager is assigned to a new project. The project management office
(PMO) and the project manager agree that this is the right opportunity to include daily
standup meetings. The project team has never used such tools, and a few members are
challenging the decision.
What should the project manager do in this situation?
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
One of the service providers on a complex project has been facing resource
availability problems over the last six months. However, the service provider has assured the
project manager that the deliverables will be on time.
How should the project manager address this situation?
A project team is conducting a retrospective. The team wants to identify what had
a positive impact on the velocity and keep doing it.
Click on the area that the team should focus on to identify good practices.
A project management team received news that a competitor has released the
latest version of a program. What should the team do next?
A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.
What should the project manager tell the team members to focus on?
In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.
What should the project manager do to manage this conflict?
On a transformational project, the project manager is confronted with resistance
from the stakeholders. To overcome this and gain acceptance of the change, what should
the project manager do first?
A project needs to purchase a specific piece of equipment, as stated in the
project documents and approved by the project sponsor. The procurement division is
questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.
What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?
A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area
What should the project manager do first?
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.
What should the project manager do?
A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
A project team is struggling to meet the project deadline due to a reoccurring conflict between two team members. What should the project manager do?
A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.
What should the project manager do?
Generative artificial intelligence (AI) now helps produce documents on most projects across an organization and is yielding great benefits. Despite this change, a project manager notices that very few members of their current team know the AI tools available within the company. Consequently, they do not know how to use them effectively.
What should the project manager do?
A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.
Which action should the project manager take?
An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.
What should the project manager do first?
A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.
What should the new project manager do first?
A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.
What should the project manager of the contracting company do?
During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.
What should the project manager do to resolve this issue?
A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.
What should the project manager do?
A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.
What should the project manager do?
An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.
How should the project manager approach this situation?
A project manager is in the process of authoring the communications management plan for a new project. One of the project's stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.
What should the project manager do?
A project schedule's risk level continues to increase during project execution because sprints are consistently delivering less than the intended results. The project manager becomes concerned that the deliverable will be delayed and cost more than the project sponsor intended.
What should the project manager do first?
In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.
What should the project manager do first?
During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.
What should the project manager do?
A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?
During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.
What should the project manager ask the team to do next?
A project sponsor indicates that the time frame for a project needs to be shortened. The project network diagram cannot be modified, but there are extra resources available in the company.
What action should the project manager take?
The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable
What personality indicators should the project manager consider when determining what communication style to use with this team member?
A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?
A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.
What should the project manager do to address this concern?
A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.
What should the project manager do to manage such a situation for upcoming phases?
A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?
A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team
to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three)
A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically
last 45 minutes with many misunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
A project team is using an iterative and incremental delivery approach. The sprint's duration is 1 month with a production release every 3 months. In the last sprint review, the users communicated that they want the functionality presented and deployed in 5 weeks. The project lead is working on the next release plan.
When should the project lead have their team deploy the functionality?
As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?
A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.
What should the project manager do?
A project is impacting several business units with different expectations and priorities. The project manager leading this project is meeting every month with each of these groups individually. During these meetings, each group has expressed dissatisfaction with the project and uses every opportunity to replace other groups' priorities with their own.
What should the project manager do to address these challenges?
A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.
What should the project manager do to initiate the adoption of agile within the company?
A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.
What should the project manager do next?
A project team member who was a top performer in the planning phase of a project was easily irritated during the fifth sprint of the software development phase. The team member's attitude and behavior made the other team members feel uncomfortable.
What should the project manager do?
A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.
What should the project manager do to handle the scope change?
A project manager has been assigned to a new project. The project manager read the business case, charter, and statement of work (SOW) and scheduled a discussion with the sponsor about the scope, goals, and objectives. The project manager requested a meeting with the sponsor and the business analyst who performed the business case before setting up a kickoff meeting.
Why did the project manager request the meeting?
The team's velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.
What should the scrum master do first?
A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.
What should the project manager do?
Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.
How should the project manager approach the situation?
A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.
Which two actions should the project manager take first? (Choose 2)
A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.
What should the project manager do?
A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.
Which action should the project manager take to address this situation?
A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.
What should the project manager do?
A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.
What should the project manager do?
A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.
What should the project manager do to demonstrate the capabilities of a servant leader?
A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.
What should the project manager do?
A project manager coordinates several projects in one program. Each project concerns a different country, has a different sponsor, and has specific business priorities. The resources are shared among the projects. The project manager anticipates this could result in delays and/or conflicts that will affect the program outcomes.
What should the project manager do to prevent such a situation?
One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.
What should the project manager do?
A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?
A new project manager has been assigned to an ongoing project because of the promotion of their predecessor. The new project manager needs to understand the levels of decision-making authority on the team.
Which document should the incoming project manager review?
In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market
while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.
What should the project manager do to avoid a reoccurrence of this scenario?
A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.
What should the project manager do?
A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.
What should the project lead use for backlog refinement considering the sprints are 2 weeks long?
To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.
How should these issues be resolved?
A project's planning process is finished, and all resources were budgeted for and approved by senior management. Just before the kickoff meeting, a member of the production department realizes that the plan does not meet the requirements for their area.
What should the project manager have done during the planning process?
A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.
What should the project manager have done to avoid this situation?
Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.
What should the project manager do next?
A project manager is leading the development and delivery of a strategic product that must be delivered on time. The project is facing technical issues that could significantly impact the budget and ability to deliver some of the product features.
What should the project manager do first to resolve the issue?
A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.
How should the project manager respond?
During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?
A project team consists of several consultants from an external vendor. These consultants often change from month to month.
What should the project manager do to communicate the organizational values?
A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager's organization, the client organization, and the local community.
What should the project manager do after identifying the stakeholders?
A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner's preferred language; however, they are very skilled in the other language.
What should the project manager do?
During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager's influence, the project team is concerned about the overall impact to the project.
What should the project manager have done?
A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.
What should the project manager do first?
A multinational company is embarking on an ambitious organizational change project. The objectives of the project include the complete transformation of the organization's structure, role catalog, and global locations in which supporting services are to be delivered.
What should the project manager advise as an essential component of the project?
A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.
What should the project manager do first to manage the team's workload effectively?
A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.
What should the project manager do?
During a risk review meeting early in a project, the project team flags the possibility that a key team member might be away during the implementation of a key work package. Unfortunately, this team member is currently the only resource with the knowledge to perform this work, although it is possible someone else could do it with training.
What should the project manager do?
A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.
How should the project manager address this request?
A new offshore call center project is vital for a company's branch offices. The project is at the end of the planning phase when the project manager is informed by the sponsor that the project will be delayed due to reprioritization.
What should the project manager do?
A project manager has just been designated to lead an approved project with a virtual team. The team members are from several countries and have never met before.
In order to promote team engagement and introduce the project team, what should the project manager do?
A project manager was notified about a new regulatory requirement that could impact the project schedule.
What should the project manager do first?
A project manager is leading a highly visible project with a critical time constraint. Frequent scope changes have been well-managed with change control, but there have been misunderstandings among project team members.
What should the project manager do?
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?
During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.
What should the project lead do?
A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The
project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?
A project manager was assigned to lead a global project with a virtual team that is globally dispersed. The project manager has difficulties communicating with the team members and there seems to be frequent misunderstandings and conflicts.
What should the project manager do?
A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.
What should the project manager do?
A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.
What should the project manager do?
Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.
What should the project manager do?
A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide
any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?
A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.
How should the project manager respond?
A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.
Which tool should the project manager use for this purpose?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does
not have a requirement for it.
What should the project manager do?
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety
approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.
What should the project manager do?
A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?
During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager
react to ensure the project remains successful?
A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.
What should the project manager suggest?
A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional
managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.
What should the project manager do?
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?
An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery
What should the project lead do?
A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.
What should the project manager do next?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and
delay new feature development.
Which action should the project manager take to resolve the quality issues?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.
What should the project manager do?
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.
What should the project manager do next?
A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going
well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference
to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
What should the project manager recommend?
A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.
What should the project manager do?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?
A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.
What should the project manager do to manage this situation?
A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next ?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that
could become unmanageable with time. What should the project manager do?
An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the
project manager do to help improve the team's collaboration approach?
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the
project manager ensure that the needs of stakeholders are consistently met?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a
low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that
this could be a high risk for the project.
Which action should the project manager take?
A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.
What should the agile project manager do to engage the stakeholder in the project?
In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What
should the project lead do next?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.
How should the project manager handle this situation?
A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.
What should the project manager do first?
A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.
The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.
What should the project manager do?
A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The
procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.
How should the project manager approach this project?
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?
A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly
requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes
of a request. Both of them are equal in seniority and both report to the same functional manager.
How should the project manager proceed?
A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.
How should the project manager deal with this when planning the project?
A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.
What should the project manager do next?
After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project
manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team's work?
In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress
What should the project manager do first?
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.
What should the project manager do first?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.
What should the project manager do?
At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.
What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?
At the end of the last iteration, the customer rejects the deliverables since they did
not meet the customer's expectations. What should the project manager have been done
to prevent this situation?
A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager
expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project
manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to ensure project success?
A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.
What should the project manager do to address this issue?
An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.
Who should the project manager contact to help the team accelerate the delivery?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project
manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?
During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component
managed by an external vendor. How should the project manager address the team member's concern?
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.
This uncertainty from the junior engineers is now slowing progress.
‘What should the project manager do?
A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to
water. What should the project manager do next?
During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain
feedback from on project deliverables. What should the project manager do?
Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.
What should the project manager do?
A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager
discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The
remote team member feels they are not being adequately rewarded and recognized for their job.
What should the project manager do?
A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce
the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December
might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.
What should the project manager do about this risk?
During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do
next?
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall
progress.
What should the project manager do next?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings,
the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.
How should the project manager ensure that project risks are reported accurately in the risk register?
Project-Management-Professional | PMP Questions Answers | PMP Test Prep | Project Management Professional (2021 Version) Questions PDF | PMP Online Exam | PMP Practice Test | PMP PDF | PMP Test Questions | PMP Study Material | PMP Exam Preparation | PMP Valid Dumps | PMP Real Questions | Project-Management-Professional PMP Exam Questions