Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cramtick70

C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

What are the advantages of collective orders? Note: There are 2 correct answers to this question.

Options:

A.

To perform availability checks across the entire collective order

B.

To coordinate orders in the planning board for a collective order

C.

To show the flow of batches across the entire collective order

D.

To post confirmations for the entire collective order

Buy Now
Questions 5

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

Options:

A.

Post the goods receipt for the finished product.

B.

Reduce run schedule quantities.

C.

Post production costs to the planned order.

D.

Update statistics for the Business Information Warehouse.

E.

Create associated capacity requirements.

Buy Now
Questions 6

What is a work center hierarchy?

Options:

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel

Buy Now
Questions 7

During production order creation, several valid production versions are found. How does the system choose the production version?

Options:

A.

Alphanumeric or quota arrangement

B.

Planned order or material number

C.

Validity period or sales order

D.

Lot size or material cost

Buy Now
Questions 8

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

B.

MRP creates the capacity requirements without considering existing load on the work centers.

C.

MRP creates the capacity requirements at the earliest possible time.

D.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Buy Now
Questions 9

Which of the following processes lead to an entry in the MRP planning file? Note: There are 2 correct answers to this question.

Options:

A.

Changing the delivery address in transportation management

B.

Changing the storage bin in warehouse management

C.

Changing the procurement type in the product master

D.

Changing the stock in inventory management

Buy Now
Questions 10

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

Options:

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities.

C.

Alternative work centers are fully occupied.

D.

The Change Planning Direction indicator is set in the strategy profile.

Buy Now
Questions 11

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

Options:

A.

When several operations are maintained for one product

B.

When alternative resources are used within one operation

C.

When several production versions are maintained for one product

D.

When multiple planned orders are scheduled in parallel on one resource

Buy Now
Questions 12

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.

Options:

A.

Resource hierarchy

B.

Resource selection

C.

Resource matrix

D.

Resource network

Buy Now
Questions 13

How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By order confirmation

C.

By order release

D.

By mass processing

Buy Now
Questions 14

Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a resource group.

B.

Use a planning group.

C.

Use a propagation range.

D.

Use a planning area.

Buy Now
Questions 15

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Options:

A.

Assign the alert profile to the overall profile.

B.

Assign the overall profile to the authorization profile.

C.

Create an object selection variant for alerts according to the priority of ATP categories.

D.

Create an object selection variant for production-planning-related alerts.

Buy Now
Questions 16

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Wait time

B.

Float before production

C.

Processing time

D.

Pick time

E.

Setup time

Buy Now
Questions 17

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Options:

A.

Backflushing

B.

Kanban

C.

Material requirements planning

D.

Production order release

Buy Now
Questions 18

Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Variable-size item

B.

Work item

C.

Preliminary item

D.

WBS item

Buy Now
Questions 19

Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

Base unit of measure

B.

Industry sector

C.

Selection screen for views

D.

Product type

Buy Now
Questions 20

You are a consultant on an SAP S/4HANA Cloud Greenfield project. Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.

Options:

A.

Efficiency

B.

Accuracy

C.

Timeliness

D.

Stability

Buy Now
Questions 21

In your plant MRP is activated. Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

Options:

A.

Use a specific MRP list.

B.

Use a specific material status.

C.

Use a specific material group.

D.

Use a specific MRP type.

Buy Now
Questions 22

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.

Options:

A.

Planned delivery time

B.

Total replenishment lead time

C.

Operation duration

D.

In-house production time

Buy Now
Questions 23

Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

Options:

A.

The quantity and value updates are the same.

B.

The same batch management level is used.

C.

The same base unit of measure is used.

D.

The same account category is used.

Buy Now
Questions 24

What are the key features of using a low-level code? Note: There are 2 correct answers to this question.

Options:

A.

To determine the priority of alternative components inside ATP

B.

To determine how costs are rolled up by product costing

C.

To determine the sequence in which materials are planned in MRP

D.

To determine the use of sub-items inside material BOM (bill of material)

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Apr 30, 2025
Questions: 80
C_TS422_2023 pdf

C_TS422_2023 PDF

$25.5  $84.99
C_TS422_2023 Engine

C_TS422_2023 Testing Engine

$30  $99.99
C_TS422_2023 PDF + Engine

C_TS422_2023 PDF + Testing Engine

$40.5  $134.99